Which one of the following is the objective in crashing?
(a) Reduction in duration (b) Reduction in resources
(c) Reduction in cost (d) Reduction in project size

1 Answer

Answer :

(c) Reduction in cost

Related questions

Description : Feasibility study determines -----------------  A.Whether the project is possible with resources  B.Comparing the project with world class manufacturing norms C.Calculate the cost crashing each unit  D.Add duration to each unit

Last Answer : A.Whether the project is possible with resources

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : In resources levelling (A) Total duration of project is reduced (B) Total duration of project is increased (C) Uniform demand of resources is achieved (D) Cost of project is controlled

Last Answer : C

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : The constraints in case of resource smoothening operation would be (A) Resources (B) Project duration time (C) Both resources and project duration time (D) None of the above

Last Answer : (B) Project duration time

Description : In Project crashing, rent and overheads are treated as  A.Significant Cost  B.Insignificant costs  C.Direct Costs  D.Indirect Costs

Last Answer : D.Indirect Costs

Description : In project crashing, as we systematically, crash the project, direct cost of project ______ a. Increases b. Decreases c. Remain same d. None of the above

Last Answer : a. Increases

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : The reduction in project time normally results in (A) Decreasing the direct cost and increasing indirect cost (B) Increasing the direct cost and decreasing the indirect cost (C) Increasing the direct cost and indirect cost both (D) Decreasing the direct cost and indirect cost both

Last Answer : (B) Increasing the direct cost and decreasing the indirect cost

Description : Which of these is not an objective of Cost Accounting? (a) Ascertainment of Cost (b) Determination of Selling Price (c) Cost Control and Cost reduction (d) Assisting Shareholders in decision making

Last Answer : (d) Assisting Shareholders in decision making

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : Economic saving of time results by crashing (A) Cheapest critical activity (B) Cheapest noncritical activity (C) Costliest critical activity (D) Costliest noncritical activity

Last Answer : (A) Cheapest critical activity

Description : Scheduling can best be defined as the process used to determine: a. overall project duration. b. project cost estimating. c. the project management plan. d. sub-contractor’s responsibilities.

Last Answer : a. overall project duration.

Description : During project estimation, project manager estimates following A. project cost B. project duration C. project effort D. all of the above

Last Answer : D. all of the above

Description : In Project Management, the end users and developers require to know the a. cost of the project, b. duration c. Length d. All the above

Last Answer : d. All the above

Description : Scheduling can best be defined as the process used to determine:  a. overall project duration.  b. project cost estimating.  c. the project management plan.

Last Answer : a. overall project duration.

Description : What is the overall objective of internal auditing? a. To attest to the efficiency with which resources are used. b. Ascertain that the cost of internal control is justified. c. To ... and stockholders' equity. d. To help members of the organization to effectively discharge their responsibilities.

Last Answer : To help members of the organization to effectively discharge their responsibilities.

Description : Addition of pyrazinamide and ethambutol for the first two months to the isoniazid + rifampin therapy of tuberculosis serves the following purpose(s): A. Reduces the total duration of therapy to 6 months B. ... sputum conversion C. Permits reduction of rifampin dose D. Both A' and B' are correct

Last Answer : D. Both ‘A’ and ‘B’ are correc

Description : Developing software __________ means a major commitment of time, money and resources. a) In-house b) In-sync c) On-date d) On-duration

Last Answer : Answer: a Explanation: Developing software in-house means the same. It is easier to carry out changes in the software if it is developed in-house

Description : The required resources for communication between end systems are reserved for the duration of the session between end systems in ________ method. a) Packet switching b) Circuit switching c) Line switching d) Frequency switching

Last Answer : b) Circuit switching

Description : Select the FALSE statement about an inventory system. A)The objective of minimum total inventory cost must be balanced against a customer service level necessary to maximise profits. B)EOQ is ... of stockouts. D)Inventory carrying costs usually increase as the level of customer service increases.

Last Answer : B)EOQ is the size of inventory that minimises only the cost of carrying inventory.

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : A software company needs to develop a project that is estimated as 1000 function points and is planning to use JAVA as the programming language whose approximate lines of code per function point is accepted as 50. Considering a=1. ... ? (1) 11.2 months (2) 12.2 months (3) 13.2 months (4) 10.2 months

Last Answer : Generally, any projects are measured in weeks. However, the complex project might take more time depending on the level of object re-use available.

