In a routine pile load test the test load is --
a) 1.25 times the design load
b) 1.5 times the design load*
c) 1.75 times the design load
d) 2 times the design load

1 Answer

Answer :

b) 1.5 times the design load*

Related questions

Description : In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net ... load should not exceed (A) 10 mm (B) 15 mm (C) 20 mm (D) 25 mm

Last Answer : Answer: Option D

Description : Peak hour demand of water is taken as ---------- times the average daily demand a)1.5 b)1.9 c)2.25* d)2.75

Last Answer : c)2.25*

Description : A temporary enclosure in a river or Lake built around a working area for the purpose of excluding water during construction is known a) Caisson b) Augur c) Cofferdam * d) Sheet pile wall

Last Answer : c) Cofferdam *

Description : centre to centre spacing of pile should not be more than __where d is the dia of pile shaft

Last Answer : 4d

Description : Bentonite is used in pile driving -- a) to facilitate pile driving b) to enable proper pile concreting c) to stabilize the bore hole walls* d) None of the above

Last Answer : c) to stabilize the bore hole walls*

Description : One of the following is a shallow foundation a) Pile foundation b) Raft foundation* c) Under reamed pile foundation d) Well foundation

Last Answer : b) Raft foundation*

Description : Speed restrictions is suggested for distressed bridges on Group II a) upto maximum of 15 kmph b) 25 kmph to 50 kmph* c) 75 kmph d) 60 kmph

Last Answer : b) 25 kmph to 50 kmph*

Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm

Last Answer : a) 25 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : RBG loading caters for maaaaximum axle load of…….tones for locomotive with trailing loadof…… tonnes/metre of track with maximum axle load of…….tonnes for wagons a)22.9,7.67,25 b)22.5,7.67,22.9* c)25,7.67,22.9, d)None of above

Last Answer : b)22.5,7.67,22.9*

Description : GML loading caters for maaaaximum axle load of…….tonnes for locomotive with trailing load of………tonnes/metre. a)22.9,7.67* b)22.5,7.67 c)25,7.67 d)None of above

Last Answer : a)22.9,7.67*

Description : Minm. deflection during transverse breaking load test is? (i) 5 mm (ii) 10 mm (iii) 15 mm* (iv) 20 mm

Last Answer : (iii) 15 mm*

Description : Min. breaking load of 60kg weld during transverse breaking load test is? (i) 110 MT (ii) 115 MT* (iii) 90 MT (iv) 120 MT

Last Answer : (ii) 115 MT*

Description : Min. breaking load of 52kg weld during transverse breaking load test is? (i) 90MT* (ii) 100 MT (iii) 110 MT (iv) 120 MT

Last Answer : (i) 90MT*

Description : The minimum pitch of rivets of diameter ‘d’ in steel plates shall be a) 2 x d b) 3 x d c) 1.75 x d d) 2.5 x d*

Last Answer : d) 2.5 x d*

Description : The wash hand basin shall be fixed at a height of (a) 75-80 cm* (b) 75 cm (c) 80 cm (d) Not specified

Last Answer : (a) 75-80 cm*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : he minimum compressive strength of first class brick should be a) 75 kg per centimeter square b) 90 kg per centimeter square c) 100 kg per centimeter square* d) 120 kg per centimeter square

Last Answer : c) 100 kg per centimeter square*

Description : Cross sectional area of catch water drain should not be more than a) 0 .75 square meter* b) 0. 90 square meter c) 0. 80 square meter d). 50 square meter

Last Answer : a) 0 .75 square meter*

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100* (d) 1 in 150

Last Answer : (c) 1 in 100*

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100 * (d) 1 in 150

Last Answer : (c) 1 in 100 *

Description : What is the width of Head of 52 kg Rail section a. 70 mm b. 75 mm c. 67 mm* d. 60 mm

Last Answer : c. 67 mm*

Description : For determining the ultimate bearing capacity of soil, the recommended size of a square bearing plate to be used in load plate test should be 30 to 75 cm square with a minimum thickness of (A) 5 mm (B) 10 mm (C) 15 mm (D) 25 mm

Last Answer : Answer: Option D

Description : eFor design of sewers for sullage, minimum velocity of ---- metres per second is taken. (a) 1.0 m sec* (b) 1.5 m/sec (c) 2.0 m/sec (d) 2.5 m/sec

Last Answer : (a) 1.0 m sec*

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : For achieving self-cleaning velocity, a minimum velocity of ---- mps. Is desirable for design peak flow (a) 0.6 mps (b) 0.8 mps* (c) 1.0 mps (d) 2.0 mps

