The constraints in case of resource smoothening operation would be
(A) Resources
(B) Project duration time
(C) Both resources and project duration time
(D) None of the above

1 Answer

Answer :

(B) Project duration time

Related questions

Description : The process of incorporating changes and rescheduling or replanning is called (A) Resource levelling (B) Resource smoothening (C) Updating (D) Critical path scheduling

Last Answer : (C) Updating

Description : In resources levelling (A) Total duration of project is reduced (B) Total duration of project is increased (C) Uniform demand of resources is achieved (D) Cost of project is controlled

Last Answer : C

Description : Which one of the following is the objective in crashing? (a) Reduction in duration (b) Reduction in resources (c) Reduction in cost (d) Reduction in project size

Last Answer : (c) Reduction in cost

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : Which of these is not one of the constraints of a project? A. Scope B. Resources C. Team D. Budget

Last Answer : C. Team

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : In resource allocation, the resources are allocated to a project in  order that the…...............are attained a. Goals b. Objectives c. Both a, b d. None of the above

Last Answer : c. Both a, b

Description : 42. _____ assumption means the prior knowledge of all the coefficients in the objective function , the coefficients of the constraints and the resource values a. Proportionality b. Certainty c. Finite choices d. Continuity

Last Answer : b. Certainty

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : Feasibility study determines -----------------  A.Whether the project is possible with resources  B.Comparing the project with world class manufacturing norms C.Calculate the cost crashing each unit  D.Add duration to each unit

Last Answer : A.Whether the project is possible with resources

Description : Harrow is secondary tillage implement used to cut soil to shallow depth for _ and A) smoothening. C) none of the above B) pulverizing. D) both

Last Answer : both 

Description : 56. Constraints in LP problem are called active if they a. Represent optimal solutions b. At optimality do not consume all the available resources c. Both a & b d. None of the above

Last Answer : a. Represent optimal solutions

Description : 53. While plotting constraints on a graph paper, terminal points on both the axes are connected by straight line because a. The resources are limited in supply b. The objective function as a linear function c. The constraints are linear equations or inequalities d. All of the above

Last Answer : c. The constraints are linear equations or inequalities

Description : Constraints in an LPP are treated as active, if they: a. Do not consume all the available resources at optimality b. Represent optimal solution c. Both a and b d. None of these

Last Answer : b. Represent optimal solution

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : )Resource leveling attempts to : 1. Reduce resource requirements by smoothing out period-to period resource assignments.  2. Ensure that the budget abnormalities are overcome. 3. Reduce the ... Increase the amount of the project manager's authority so that budget dollars can be  appropriated.

Last Answer : 1. Reduce resource requirements by smoothing out period-to period resource assignments.

Description : A Solution to overcome the challenge to support a large number of application service consumers from around the world, cloud infrastructure providers (i.e., IaaS providers) have established data ... ) Global exchange of cloud resources b) Resource provisioning c) Cloud security d) Resource sharing

Last Answer : Global exchange of cloud resources

Description : The assignment problem a. Requires that only one activity be assigned to each resource b. Is a special case of transportation problem c. Can be used to maximize resources d. All of the above

Last Answer : d. All of the above

Description : Software feasibility is based on which of the following (A) business and marketing concerns (B) scope, constraints, market (C) technology, finance, time, resources (D) technical prowess of the developers

Last Answer : (C) technology, finance, time, resources

Description : A pipe is defined as 'hydraulically smooth', if the friction factor (A) Is not a function of Reynolds number (B) For a given Reynolds number remains constant even on further smoothening of the pipe (C) Is zero irrespective of the Reynolds number (D) None of these

Last Answer : (B) For a given Reynolds number remains constant even on further smoothening of the pipe

Description : For a given Reynolds number, in a hydraulically smooth pipe, further smoothening __________ the friction factor. (A) Brings about no further reduction of (B) Increases (C) Decreases (D) None of these

Last Answer : (A) Brings about no further reduction of

Description : It is a wooden plank used for smoothening the soil and crushing the weed. a. Spring tooth harrow b. Acme tooth harrow d. None of the above

Last Answer : Ans - c. Patela

Description : Harrow is a tillage implement that cuts the soil to shallow depth for smoothening and pulverizing the soil as well as to cut weeds and to mix the materials with the soil. a. Primary. c. Tertiary b. Secondary. d. None

Last Answer : Secondary

Description : The basic function of air dryer in a compressor is: a. prevent dust from entering compressor b. storage and smoothening pulsating air output c. reduce the temperature of the air before it enters the next state to increase efficiency d. to remove remaining traces of moisture after after-cooler 

Last Answer : d. to remove remaining traces of moisture after after-cooler 

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : Deciding how much testing is enough should take into account:- i. Level of Risk including Technical and Business product and project risk ii. Project constraints such as time and budget iii. Size of Testing Team iv. Size ... ii are true and iii, iv are false d) ii, iii, iv are true and i is false

Last Answer : c) i, ii are true and iii, iv are false

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : According to the Project Management Institute (PMI), the scope statement should  address all of the following issues EXCEPT: Select one: a. project constraints. b. project assumptions c. project ... d. code of conduct for the team members working on the project. e. project deliverables.

