Description : The BCWS = $250, the ACWP = $350, and the BCWP = $200. Calculate the Cost Variance. 1. -$150 2. $150 3. -$50 4. $50
Last Answer : 1. -$150
Description : Which of the following represents the estimated value of the work actually accomplished? A. Earned value (EV) B. Planned value (PV) C. Actual cost (AC D. Cost variance (CV)
Last Answer : A. Earned value (EV)
Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance
Last Answer : D. There is no cost variance
Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance
Last Answer : C. Management Contingency Reserve
Description : A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance
Last Answer : A. Cost Baseline
Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance
Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.
Last Answer : a. All variance to the project scope is evaluated.
Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000
Last Answer : d. $875,000
Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected
Description : Price movement between two Information Technology stocks would generally have a co-variance. A. zero B. positive C. negative
Last Answer : B. positive
Description : What Is Effort Variance?
Last Answer : Effort Variance = (Actual effort – Estimated Effort) / Estimated Effort.
Description : CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the project is complete? Select one: a. 80% b. 53% c. 45% d. 35% e. 75% Answer - a. 80% 39. As a project manager, John ... paid off the project. d. John's boss is happy. e. John and his team are promoted and get salary increases.
Last Answer : c. John’s client has paid off the project.
Description : Connecting MacBook to SV projector.
Last Answer : What output does your mac have? You’ll need a ____ out to S-Video cable.
Description : Are there any cases where an average value can be maximized only at the cost of increasing variance?
Last Answer : answer:Are you looking for real world examples? Assuming so You would probably like your income from work to be as high as possible, and would like to keep the value above a certain level where you ... does, since it's a much simpler set of rules if you can identify the likelihood of winning.
Description : During September, 300 labour hours were worked for a total cost of Rs 4800. The variable overhead expenditure variance was Rs 600 (A). Overheads are assumed to be related to direct labour hours of active working. What was the standard cost per labour hour? (a) Rs 14 (b) Rs 16.50 (c) Rs 17.50
Last Answer : (a) Rs 14
Description : During a period 17, 500 labour hours were worked at a standard cost of Rs 6.50 per hour. The labour efficiency variance was Rs 7,800 favourable. How many standard hours were produced? (a) 1,200 (b) 16,300 (c) 17,500 (d) 18,700
Last Answer : (d) 18,700
Description : Formula for calculating Material cost variance = ________ a) (SQ*SR) – (AQ* AR b) AQ (SP-AP) c) SP(SQ- RSQ) d) SP(SQ-AQ)
Last Answer : a) (SQ*SR) – (AQ* AR
Description : The formula used for calculation of labour rate variance is A. Total standard labour cost of actual output - Total actual cost of actual output B. (Standard rate per hour - Actual rate per hour) ... time - Actual time) * Standard rate per hour D. Abnormal idle hours * Standard hourly rate
Last Answer : B. (Standard rate per hour - Actual rate per hour) * Actual Hours
Description : The sub-variance of material usage variance, known as Material mix variance is measured as A. Total standard cost - Total actual cost B. Standard cost of revised standard mix - Standard cost of ... unit price) * Actual quantity used D. (Standard quantity - Actual quantity) * Unit standard price
Last Answer : B. Standard cost of revised standard mix - Standard cost of actual mix
Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer
Last Answer : (B) Features, Quality, Cost, Schedule, Staff
Description : Project performance consists of (A) Time (B) Cost (C) Quality (D) All of the above
Last Answer : (C) Quality
Description : Following is(are) the responsibility(ies) of the project manager. (A) Budgeting and cost control (B) Allocating resources (C) Tracking project expenditure
Last Answer : (C) Tracking project expenditure
Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)
Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).
Description : The main purpose of the Project Management Plan is to: a. provide justification for undertaking the project in terms of evaluating the benefit, cost and risk of alternative options. b. ensure ... the project. d. document the outcome of the risk, change and configuration management processes.
Last Answer : c. document the outcomes of the planning process and provide the reference document for managing the project.
