Track structure for CC+8 t+ 2 t loaded trains is:-
(a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast.
(b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*
(c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast.
(d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

1 Answer

Answer :

b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Related questions

Description : Sleeper density for group ‘A’ route with traffic density more than 20 GMT is:- (a) 1560 sleepers/ Km. (b) 1660 sleepers/ Km.* (c) 1540 sleepers/ Km. (d) 1340 sleepers/ Km.

Last Answer : (b) 1660 sleepers/ Km.*

Description : In M+7 sleeper density, how many sleepers are there in a km Track. a. 1660 nos b. 1540 nos.* c. 1310 nos. d. 1440 nos.

Last Answer : b. 1540 nos

Description : Number of sleepers required having sleeper density of M+7 for one Km of BG single line is (a) 1360 (b) 1540* (c) 1660 (d) None of the above

Last Answer : (b) 1540*

Description : Minimum rail section recommended for section having traffic more than 20 GMT is (a) 90 UTS (b) 52 Kg. (c) 60 Kg.* (d) None of the above.

Last Answer : (c) 60 Kg.

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : Service life in terms of total GMT carried for 52 kg. 90 UTS rail is:- (a) 425 GMT (b) 475 GMT (c) 525 GMT* (d) 545 GMT

Last Answer : (c) 525 GMT*

Description : What is the assessed GMT service life of 52 kg 90 UTS rail. a. 650 GMT b. 600 GMT c. 525 GMT* d. 500 GMT

Last Answer : c. 525 GMT*

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : What is the assessed GMT service life of 60 kg 90 UTS rail? a. 650 GMT b. 600 GMT c. 800 GMT* d. 500 GMT

Last Answer : c. 800 GMT*

Description : To take care of differential cooling rail ends of 72 UTS rails are lifted by? (i) 1 to 1.5 mm (ii) 1 to 2 mm (iii) 2 to 2.5 mm (iv) 3 to 4 mm *

Last Answer : iv) 3 to 4 mm *

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : To take care of differential cooling rail ends of 90 UTS rails are lifted by? (i) 1 mm (ii) 2 mm (iii) 2 to 2.2 mm.* (iv) 1 to 2 mm

Last Answer : (iii) 2 to 2.2 mm.*

Description : Permitted wind velocity for running of trains on the bridge a) 72 km/h* b) 58 km/h c) 64 km/h d) No limits

Last Answer : a) 72 km/h*

Description : What is the difference between rail flange of 60 kg & 52 rail section a. 20 mm b. 18 mm c. 14 mm* d. 16 mm

Last Answer : c. 14 mm

Description : What is the width of Head of 52 kg Rail section a. 70 mm b. 75 mm c. 67 mm* d. 60 mm

Last Answer : c. 67 mm*

Description : 65- Grade of 72 UTS rail is? (i) 880 (ii) 1080 (iii) 710* (iv) None of above

Last Answer : (iii) 710*

Description : The colour of bag containing Portion for 72 UTS ? (i) Pink (ii) Green (iii) Red * (iv) Black

Last Answer : (iii) Red *

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : Service life of CMS crossing ( 52 Kg rail) is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT. (d) 150 GMT.*

Last Answer : (d) 150 GMT.*

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*

Description : For laying a Railway track the prepared surface ready to receive the ballast is called a) Sub ballast b) Formation* c) Blanket d) Cushion

Last Answer : b) Formation*

Description : Wing walls and return walls are provided to retain a) earth on approaches b) ballast c) track on approaches d) none

Last Answer : a) earth on approaches

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Clear distance between consecutive sleepers not to exceed on bridges in BG is a) 450 mm* b) 600 mm c) 510 mm d) 500 mm

Last Answer : a) 450 mm*

Description : Grade of 90 UTS rail is? (i) 880* (ii) 1080 (iii) 710 (iv) None of above

Last Answer : i) 880*

Description : he colour of bag containing Portion for 90 UTS ? (i) Red (ii) Green * (iii) Pink (iv) Black

Last Answer : ii) Green *

Description : How many sleepers are there in Fan shaped 1 in 12 turnout a. 85 sleepers b. 96 sleepers* c. 90 sleepers d. 100 sleepers

Last Answer : b. 96 sleepers*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : Service life of improved SEJ of 60 Kg rail is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT.* (d) 150 GMT.

