Peak hour demand of water is taken as ---------- times the average daily demand  a)1.5   b)1.9   c)2.25*   d)2.75

1 Answer

Answer :

c)2.25*

Related questions

Description : In a routine pile load test the test load is -- a) 1.25 times the design load b) 1.5 times the design load* c) 1.75 times the design load d) 2 times the design load

Last Answer : b) 1.5 times the design load*

Description : Speed restrictions is suggested for distressed bridges on Group II a) upto maximum of 15 kmph b) 25 kmph to 50 kmph* c) 75 kmph d) 60 kmph

Last Answer : b) 25 kmph to 50 kmph*

Description : The level of guard rail in bridges shall not be lower than that of running rail by more than a) 25 mm* b) 55 mm c) 75 mm d) 65 mm

Last Answer : a) 25 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : Demand of water for passengers on railway station is a)10 litres per passenger b)15 litres per passenger c) 20 litres for passenger d) 25 litres per passenger*

Last Answer : d) 25 litres per passenger*

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : For achieving self-cleaning velocity, a minimum velocity of ---- mps. Is desirable for design peak flow (a) 0.6 mps (b) 0.8 mps* (c) 1.0 mps (d) 2.0 mps

Last Answer : b) 0.8 mps*

Description : ormal size of brick used in India is a) 22 x 11.2 x 7 cm* b) 25 x 16 x 8 cm c) 19 x 12 x 9 cm d) 20 x 10 x 5 cm

Last Answer : a) 22 x 11.2 x 7 cm*

Description : RBG loading caters for maaaaximum axle load of…….tones for locomotive with trailing loadof…… tonnes/metre of track with maximum axle load of…….tonnes for wagons a)22.9,7.67,25 b)22.5,7.67,22.9* c)25,7.67,22.9, d)None of above

Last Answer : b)22.5,7.67,22.9*

Description : GML loading caters for maaaaximum axle load of…….tonnes for locomotive with trailing load of………tonnes/metre. a)22.9,7.67* b)22.5,7.67 c)25,7.67 d)None of above

Last Answer : a)22.9,7.67*

Description : A certain company employed 600 men and 400 women and the average wage was 2.55 per hour.If a women got 50 paise less than a man, what were their wages per hour ? (a) Man rs 3.00,Woman Rs 2.50 (b) Man Rs 3.50, Woman Rs 3.00 (c) Man Rs 2.75, Woman Rs 2.25 (d) Man Rs 3.25, Woman Rs 2.75

Last Answer : Man = Rs 2.75, woman = Rs 2.25

Description : Which of the following agents and dosage regimens is the best choice of treatment for an asthma patient with rheumatoid arthritis who is considered sensitive to aspirin (experiences bronchospasm with use)? ... once a week (d) Azathioprine, 75 mg daily (e) Cyclophosphamide, 100 mg daily

Last Answer : Ans: C

Description : Cross sectional area of catch water drain should not be more than a) 0 .75 square meter* b) 0. 90 square meter c) 0. 80 square meter d). 50 square meter

Last Answer : a) 0 .75 square meter*

Description : The minimum pitch of rivets of diameter ‘d’ in steel plates shall be a) 2 x d b) 3 x d c) 1.75 x d d) 2.5 x d*

Last Answer : d) 2.5 x d*

Description : The wash hand basin shall be fixed at a height of (a) 75-80 cm* (b) 75 cm (c) 80 cm (d) Not specified

Last Answer : (a) 75-80 cm*

Description : Minimum traffic block required for execution of AT Weld ? (i) 70 minutes (ii) 70-75 minute.* (iii) 60 mints (iv) 1 hrs and 30 mints

Last Answer : (ii) 70-75 minute.*

Description : he minimum compressive strength of first class brick should be a) 75 kg per centimeter square b) 90 kg per centimeter square c) 100 kg per centimeter square* d) 120 kg per centimeter square