Description : The justification for the investment to be made in a project is documented in the: a. Cost Breakdown Structure. b. procurement strategy. c. business case. d. Project Management Plan.
Last Answer : c. business case.
Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms
Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.
Description : . A project is typically defined in terms of scope, time, cost and which other parameter? a. Benefits. b. Quality. c. Tolerance. d. Controls.
Last Answer : b. Quality.
Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.
Last Answer : b. to deliver the project objectives to enable benefits to be realised.
Description : Which one of the following statements is true? a. An increase in project scope is likely to increase project cost. b. A decrease in the project time is likely to increase project quality. c. ... to decrease project cost. d. A decrease in the project cost is likely to decrease project time.
Last Answer : a. An increase in project scope is likely to increase project cost.
Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.
Last Answer : a. overall project duration.
Description : Sam Consultancy is planning to buy ten desktops for $1500 each from a leading computer store. Which type of contract will get signed in this case? A. Purchase Order B. Cost plus Fee C. Fixed cost D. Time and Material
Last Answer : A. Purchase Order
Description : Which of the following is not correct about initial phase of a project? a. The cost associated at the beginning of the project is highest. b. Stakeholders have maximum influence during this phase c. The highest uncertainty is at this stage of the project. d. All the above statements are correct.
Last Answer : a. The cost associated at the beginning of the project is highest.
Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above
Last Answer : D. all of the above
Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation
Last Answer : B. Project Monitoring and Control
Description : Which of the following is a form of trust that is built on the examination of the person’s motives and the conclusion that he or she is not hostile? Select one: a. Objective credibility b. Attribution of benevolence c. Non-manipulative trust d. Unequivocal liberality e. High cost of lying
Last Answer : b. Attribution of benevolence
Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit
Last Answer : e. quality audit
Description : Fill in the blanks. It is during the ______________ phase that the decision should be made regarding whether the project should continue. During this phase, ____________ must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk
Last Answer : e. initiation, risk
Description : Which of the following statements about flowcharts is true? Select one: a. Most flowcharts use one width of column to represent a category, while the vertical axis represents the ... used to identify trends. e. Flowcharting is useful for communicating responsibility for work processes.
Last Answer : e. Flowcharting is useful for communicating responsibility for work processes.
Description : Which of the following project baselines provides the basis for measurement of the expected cash flow against requirements over time and is often displayed as an S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline
Last Answer : b. Cost performance baseline
Description : Fill in the blank. The _____ is the difference between the additional money spent on prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis
Last Answer : c. cost of quality
Description : When a project manager starts to plan a new project budget, the cost of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning
Last Answer : d. Closing
Description : Which of the following is a personal characteristic that reflects the truthfulness of an individual that can be checked against observable facts? Select one: a. Objective credibility b. Attribution ... c. Non-manipulative trust d. High cost of lying e. Acknowledgment of munificence
Last Answer : a. Objective credibility
Description : Which of the following is a quality management system that gives titles to specialists and requires a cost-benefit analysis? Select one: a. Lean accounting b. Business process re-engineering c. Kaizen d. Six Sigma e. Total Quality Management
Last Answer : d. Six Sigma
Description : ___ should be made of all cost factors so as to reflect on all relevant investment and operational costs of the project including contingencies.
Last Answer : Ans. Realistic estimates
Description : The project manager works with the project sponsor to identify the necessary resources and team members needed to further develop the key project parameters – Cost, Scope, Schedule, and Quality (CSSQ). (True/False)
Last Answer : Ans. True
Description : Scope, cost, and schedule are some of the parameters used for project negotiation. (True/False)
Description : Algorithmic cost estimation in different organisations may be different for the same application development, because a) Different organisations consider complexity factors differently b) Different organisations may use ... measurement of productivity may vary e) All of the above may be true.
Last Answer : e) All of the above may be true.
Description : Internal costs include a) Developers salaries b) Managers and support personnel salaries c) The cost of overheads such as utilities, rent and senior managers d) Materials (such as manuals) and services such as travel e) All of the above.
Last Answer : a) Developers salaries