Consider the following statements:
In the bar chart planning
 1. Interdependence of the operations cannot be portrayed.
 2. Progress of work can be measured.
 3. Spare time of the activities can be determined.
 4. Schedule cannot be updated.
 Of these statements
(A) 1, 2 and 3 are correct
(B) 1 and 4 are correct
(C) 2, 3 and 4 are correct
(D) 1, 2 and 4 are correct

1 Answer

Answer :

(B) 1 and 4 are correct

Related questions

Description : A bar chart is commonly used because (a) It is simple to draw and easy to understand (b) It indicates at a glance the overall progress of the project (c) It shows critical ... critical activities (d) It incorporates uncertainties for delay in estimation of time required for completion of activities.

Last Answer : (a) It is simple to draw and easy to understand

Description : Which of the following is a weakness of bar chart? (A) Interdependencies of activities (B) Project progress (C) Uncertainties (D) All of the above

Last Answer : (D) All of the above

Description : Time and progress chart of a construction, is also known as (A) Bar chart (B) Gantt chart (C) Modified Mile stone chart (D) All the above

Last Answer : (D) All the above

Description : Which one of the following statements is not correct? A Since voltage depends on concentrations, using standard conditions makes it easier to compare different electrochemical reactions. B We have ... half-reactions are determined by combining the relevant half-cell with a standardised half-cell.

Last Answer : C The direction of a redox reaction can only be determined experimentally. 

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : Gantt chart (or Bar chart) is helpful in (A) Efficient utilisation of manpower and machines (B) Preparing production schedule (C) Efficient despatching of products (D) Inventory control

Last Answer : (B) Preparing production schedule

Description : Which one from the following is highly associated activity of project planning? (A) Keep track of the project progress. (B) Compare actual and planned progress and costs (C) Identify the activities, milestones and deliverables produced by a project (D) Both (B) and (C)

Last Answer : (C) Identify the activities, milestones and deliverables produced by a project

Description : Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to ... and 4 (B) 3, 4 and 5 (C) 1, 3 and 4 (D) 1, 2 and 5

Last Answer : (A) 1, 2 and 4

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is (A) 1 (B) 2 (C) 3 (D) 4

Last Answer : (A) 1

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : Which of Which of the following activ ng activities is not a direct responsi esponsibility of operati operations management? a. Planning Planning & controlling controlling the operations operations b ... operation operation d. Determining the exact mix of products & services that customers will want

Last Answer : d. Determining the exact mix of products & services that customers will want

Description : Consider a problem of preparing a schedule for a class of student. What type of problem is this? a) Search Problem b) Backtrack Problem c) CSP d) Planning Problem

Last Answer : c) CSP

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : A construction schedule is prepared after collecting (A) Number of operations (B) Output of labour (C) Output of machinery (D) All the above

Last Answer : (D) All the above

Description : Consider the following statements for priority queue: S1: It is a data structure in which the intrinsic ordering of the elements does determine the result of its basic operations. S2: The elements of a priority queue ... . (C) SI is incorrect and S2 is correct. (D) Both S1 and S2 are correct.

Last Answer : (D) Both S1 and S2 are correct.

Description : Consider the following operations performed on a stack of size 5: Push(a); Pop(); Push(b); Push(c); Pop(); Push(d); Pop(); Pop(); Push(e); Which of the following statements is correct? (A) Underflow occurs (B) Stack operations are performed smoothly (C) Overflow occurs (D) None of the above

Last Answer : (B) Stack operations are performed smoothly

Description : The auditor of financial statements must make very difficult interpretations regarding authoritative literature. Additionally, the auditor must a. Proceed beyond PFRS to assess how the economic activity is ... of the evidence d. Establish new criteria by which financial statements may be compared.

Last Answer : Proceed beyond PFRS to assess how the economic activity is portrayed in the financial statements

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : To determine the efficiency of an algorithm the time factor is measured by: (A) Counting micro seconds (B) Counting number of key operations (C) Counting number of statements (D) Counting kilobytes of algorithm

Last Answer : (B) Counting number of key operations

Description : What activities do you do on your spare time?

Last Answer : mostly I prefer to spend my spare time doing some small activities like drawing on learning new things related to innovations. and sometimes I prefer to spend my spare time with my family members. but when i am in a dull mood I will definitely try to watch comedy videos.

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is (A) 1, 2, 4, 3, 5 (B) 1, 3, 2, 4, 5 (C) 1, 2, 3, 4, 5 (D) 1, 3, 4, 2,

Last Answer : (C) 1, 2, 3, 4, 5

Description : The famous spare tire problem or Scheduling classes for bunch of students or Air cargo transport are the best example of ____________ a) Planning problem b) Partial Order planning problem c) Total order planning d) None of the mentioned

Last Answer : a) Planning problem

Description : Select the correct statement. . A) Contour interval on any map is kept constant. (B) Direct method of contouring is cheaper than indirect method. (C) Intervisibility of points on a contour map cannot be ascertained. (D) Slope of a hill cannot be determined with the help of contours.

