Additional time which a non-critical activity can consume without increasing the project
duration is called _____________.
A. Total Float.
B. Free Float
C. Independent Float.
D. Dependant Float

1 Answer

Answer :

A. Total Float.

Related questions

Description : _____________ is used to accomplish the project economically in the minimum available time with limited resources A. Project Scheduling. B. Network Analysis. C. Budget Analysis. D. Critical Planning.

Last Answer : A. Project Scheduling.

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : _____________ refers to some action which is a time consuming effort necessary to complete a specific event. A. A Network. B. An Activity. C. An Event. D. A Node.

Last Answer : B. An Activity.

Description : _____________ can be defined as a specifically evolved work plan densed to achieve a specific objective within a specific period of time A. Idea generation. B. Opportunity Scanning. C. Project. D. Strategy.

Last Answer : C. Project.

Description : _____________ is primarily concerned with the identification, qualification and evaluation of the project resources. A. Techno-economic analysis. B. Feasibility analysis. C. Input analysis. D. Financial analysis.

Last Answer : B.Feasibility analysis.

Description : _____________ may be defined as the excess of present value of project cash inflows over that of out flows. A. Net present value technique. B. Average rate of return. C. Benefit-Cost ratio. D. Internal rate of return

Last Answer : A. Net present value technique.

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : ____________ is a graphical representation of the various activity and event relating to a project. A. Network analysis. B. Scheduling technique. C. Logical Model. D. Network Diagram

Last Answer : D. Network Diagram

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : When a firm enters into some business which is related with its present business in terms of technology, marketing or both it is called as _____________. A. conglomerate diversification. B. horizontal integration. C. vertical integration. D. concentric integration.

Last Answer : D. concentric integration.

Description : An individual who starts, creates and manages a new business can be called _____________. A. A leader B. A manager C. A professional D. An entrepreneur

Last Answer : D. An entrepreneur

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : NABARD is a Bank for _____________ development A. Urban B. Agricultural and Rural C. Scientific D. Agriculture and research

Last Answer : B. Agricultural and Rural

Description : Swot Analysis is a _____________ tool A. Conceptual B. Modern C. Scientific D. Traditional

Last Answer : A. Conceptual

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : Today, many companies are using managerial techniques that are designed to encourage _________. A. increasing profits B. legal compliances C. Ethical behaviour D. shareholders value

Last Answer : C. Ethical behaviour

Description : A commercial banker would prefer a ____________ debt-equity ratio over the years as it indicates financial strength of a unit. A. Declining. B. Increasing. C. Stable. D. Fluctuating.

Last Answer : A. Declining A commercial banker would prefer a declining debt-equity ratio over the years as it indicates the financial strength of a unit. A declining debt-equity ratio means that the company ... fluctuating ratio might indicate that the company is not able to manage its debt and equity properly.

Description : An entrepreneurship primary motivation for starting a business isa) To make money b) To be independent c) To be famous d) To be powerful

Last Answer : b) To be independent

Description : Which could provide an individual with the motivation to start a new business venture? A. The financial rewards. B. A desire to be independent. C. Risk taking D. All the above.

Last Answer : D. All the above.

Description : The activity which occurs when the new venture is started is called - a) Motivation b) Business skills c) Departure point d) Goal orientation

Last Answer : c) Departure point

Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP

Last Answer : A. CPM

Description : Which of the following factors should not be included in PESTLE analysis? A. Government re-cycling policy. B. Proposed reduction in interest rates. C. Competitor activity. D. Demographic changes.

Last Answer : C. Competitor activity.

Description : The process of preparing an inventory of skills needed for effective implementation of the project is called as ____________. A. Economic viability. B. Financial feasibility. C. Technical feasibility. D. Managerial competence.

Last Answer : D. Managerial competence.

Description : Underestimation of project cost leads to ___________. A. Time under run. B. Cost under run C. Time over run. D. Cost over run

Last Answer : D. Cost over run

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : ______________ describes the direction, the enterprise is going in, what its goals are, where it wants to be,and how it is going to get there. A. project report B. technical anlaysis C. market analysis D. financial analysis

Last Answer : A. project report

Description : Every entrepreneur should draw an _______ for his project to ensure the timely completion of all activities involved in setting up an enterprise. A. cost structure B. implementation plan C. market structure D. production structure

Last Answer : B. implementation plan

Description : market potential of the project report includes ________. A. demand and supply conditions B. market strategy C. after sales service D. all the above

Last Answer : D. all the above

Description : what are the components of then project report ________. A. requirement of funds B. location C. manpower D. all the above

Last Answer : All

Description : Project mission and objectives, procedures and systems used, and organization resources used typically appear in the _____ section of the final project report. A. Analysis B. Recommendation C. lessons learned D. financial feasibility

Last Answer : A. Analysis

Description : Integration of project management with the organization takes place with the _______________. A. master budjet B. strategic plan C. Process of managing actual projects D. both b and c

Last Answer : D. both b and c

Description : Project management is ideally suited for a business environment requiring all of the following except _________. A. Flexibility B. Innovation C. speed D. Repetability

Last Answer : A. Flexibility

Description : Which of the following is not considered to be a characteristic of a project? A. An established objective B. Complex tasks C. A clear beginning and end D. Only for internal use

Last Answer : D. Only for internal use

Description : The minimum amount of------------------,irrespective of such private participation,could be specified at a minimum 17.5 per cent of project costs by lending institutions. A. bank loans B. promotors contribution C. fixed capital D. working capital

Last Answer : B. promotors contribution

Description : ____________, which is included in the project cost, is estimated on the basis of the year when the enterprise breaks even. A. working capital B. cost of capital C. cost of production D. cost of equity

Last Answer : A. working capital

Description : A project, which may not add to the existing profits, should be financed by _________ A. debentures. B. preference share capital. C. equity capital. D. public deposits.

Last Answer : A. debentures.

Description : __________________ is the systematic development of a project idea for the eventual purpose of arriving at an investment decision. A. Project identification. B. Project formulation. C. Project feasibility. D. Project evaluation.

Last Answer : B. Project formulation.

Description : ______________ is the analysis of costs and benefits of a proposed project with the goal of assuming a rational allocation of limited funds. A. Project formulation. B. Project evaluation. C. Project appraisal . D. Project Design.

Last Answer : C. Project appraisal .

Description : ____________ is primarily concerned with the identification of the project demand potential and the selection of the optimal technology. A. Techno-economic analysis. B. Feasibility analysis. C. Input analysis. D. Financial analysis.

Last Answer : A. Techno-economic analysis.

Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.

Last Answer : C. Programme Evaluation and Review Techniques.

Description : Large investment is made in fixed assets, the project will be termed as __________. A. Capital Intensive. B. Labour Intensive. C. Product Intensive. D. Market Intensive.

Last Answer : A. Capital Intensive.