Last Answer : b) 0.8 mps*

Description : A Railway Stations is provided for the following purpose (a) To entrain or detrain the passengers (b) To load or off load the goods or parcels (c) To enable the faster trains to overtake the slower trains (d) All the above*

Last Answer : d) All the above*

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder

Last Answer : c) semi-through type girder*

Description : The load transferred from rails to bottom flanges is in a) deck type girder b) through type girder* c) semi-through type girder d) plate girder

Last Answer : b) through type girder*

Description : Bearings are provided in bridges to transfer the load to a) Super structure b) Track c) Embankment d) Sub structure*

Last Answer : d) Sub structure*

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : The main drawback of centrifugal pump is a)necessity of priming b) discharge from pump varies with the load of water c) For high heads efficiency is low up to 50% d) the suction lift is limited to 6 metre e) all of the above*

Last Answer : e) all of the above*

Description : For new lines, width of formation in bank for N.G single line is (a) 3.35 m (b) 3.70 m* (c ) 5.25 m (e) 5.85 m

Last Answer : b) 3.70 m*

Description : For new lines, width of formation in cutting for N.G. single line is (a) 3.35 m* (b) 3.70 m (c) 5.25 m (d) 5.85 m

Last Answer : a) 3.35 m*

Description : For new lines, width of formation in bank for M.G. single line is (a) 5.25 m (b) 5.85 m* (c ) 6.25 m (e) 6.85 m

Last Answer : (b) 5.85 m*

Description : For new lines, width of formation in cutting for M.G. single line is (a) 5.25 m* (b) 5.85 m (c) 6.25 m (d) 6.85 m

Last Answer : (a) 5.25 m*

Description : Formation width for cuttings for B.G. single line section is (a) 5.40 m (b) 6.20 m (c) 6.25 m* (d) 6.50 m

Last Answer : (c) 6.25 m*

Description : ormal size of brick used in India is a) 22 x 11.2 x 7 cm* b) 25 x 16 x 8 cm c) 19 x 12 x 9 cm d) 20 x 10 x 5 cm

Last Answer : a) 22 x 11.2 x 7 cm*

Description : In guniting/ shotcreting , water cement ratio is kept as a) 0.4 to 0.5 b) 0.3 to 0.4 c) 0.25 to 0.35 d) 0.35 to 0.5*

Last Answer : d) 0.35 to 0.5*

Description : In cement pressure grouting, water cement ratio is kept as a) 0.4 to 0.5* b) 0.3 to 0.4 c) 0.25 to 0.35 d) 0.35 to 0.5

Last Answer : a) 0.4 to 0.5*

Description : Permissible speed of Turnout with 1 in 8.5 curved switches a. 40 kmph b. 25 kmph* c. 15 kmph d. 20 kmph

Last Answer : b. 25 kmph*

Description : For high level flush the nominal dia of flush pipe shall be (a) 32 mm* (b) 40 mm (c) 25 mm (d) None of these

Last Answer : a) 32 mm*

Description : The frequency of a wave travelling at a speed of 500 ms-1 is 25 Hz. Its time period will be ______. (i) 20 s (ii) 0.05 s (iii) 25 s (iv) 0.04 s

Last Answer : (iv) 0.04 s

Description : What is the time of removal the tensor from the newly executed A T Weld? (i) 15 minutes after pouring. (ii) 20 minutes after pouring* (iii) 25 minutes after pouring. (iv) 30 minutes after pouring.

Last Answer : (ii) 20 minutes after pouring*

Description : Thickness of Lining/Charge is kept? (i) 20 mm. (ii) 25 mm* (iii) 30 mm (iv) As decided by the site supervisor

Last Answer : (ii) 25 mm*

Description : After AT Welding First train is to be passed after ? (i) 20 Minutes from pouring of weld metal. (ii) 35 Minutes from pouring of weld metal. (iii) 30 Minutes from pouring of weld metal.* (iv) 25 Minutes from pouring of weld metal.

Last Answer : (iii) 30 Minutes from pouring of weld metal.*

Description : The depth of frog in a brick is a) 15 mm b) 10 mm c) 6. 25 mm* d) 3 mm

Last Answer : c) 6. 25 mm*

Description : arthwork in embankment for railway with manual compaction should be done in layers not exceeding-------------- a) 15 centimeter b) 20 centimeters c) 25 centimeters d) 30 centimeters*

Last Answer : d) 30 centimeters*

Description : The concrete under water minimum grade of cement recommended by IS code a) M 10 b) M 15 c) M 20* d) M 25

Last Answer : c) M 20*

Description : The total number of bridges on I.R.is about a)1 Lac b)1.25 Lacs* c)1.50 Lacs d)2 Lacs

Last Answer : b)1.25 Lacs*