Last Answer : (A) Contour interval on any map is kept constant.

Description : Strategic planning: (a) Addresses the organization's basic mission or business, issuing broad statements of purpose or direction that have a long lead time. (b) Involves managers in each unit of ... overall plans of the organization. (d) Determines the day-to-day operations within an organization.

Last Answer : (a) Addresses the organization's basic mission or business, issuing broad statements of purpose or direction that have a long lead time.

Description : Which of the following statements is a wrong statement under Value Chains ? A. Technology development is a support activity B. Marketing & Sales is a support activity C. Operations are ... Inputs into Final Product or Service D. Procurement is a support activity which deals with Vendors

Last Answer : Marketing & Sales is a support activity

Description : Which of these statements BEST describes international marketing ? 1. Developing and performing marketing activities across national boundaries 2. the exporting of goods and services 3. the creation ... . having firms with operations or subsidiaries located in many countries 5. none of these

Last Answer : Developing and performing marketing activities across national boundaries

Description : Which of these statements BEST describes international marketing? A)developing and performing marketing activities across national boundaries. B)the exporting of goods and services. C)the creation ... between countries. D)having firms with operations or subsidiaries located in many countries.

Last Answer : A)developing and performing marketing activities across national boundaries.

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Consider the following Statements: Indicative Planning is a feature of Mixed Economy'. Perspective Planning is used by socialist countries where each and every aspect of planning is controlled by the State. Which of the above Statement( ... B. B Only 2 C. C Both 1 and 2 D. D Neither 1 nor 2

Last Answer : A. A Only 1

Description : Consider the following salient points in a stress-strain curve of a mild steel bar: 1. Yield point 2. Braking point 3. Yield plateau 4 . Proportionality limit 5. Ultimate point The correct sequence in which they occur while testing the mild ... , 5 and 2 (c) 4, 1, 3, 5 and 2 (d) 1, 4, 2, 3 and 5

Last Answer : (c) 4, 1, 3, 5 and 2

Description : Economic progress of a country is determined by - (1) Increase in per capita income of people of country (2) Increase in the price of produced capital goods during the year (3) Increased numbers of Trade Unions (4) Fall in the general price level of a country

Last Answer : (1) Increase in per capita income of people of country Explanation: Economic progress of a country is determined by increase in per capita income of people f that country.

Description : Economic progress of a country is determined by (1) Increase in per capita income of people of country (2) Increase in the price of produced capital goods during the year (3) Increased numbers of Trade Unions (4) Fall in the general price level of a country

Last Answer : Increase in per capita income of people of country

Description : Routing in production, planning & control is concerned with the (A) Sequence of operation to be performed (B) Progress of work performed (C) Authorisation of work to be performed (D) Balancing of load on machines

Last Answer : (A) Sequence of operation to be performed

Description : A student who is mentally retarded, cannot follow your lecture and sit in a deaf and dumb manner, when you recognise him, what will you do? Options: A) Make your lecture very simple and spare some extra ... ) You attempt in such a manner that he leaves your class D) You do not support him at all

Last Answer : A) Make your lecture very simple and spare some extra time for him 

Description : Which one of the following statements is correct? (A) The function of an information system is to improve one s ability to make decisions (B) The information system is the chain of operations ... , analysed data, its stored information is suitability used in making decisions (D) All the above

Last Answer : Answer: Option D

Description : Is it time for a Declaration of Interdependence?

Last Answer : No. It's like the airline attendant coaches you. If the cabin pressure drops and the yellow mask comes down, the grownups have to use them first, otherwise nobody will be left to tend to the ... to take care of yourself (the Individual) first, otherwise there is no such thing as helping others.

Description : Which of the following statements would least likely appear in an auditor's engagement letter? a. Our engagement is subject to the risk that material errors, fraud, and defalcations, if they exist, ... services are based on our regular per diem rates, plus travel and other out-of-pocket expenses

Last Answer : After performing our preliminary analytical procedures we will discuss with you the other procedures we consider necessary to complete the engagement.

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : Explain the interdependence of all the three economic sectors giving examples from transportation system. -SST 10th

Last Answer : All the three sectors are highly interdependent on each other: (i) All that is produced in the primary sector is of no use until it undergoes a change into finished product which ... different places and require many other services. For all this we cannot think of working without transportation.

Description : What effect increasing economics interdependence have on the countries of the world?

Last Answer : Growing international trade and rising standards of living