In M+7 sleeper density, how many sleepers are there in a km Track. a. 1660 nos
b. 1540 nos.*
c. 1310 nos.
d. 1440 nos.

1 Answer

Answer :

b. 1540 nos

Related questions

Description : Number of sleepers required having sleeper density of M+7 for one Km of BG single line is (a) 1360 (b) 1540* (c) 1660 (d) None of the above

Last Answer : (b) 1540*

Description : Sleeper density for group ‘A’ route with traffic density more than 20 GMT is:- (a) 1560 sleepers/ Km. (b) 1660 sleepers/ Km.* (c) 1540 sleepers/ Km. (d) 1340 sleepers/ Km.

Last Answer : (b) 1660 sleepers/ Km.*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Number of Elastic clips used for one K to BG single line section having 13 length & concrete sleepers of M+7 sleeper density are (a) 5280 (b) 6160* (c) 6250 (d) 6500

Last Answer : (b) 6160*

Description : “Composite sleeper index” is employed to determine a) sleeper density requirement b) number of fixtures required for a particular type of sleeper c) durability of sleeper d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Last Answer : d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : Min. sleeper density in case of semi permanent diversion- (a) (m + 2) (b) (m + 3)* (c) (m + 4) (d) ( m + 7 )

Last Answer : (b) (m + 3)*

Description : 1. Which of the statements with regard to formation is correct (1) One of the Functions of the formation is to facilitate drainage (2) Width of bank for double railway line is 12.155 meters (3) Width of cutting for double railway track is 11. ... a) 2, 3, 5 b) 3, 4, 5* c) 2, 3, 4 d) 2, 4, 5

Last Answer : b) 3, 4, 5*

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : The G.T. road from Lahore to Calcutta in undivided India, was constructed during (A) 3495-3500 BC (B) 265-270 BC (C) 1540-1545 AD (D) 1440-1450 AD

Last Answer : Answer: Option C

Description : Minimum length of steel channel sleeper in BG a) 2500mm b) 2440mm* c) 2400mm d) 2600mm

Last Answer : b) 2440mm*

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : How many sleepers are there in Fan shaped 1 in 12 turnout a. 85 sleepers b. 96 sleepers* c. 90 sleepers d. 100 sleepers

Last Answer : b. 96 sleepers*

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : For taking track measurement at accident site stations shall be marked at …….. Apart. (a) 1 m (b) 2m (c) 3m* (d) 5m

Last Answer : (c) 3m*

Description : Permissible creep in track is m. 50 mm n. 100 mm o. 125 mm p. 150 mm.*

Last Answer : p. 150 mm.*

Description : The number of standard rails (13 m) for one km. BG section single line section is (a) 120 (b) 154* (c) 168 (d) 196

Last Answer : (b) 154*

Description : On an unmanned level crossing stop board should be provided at a distance of --------- from the centre of nearest track a) 5 meters * b) 6 meters c) 3 meters d) 7.5 meters

Last Answer : a) 5 meters

Description : RBG loading caters for maaaaximum axle load of…….tones for locomotive with trailing loadof…… tonnes/metre of track with maximum axle load of…….tonnes for wagons a)22.9,7.67,25 b)22.5,7.67,22.9* c)25,7.67,22.9, d)None of above

Last Answer : b)22.5,7.67,22.9*

Description : what is the value of long chord for measuring unevenness in track recording a. 3.6 meter b. 9.6 meter* c. 7.2 meter d. 4.8 mete

Last Answer : b. 9.6 meter*

Description : The ruling gradient is 1 in 200 on a section of the BG track. If the track is laid in that place at a curve of 5 degrees then the allowable ruling gradient on the curve will be a) 1 in 16.7 b) 1 and 400 c) 1 in 240 d) 1 in 333*

Last Answer : d) 1 in 333*

Description : It takes 60 sec for a train running at 162 km/hr to cross a bridge. And it takes 36 sec for the same speed to cross a boy walking at the rate of 18km/hr in the same direction in which the train is ... the train and length of the platform. A) 1440 &1260m B) 1220 &60m C) 1000 & 1460m D) 1260 &1450m

Last Answer : ANSWER: A  Explanation:  Relative speed of the train to man = (162 - 18)  = 144km/hr  Convert km/hr into m/s  144km/hr = (144 * 5 /18) m/s  = 40 m/s  When the train passes ... of bridge = 2700  length of bridge = 1260 m  the length of the bridge & train are 1260 and 1440m

Description : The weight of the rails depends upon A. Gauge of track B. Speed of train C. Spacing of Sleepers D. All the above

Last Answer : D [All the above] Explanation: Indian Railways is divided into 18 zones. Recently added South Coast Railway zones in Indian Railway (2019).

Description : How many detonators are planted during protection of track for welding site ? (i) One (ii) Two (iii) Three* (iv) None of the above

Last Answer : iii) Three*

Description : Weather protection of track is required during block for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : For laying a Railway track the prepared surface ready to receive the ballast is called a) Sub ballast b) Formation* c) Blanket d) Cushion

Last Answer : b) Formation*

Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.

Last Answer : c) Duty hut should be on the outside of the curve.*

Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.

Last Answer : c) Level crossing should not fall within the breathing length of LWR*

Description : Stop boards on either side of approaches of all unmanned level crossings shall be provided at -------------from the centre line of nearest track. a) 3meters b) 5 meters* c) 6 meters d) 10 meters

Last Answer : b) 5 meters*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : Minimum distance of duty hut from centre line of nearest track on BG is a) 2 meters b) 3 meters c) 4 meters d) 6 meters*

Last Answer : d) 6 meters*

Description : Minimum distance of gate post from centre line of nearest track on BG is a) 2 meters b) 3 meters* c) 4 meters d) 5 meters

Last Answer : b) 3 meters*

Description : TVU is abbreviated for a) Track vulnerable unit b) Train vehicle unit * c) Total vehicle unit d) Traffic variation unit

Last Answer : b) Train vehicle unit *

Description : Length of guard rails to be bent so as to be brought together at the middle of the track.(L2) a) 3200 mm b) 4875 mm* c) 3655 mm d) None of the above

Last Answer : b) 4875 mm*

Description : Facia boards of platform shelters shall have a minimum horizontal clearance of ……. from C.L. of track at a minimum height of 4.61m above RL. a) 2360 mm b) 3660 mm c) 3000 mm d) 1600 mm*

Last Answer : d) 1600 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : Wing walls and return walls are provided to retain a) earth on approaches b) ballast c) track on approaches d) none

Last Answer : a) earth on approaches

Description : Bearings are provided in bridges to transfer the load to a) Super structure b) Track c) Embankment d) Sub structure*

Last Answer : d) Sub structure*

Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier

Last Answer : a) C.L. of water course/road to C.L. of track*

Description : Skew of a bridge is the angle between a) C.L. of water course to C.L. of track b) C.L. of water course to C.L. of pier c) C.L. of water course/road to normal (perpendicular) of C.L. of track* d) C.L. of abutment to C.L. of pier

Last Answer : c) C.L. of water course/road to normal (perpendicular) of C.L. of track*

Description : The minimum track centres in B.G. double line is (a) 4500 mm (b) 4750 mm (c) 5000 mm (d) 5300 mm*

Last Answer : (d) 5300 mm*

Description : The minimum horizontal distances form centre of track to face of passenger platform coping for B.G. is ……. Mm (A) 1650 MM. (B) 1670 MM* (C)1676 MM (D) 1685 MM

Last Answer : (B) 1670 MM*