Last Answer : (c) 200 GMT.

Description : Service life of Glued insulated rail joint of 60 Kg rail is:- (a) 300 GMT. (b) 200 GMT.* (c) 400 GMT. (d) 150 GMT.

Last Answer : (b) 200 GMT.

Description : What is the height of 60 kg rail section? a. 180 mm b. 172 mm* c. 185 mm d. 165 mm

Last Answer : b. 172 mm*

Description : Two trains are moving in opposite directions at 60 km/hr and 90 km/hr. Their lengths are 1.10 km and 0.9 km respectively. The time taken by the slower train to cross the faster train in seconds is: A.58 sec B.50 sec C.48 sec D.56 sec E.None of these

Last Answer : Answer – C (48 sec) Explanation – Relative speed = all lengths/time [60+90] = [1.10 +0.9 ]/time [ PLUS when opposite direction] time=2/150 = 1/75 h 1 hour______3600 sec 1/75 hr______? ?= 3600/75=48 sec

Description : What is the limit of Unevenness of A category of track a. 0 to 10 mm b. 0 to 5 mm c. 0 to 6 mm* d. 0 to 8 mm

Last Answer : c. 0 to 6 mm

Description : The average speed of a train is 1 3/7 times the average speed of a car. The car covers a distance of 616 km in 8 hours. How much distance will the train cover in 13 hours? a) 1340 km b) 1423 km c) 1430 km d) 1936 km e) None of these

Last Answer : speed of the car = 616/8 = 77km/hr speed of the train = 10/7 × 77 = 110 km/hr Distance covered by train = 110 × 13 = 1430 km. Answer: c)

Description : If digital DRT is calibrated for 300 mm longitudinal wave using 00 double crystal probe then 60kg rail ---------peak will appear at (i) 5.2 (ii) 5.7* (iii) 7.8 (iv) 8.6

Last Answer : ii) 5.7*

Description : Maximum distance covered in a day by a Patrolman should not normally exceed q. 2 km. r. 5 km. s. 10 km. t. 20 km .*

Last Answer : t. 20 km

Description : The combined mass of car and passengers travelling at 72 km/hr is 1500 kg. Find the kinetic energy of this combined mass. (Formula: K =mv2 / 2k )  a. 300 kJ  b. 200 kJ  c. 500 kJ  d. None of the above

Last Answer : 300 kJ

Description : PSC is the abbreviation of…

Last Answer : Prestressed Concrete

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : riodicity of recording of camber in PSC girders a) Once in a year* b) Once in two years c) Once in three years d) During the detailed inspection of SE/Br.

Last Answer : a) Once in a year*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : Periodical inspection of PSC & Composite girders a) Once in 3 years b) Once in 5 years * c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 5 years *

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : What is the app. Weight of 52 kg portion? (i) 10 kg (ii) 11 kg* (iii) 12 kg (iv) None of the above

Last Answer : (ii) 11 kg*

Description : Standard bag of cement in ……… kg a) 52 kg b) 30.5kg c) 10.7kg d) 50 kg*

Last Answer : d) 50 kg*

Description : 32 kmph 11.What is the weight per meter length of 52 kg Rail? a. 54.14 kg b. 50.25 kg c. 51.89 kg* d. 53.85 kg

Last Answer : c. 51.89 kg*

Description : Flat rate parcel rates Flat Rate Parcel Boxes size Dimension of boxes (in mm) Weight (in Kg.) Tariff (in Rs.) Small - S 250*50*300 0 to 1 125 Medium - M 250*100*300 Above 1 to 2.5 200 Large - L 300*250*200 Above 2.5 to 5 400

Last Answer : Large - L 300*250*200 Above 2.5 to 5 400