If the Earned Value is equal to Actual Cost, it means:
A. Project is on budget and on schedule
B. Schedule Variance Index is 1
C. There is no schedule variance
D. There is no cost
variance
A. Project is on budget and on schedule
B. Schedule Variance Index is 1
C. There is no schedule variance
D. There is no cost
variance