Last Answer : d. code of conduct for the team members working on the project.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : Your company has asked you to be the project manager for the product introduction  of its new DeskTop Rock media system. You recently published the project scope  statement. Which ... . Constraints  B. Project specifications  C. Requested changes D. Project configuration management requirements

Last Answer : C. Requested changes

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : In simplex method, we add .......................... in the case of constraints with sign “=” a. Surplus variable b. Artificial variable c. Slack variable d. None of these

Last Answer : b. Artificial variable

Description : The resource-based perspective suggests that unique firm resources should be the starting point for developing successful strategies a) the business opportunity should be the starting point for ... nor unique firm resources should be the starting point for developing successful strategies.

Last Answer : unique firm resources should be the starting point for developing successful strategies.

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : While a proclamation of emergency is in operation the duration of the Lok Sabha can be extended for a period - (1) not exceeding three months (2) not exceedng nine-months (3) of one year at a time (4) of two years at a time

Last Answer : (3) of one year at a time Explanation: While a proclamation of emergency is in operation, this period may be extended by Parliament by law for a period not exceeding one year at a time. Under ... when the security of India or part of it is threatened by war or external aggression or armed rebellion.

Description : Which one of the following statements is incorrect ? (A) Pareto analysis is a statistical method used for analyzing causes, and is one of the primary tools for quality management. (B) Reliability of ... (D) In white-box testing, the test cases are decided from the specifications or the requirements.

Last Answer : (D) In white-box testing, the test cases are decided from the specifications or the requirements.

Description : Developing software __________ means a major commitment of time, money and resources. a) In-house b) In-sync c) On-date d) On-duration

Last Answer : Answer: a Explanation: Developing software in-house means the same. It is easier to carry out changes in the software if it is developed in-house

Description : Draw and explain integrated duration curve used in system operation. 

Last Answer : Diagram of integrated duration curve used in system operation: Explanation:  Integrated duration curve is obtained from load duration curve. It is drawn in between load on Y-axis in KW/MW and the X- ... a particular time of a day can also be shown on a curve which is called as mass curve. 

Description : The required resources for communication between end systems are reserved for the duration of the session between end systems in ________ method. a) Packet switching b) Circuit switching c) Line switching d) Frequency switching

Last Answer : b) Circuit switching

Description : Which of the following is a core management feature offered by most cloud management service products? a) Support of different cloud types b) Creation and provisioning of different types of cloud ... and uptime, response time, resource quota usage, and other characteristics d) All of the mentioned

Last Answer : All of the mentioned

Description : Match the following. i) Mutual exclusion a) A process may hold allocated resources while waiting assignment. ii) Hold and wait b) No resource can be forcibly removed from a process holding it. iii) No preemption c) Only one process may use ... , ii-c, iii-b C) i-b, ii-c, iii-a D) i-c, ii-a, iii-b

Last Answer : D) i-c, ii-a, iii-b

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : Define the term ‘Resource’. Do you think that resources are free gifts of nature? Support your argument. -Geography

Last Answer : Everything available in our environment which can be used to satisfy our needs, provided it is technologically accessible and economically feasible and culturally acceptable can be termed as ... of resources. They transform material available in our environment into resources and use them.

Description : Define the term ‘Resource’. Do you think that resources are free gifts of nature? Support your argument. -SST 10th

Last Answer : Everything available in our environment which can be used to satisfy our needs, provided it is technologically accessible and economically feasible and culturally acceptable can be termed as ... of resources. They transform material available in our environment into resources and use them.

Description : Which among the following is not a problem of resource development? (a) Depletion of resources for satisfying

Last Answer : Which among the following is not a problem of resource development? (a) Depletion of resources for ... . (d) An equitable distribution of resources.

Description : If you would like to see a list of resources and the tasks that people are assigned to.  What view best displays this information?  A.Resource Sheet  B. Task Usage  C. Gantt Chart  D.: Resource Usage

Last Answer : C. Gantt Chart