Last Answer : c) 100 kg per centimeter square*

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100* (d) 1 in 150

Last Answer : (c) 1 in 100*

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100 * (d) 1 in 150

Last Answer : (c) 1 in 100 *

Description : What is the width of Head of 52 kg Rail section a. 70 mm b. 75 mm c. 67 mm* d. 60 mm

Last Answer : c. 67 mm*

Description : An intense rain is falling at a uniform rate of 7.5 cm/hour for a period of 60 minutes on a basin whose area is 500 hectares. If the average infiltration capacity during the entire rain period is assumed to be 1.5 ... of the basin, is (A) 40 cumecs (B) 60 cumecs (C) 80 cumecs (D) 100 cumecs

Last Answer : Answer: Option C

Description : The peak of a 4 hour flood hydrograph is 240 m3 /sec. If the rainfall excess is 80 mm and base flow which is constant is 40 m3 /sec, peak of 4hours unit hydrograph will be (A) 20 m3 /sec (B) 25 m3 /sec (C) 30 m3 /sec (D) 35 m3 /sec

Last Answer : Answer: Option B

Description : Biochemical Oxygen Demand (BOD) of sewage is the (a) Oxygen required to oxidise (b) Oxygen required to oxidise biologically inactive organic matter* (c) a and b both (d) none of these

Last Answer : (b) Oxygen required to oxidise biologically inactive organic matter*

Description : Busy hour traffic is the (A) maximum average simultaneous traffic. (B) traffic during peak hour. (C) traffic when all subscribers are engaged. (D) the duration of maximum calls.

Last Answer : (B) traffic during peak hour.

Description : Ajay reads at an average rate of 30 pages per hour, while Vikram reads at an average rate of 40 pages per hour. If Ajay starts reading a novel at 4:30 PM and Vikram begins reading an identical copy of the same book at 5:20 PM, at ... same page? a) 7:50 PM b) 8:15 PM c) 8:40 PM d) 9:00 PM e) 9:25 PM

Last Answer : Ajay reads at average rate of 30 pages per hour ie. 1 page in every two minutes. Therefore, by 5:20 PM, he would have covered 25 pages By 6:20 PM, Ajay would have read 25+30 pages and Vikram would have ... and he will also finish 100 pages Hence, both of them will be on same page at 7:50 Answer: a)

Description : eFor design of sewers for sullage, minimum velocity of ---- metres per second is taken. (a) 1.0 m sec* (b) 1.5 m/sec (c) 2.0 m/sec (d) 2.5 m/sec

Last Answer : (a) 1.0 m sec*

Description : In guniting/ shotcreting , water cement ratio is kept as a) 0.4 to 0.5 b) 0.3 to 0.4 c) 0.25 to 0.35 d) 0.35 to 0.5*

Last Answer : d) 0.35 to 0.5*

Description : In cement pressure grouting, water cement ratio is kept as a) 0.4 to 0.5* b) 0.3 to 0.4 c) 0.25 to 0.35 d) 0.35 to 0.5

Last Answer : a) 0.4 to 0.5*

Description : According to Godrich the ratio of peak demand rate to mean demand is  (A) Max. weekly demand/Average weekly demand = 148%  (B) Max. monthly demand/Average monthly demand = 128%  (C) Max. half yearly demand/Average half yearly demand = 107%  (D) All the above 

Last Answer : (D) All the above 

Description : The regimen(s) used for postcoital emergency contraception is/are: A. Levonorgestrel 0.5 mg + ethinylestradiol 0.1 mg taken twice 12 hour apart B. Levonorgestrel 0.75 mg taken twice 12 hour apart C. Mifepristone 600 mg single dose D. All of the abov

Last Answer : D. All of the abov

Description : Dumpy level is most suitable when (a) The instrument is to be shifted frequently (b) Fly leveling is being done over long distance (c) Many readings are to be taken from a single setting of the instrument* (d) All of the above