Description : The overall objective of forensic auditing is to a. Attest to the efficiency with which resources are employed b. Assist members of the organization in the effective discharge of their ... in legal and financial disputes d. Provide assurance that financial data have been accurately recorded

Last Answer : Unearth the truth and provide evidence in legal and financial disputes

Description : The overall objective of internal auditing is to a. Attest to the efficiency with which resources are employed. b. Ascertain that controls are costs justified. c. Provide assurance ... accurately recorded. d. Assist members of the organization in the effective discharge of their responsibilities

Last Answer : Assist members of the organization in the effective discharge of their responsibilities

Description : 53. While plotting constraints on a graph paper, terminal points on both the axes are connected by straight line because a. The resources are limited in supply b. The objective function as a linear function c. The constraints are linear equations or inequalities d. All of the above

Last Answer : c. The constraints are linear equations or inequalities

Description : . Non-negativity condition in an LP model implies a. A positive coefficient of variables in objective function b. A positive coefficient of variables in any constraint c. Non-negative value of resources d. None of the above

Last Answer : d. None of the Above

Description : 37. Which of the following is not a characteristics of the LP a. Resources must be limited b. Only one objective function c. Parameters value remains constant during the planning period d. The problem must be of minimization type

Last Answer : d. The problem must be of minimization type

Description : 35. Which of the following is not a characteristic of the L P model a. Alternative courses of actions b. An objective function of maximization type c. Limited amount of resources d. Non-negativity condition on the value of decision variable

Last Answer : b. An objective function of maximization type

Description : 29. A constraint in an LP model restricts a. Value of objective function b. Value of a decision variable c. Use of the available resources d. All of the above

Last Answer : d. All of the above

Description : A constraint in a Linear Programming Model restricts: a. Value of objective function b. Value of decision variable c. Use of available resources d. All of the above

Last Answer : d. All of the above

Description : Is the apology by that conservative that murdered a protester by crashing into her with his car, genuine, or is he putting up an act?

Last Answer : Impossible to say. Now that his mentally ill little dream world has collapsed it is possible he may feel genuine remorse for it. Only he knows for sure. He was also not a conservative, he was a neo-Nazi.

Description : Were you to put a series of parachutes on an aeroplane, how big would they have to be to give a crashing plane a survivable landing?

Last Answer : What kind of plane are we talking about?

Description : Any ideas, or even direct knowledge, of why Google Chrome keeps crashing on my Windows 7 pro computer?

Last Answer : Here use the Google Crash repair page. You should be able to use the steps to get to the solution.

Description : What mechanics allow these birds to swarm without crashing into each other?

Last Answer : answer:Starling flocks have no leader. Each bird in the flock obeys a few simple rules: Stick with your own kind, maintain your personal space envelope (tight to each side, but roomier in ... flock can initiate a change in direction, and the whole flock will respond just by following these rules.

Description : What is the terminal velocity of the moon crashing into Earth?

Last Answer : answer:The Newtonian equation is F = G x (m1.m2)/r^2. It's hard to write equations on here, so see http://en.wikipedia.org/wiki/Newton's_law_of_universal_gravitation if that is unclear. ... mass of both objects, the gravitational force between the Earth and the Moon is dependent on both masses.

Description : Crashing while racing do you believe the driver has any chance to think he/she won’t survive it?

Last Answer : answer:Yes to both. I've never raced on a track, but I love driving and have been in a couple accidents. The time my car rolled over, I was upside-down and said Holy Fuck and started ... families, and that makes it even harder to live with knowing that your actions led to their injury or death.

Description : How many people would board an airplane that has a 10% risk of crashing?

Last Answer : answer:You're creating a false issue here. Getting on a plane with a 10% chance of crashing is immediate. You get on a plane and you might die. That's an entirely different type of thing ... is unlikely to make serious changes. The bottom line is that your comparison simply doesn't hold water.

Description : Is it time to develop a crashing satellite defense system for the whole Earth?

Last Answer : Either that or each new satellite could maybe have self-destruction capability or thrust feature where it could maneuver itself to be captured by Earth’s gravity then plunge into an ocean or a desert.

Description : Why is my Firefox freezing/crashing so often?

Last Answer : answer:Try disabling all of your plug-ins. Then add them one-by-one after using it to identify the problem plug-in. Or move to Chrome, which is better :)