Number of Elastic clips used for one K to BG single line section having 13 length &
concrete sleepers of M+7 sleeper density are
(a) 5280
(b) 6160*
(c) 6250
(d) 6500

1 Answer

Answer :

(b) 6160*

Related questions

Description : Number of sleepers required having sleeper density of M+7 for one Km of BG single line is (a) 1360 (b) 1540* (c) 1660 (d) None of the above

Last Answer : (b) 1540*

Description : In M+7 sleeper density, how many sleepers are there in a km Track. a. 1660 nos b. 1540 nos.* c. 1310 nos. d. 1440 nos.

Last Answer : b. 1540 nos

Description : The recommended width of Single line formation cutting for BG excluding drain is a) 6250 mm* b) 6850mm c) 54 90mm d) 6100mm

Last Answer : a) 6250 mm*

Description : The number of standard rails (13 m) for one km. BG section single line section is (a) 120 (b) 154* (c) 168 (d) 196

Last Answer : (b) 154*

Description : “Composite sleeper index” is employed to determine a) sleeper density requirement b) number of fixtures required for a particular type of sleeper c) durability of sleeper d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Last Answer : d) mechanical strength of wooden sleepers and thereby gives its suitability as to be used as li sleepers.*

Description : Sleeper density for group ‘A’ route with traffic density more than 20 GMT is:- (a) 1560 sleepers/ Km. (b) 1660 sleepers/ Km.* (c) 1540 sleepers/ Km. (d) 1340 sleepers/ Km.

Last Answer : (b) 1660 sleepers/ Km.*

Description : Minimum length of steel channel sleeper in BG a) 2500mm b) 2440mm* c) 2400mm d) 2600mm

Last Answer : b) 2440mm*

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Min. sleeper density in case of semi permanent diversion- (a) (m + 2) (b) (m + 3)* (c) (m + 4) (d) ( m + 7 )

Last Answer : (b) (m + 3)*

Description : 1. Which of the statements with regard to formation is correct (1) One of the Functions of the formation is to facilitate drainage (2) Width of bank for double railway line is 12.155 meters (3) Width of cutting for double railway track is 11. ... a) 2, 3, 5 b) 3, 4, 5* c) 2, 3, 4 d) 2, 4, 5

Last Answer : b) 3, 4, 5*

Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board

Last Answer : c) Start of the bridge/work spot*

Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m

Last Answer : b) 1200 m*

Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.

Last Answer : c) Duty hut should be on the outside of the curve.*

Description : The ruling gradient is 1 in 200 on a section of the BG track. If the track is laid in that place at a curve of 5 degrees then the allowable ruling gradient on the curve will be a) 1 in 16.7 b) 1 and 400 c) 1 in 240 d) 1 in 333*

Last Answer : d) 1 in 333*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : The minimum vertical clearance above R.L. to bottom of ROB near the yard shall be a) 6525 mm* b) 5870 mm c) 2360 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : The vertical clearance of bottom most foot over bridge structure above rail level is a) 6525 mm* b) 3660 mm c) 5330 mm d) 6250 mm

Last Answer : a) 6525 mm*

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : Formation width for banks for B.G. single line section is (a) 6.10 m (b) 6.50 m (c) 6.85 m* (d) 7.0 m

Last Answer : (c) 6.85 m*

Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.

Last Answer : c) Level crossing should not fall within the breathing length of LWR*

Description : The train runs faster on BG than on MG rail because its speed is directly proportional to a) Weight of the train* b) Gauge width c)Policy of Railway Board d) Length of the train

Last Answer : a) Weight of the train*

Description : Height of Low level platform for passengers for BG is --- high (a) 0.455 m* (b) 0.560 m (c) 0.650 m (d) 0.760 m

Last Answer : (a) 0.455 m*

Description : Height of high level platform for passengers for BG is --- high (a) 0.455 m (b) 0.560 m (c) 0.650 m (d) 0.760 m*

Last Answer : (d) 0.760 m*

Description : Minimum distance of duty hut from centre line of nearest track on BG is a) 2 meters b) 3 meters c) 4 meters d) 6 meters*

Last Answer : d) 6 meters*

Description : Minimum distance of gate post from centre line of nearest track on BG is a) 2 meters b) 3 meters* c) 4 meters d) 5 meters

Last Answer : b) 3 meters*

Description : For protection of level crossing gate in an emergency on BG double line the Gateman should place one detonator at one place and 3 detonators at a subsequent place at a distance of ------- a) and------ ... c) 500 meters and 1000 meters d) 600 meters and 1200 meters* e) 800 meters in 1500 meters

Last Answer : d) 600 meters and 1200 meters*

Description : Formation width for cuttings for B.G. single line section is (a) 5.40 m (b) 6.20 m (c) 6.25 m* (d) 6.50 m

Last Answer : (c) 6.25 m*

Description : How many nos. of sleepers should be loosened either side of the proposed weld? (i) 3 sleepers (ii) 5 sleepers.* (iii) 2 sleepers (iv) 4 sleepers

Last Answer : (ii) 5 sleepers.

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : How many sleepers are there in Fan shaped 1 in 12 turnout a. 85 sleepers b. 96 sleepers* c. 90 sleepers d. 100 sleepers

Last Answer : b. 96 sleepers*

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : Gauge conversion means: (a) Converting MG to BG (b) Converting NG to MG (c) Converting NG to BG (d) Converting MG/NG to BG*

Last Answer : (d) Converting MG/NG to BG*

Description : The minimum and maximum clearances of check rails at all BG level crossings shall be a) 51 to 57 mm* b) 44 to 48 mm c) 41 to 45 mm d) 55 to 70 mm

Last Answer : a) 51 to 57 mm*

Description : Indication post for detonator should be provided at a distance of ---------meter and --------- meter for BG level crossing a) 400 meters in 800 meters b) 500 meters and 1200 meters c) 600 meters and 1200 meter * d)600 meters and 1000 meters

Last Answer : c) 600 meters and 1200 meter *

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : For A Class, the gross clearance of over maximum moving dimension for BG is (a) 100mm (b) 125mm (c) 150mm* (d) 175mm

Last Answer : (c) 150mm*

Description : Maximum width of rolling stock on BG should be (a) 4745mm (b) 3250mm* (c) 3450mm (d) 4140mm

Last Answer : (b) 3250mm*

Description : Maximum height of rolling stock on BG should be (a) 2745mm (b) 3250mm (c) 3450mm (d) 4140mm*

Last Answer : (d) 4140mm*

Description : What is maximum height above rail level for low-level passenger platform for BG? (a) 300mm (b) 455mm* (c) 525mm (d) 550mm

Last Answer : (b) 455mm

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100* (d) 1 in 150

Last Answer : (c) 1 in 100*

Description : In a semi permanent (BG) diversion the gradient should not be steeper then (a) 1 in 75 (b) 1 in 125 (c) 1 in 100 * (d) 1 in 150

Last Answer : (c) 1 in 100 *

Description : What do you mean by BG a. Big Gauge b. Broad Gauge* c. Buffer gauge d. None of above

Last Answer : b. Broad Gauge*

Description : Longest platform of the world on BG is a) At Sonepur station* b) At Sasaram station c) At Allahabad station d) At Kharagpur station

Last Answer : a) At Sonepur station*

Description : Addition gain of 10 db is used for testing. (i) ‘D’ marked rails on single lines. (ii) ‘D’ marked rails on double lines. (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.* (iv) None of above.

Last Answer : (iii) Testing on single line and ‘D’ marked rails on double/multiple lines section.*