Last Answer : (c) Many readings are to be taken from a single setting of the instrument*

Description : hat action to be taken if slag is not separated within 20 ± 3 seconds? (i) Tap inside. (ii) Tap outside * (iii) Good reaction (iv) Tap well in time

Last Answer : ii) Tap outside *

Description : Renewal of loose rivet shall be taken up in end bearing stiffener when the % of hammer loose rivet is

Last Answer : 30%

Description : While finalizing the IRBM, which of the following have been taken into account. a) Indian RailwaysGeneral Rules 1976 b) Indian Railways Code for Engineering Department 1993 c) Bridge Rules and Substructure d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : For Box Culverts Danger level is to be taken as a) at the top of slab b)one third height below bottom of slab c) at the bottom of slab* d) None of the above

Last Answer : c) at the bottom of slab*

Description : Cement pressure grouting is suitable for a) Very fine crack b) weathered concrete c) Active crack where cause of crack is known and remedial action has been taken* d) Crushed masonry

Last Answer : c) Active crack where cause of crack is known and remedial action has been taken

Description : From distribution main of 50 mm size, number of service pipes of 15 mm size can be taken off are ------ a) 6 b)10 c) 12 e):20*

Last Answer : e):20*

Description : From the distribution main of 40 mm size, number of service pipe of 20 mm size can be taken off are ------- a)3 B) 6* c) 10 d) 12

Last Answer : B) 6*

Description : From distribution main of 40 mm size , number of service pipe of 15 mm size can be taken off are--------- a) 3 b) 6 c) 10 d) 12*

Last Answer : d) 12*

Description : An accident has taken place at out station and main line is blocked and relief train is to be turned out without medical car. The hooter shall be: a. 3 long b. 4 long* c. 4 long, 1 short d. 3 long, and 1 short

Last Answer : b. 4 long

Description : Of the four numbers, the first is twice the second, the second is one-third of the third and the third is 5 times the fourth. The average of the numbers is 24.75. The largest of these numbers is: A.45 B.25 C.30 D.45 E.None of these

Last Answer : Answer – D (45) Explanation – Let the fourth number be a then hen, third number = 5a, second number= 5a/3 and first=10a/3 a+ 5a+ 5a/3 + 10/3 = 24.75 x 4 so,a=9 So, the numbers are 9, 45, 15 and 30

Description : The concrete under water minimum grade of cement recommended by IS code a) M 10 b) M 15 c) M 20* d) M 25

Last Answer : c) M 20*

Description : For new lines, width of formation in bank for N.G single line is (a) 3.35 m (b) 3.70 m* (c ) 5.25 m (e) 5.85 m

Last Answer : b) 3.70 m*

Description : For new lines, width of formation in cutting for N.G. single line is (a) 3.35 m* (b) 3.70 m (c) 5.25 m (d) 5.85 m

Last Answer : a) 3.35 m*

Description : For new lines, width of formation in bank for M.G. single line is (a) 5.25 m (b) 5.85 m* (c ) 6.25 m (e) 6.85 m

Last Answer : (b) 5.85 m*

Description : For new lines, width of formation in cutting for M.G. single line is (a) 5.25 m* (b) 5.85 m (c) 6.25 m (d) 6.85 m

Last Answer : (a) 5.25 m*

Description : Formation width for cuttings for B.G. single line section is (a) 5.40 m (b) 6.20 m (c) 6.25 m* (d) 6.50 m

Last Answer : (c) 6.25 m*

Description : Permissible speed of Turnout with 1 in 8.5 curved switches a. 40 kmph b. 25 kmph* c. 15 kmph d. 20 kmph

Last Answer : b. 25 kmph*

Description : The maximum shear stress (qmax) in a rectangular beam is (A) 1.25 times the average (B) 1.50 times the average (C) 1.75 times the average (D) 2.0 times the average

Last Answer : Answer: Option B