The expected out turn of cement concrete 1 : 2 : 4 per mason per day is
(A) 1.5 m3
(B) 2.5 m3
(C) 3.5 m3
(D) 5.0 m3

1 Answer

Answer :

(D) 5.0 m3

Related questions

Description : The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is (A) 1.00 m3 (B) 1.25 m3 (C) 1.50 m3 (D) 1.75 m3

Last Answer : (B) 1.25 m3

Description : The expected out turn of half brick partition wall per mason per day is (A) 1.5 m3 (B) 2.0 m3 (C) 4.0 m2 (D) 5.0 m2

Last Answer : (B) 2.0 m3

Description : The expected out turn of 2.5 cm cement concrete floor per mansion per day (A) 2.5 sqm (B) 5.0 sqm (C) 7.5 sqm (D) 10 sqm

Last Answer : (C) 7.5 sqm

Description : For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is (A) 0.90 m3 (B) 0.94 m3 (C) 0.98 m3 (D) 1.00 m3

Last Answer : (B) 0.94 m3

Description : Specific weight of Reinforced cement concrete is [ A ] 24 N/m3 [ B ] 24 kN/m3 [ C ] 25 N/m3 [ D ] 25 kN/m3

Last Answer : [ D ] 25 kN/m3

Description : The expected out turn of 12 mm plastering with cement mortar is (A) 2.5 sq m (B) 4.0 sq m (C) 6.0 sq m (D) 8.0 sq m

Last Answer : (D) 8.0 sq m

Description : A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is (A) 500 m3 (B) 1000 m3 (C) 1500 m3 (D) 2000 m3

Last Answer : (C) 1500 m3

Description : For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is (A) 0.200 m3 (B) 0.247 m3 (C) 0.274 m3 (D) 0.295 m

Last Answer : (C) 0.274 m3

Description : According to IS:456-2000, the total acid soluble chlorides in concrete is restricted to________ of concrete [ A ] 0.2 kg/m3 [ B ] 0.4 kg/m3 [ C ] 2 kg/m3 [ D ] 4 kg/m3

Last Answer : [ B ] 0.4 kg/m3

Description : According to IS:456-2000, the total acid soluble chlorides in concrete is restricted to________ of concrete [ A ] 0.2 kg/m3 [ B ] 0.4 kg/m3 [ C ] 2 kg/m3 [ D ] 4 kg/m3

Last Answer : [ B ] 0.4 kg/m3

Description : Minimum number of 50 kg cement bags per cubic metre of concrete for a mix corresponding to crushing strength 280 kg/cm2 at 28 days, are (A) 5.0 (B) 6.5 (C) 7.0 (D) 7.5

Last Answer : Answer: Option B

Description : The expected out turn for earth work in excavation in ordinary soil per workman per day is (A) 1.00 cum (B) 2.00 cum (C) 3.00 cum (D) 4.00 cum

Last Answer : (C) 3.00 cum

Description : For a concrete mix 1:3:6 and water cement ratio 0.6 both by weight, the quantity of water required per bag, is (A) 10 kg (B) 12 kg (C) 14 kg (D) 16 kg

Last Answer : Answer: Option C

Description : The unit weight of cement in kN/m3 (a) 25 kN/m3 (b) 24 kN/m3 (c) 20 kN/m3 (d) 16 kN/m3

Last Answer : (d) 16 kN/m3

Description : According to IS: 456-2000, the maximum cement content exclusive of admixtures is [ A ] 200 kg/m3 [ B ] 300 kg/m3 [ C ] 450 kg/m3 [ D ] 550 kg/m3

Last Answer : [ C ] 450 kg/m3

Description : According to IS:456 minimum cement content inclusive of admixtures is [ A ] 200 kg/m3 [ B ] 300 kg/m3 [ C ] 450 kg/m3 [ D ] 550 kg/m3

Last Answer : [ B ] 300 kg/m3

Description : According to IS: 456-2000, the maximum cement content exclusive of admixtures is [ A ] 200 kg/m3 [ B ] 300 kg/m3 [ C ] 450 kg/m3 [ D ] 550 kg/m3

Last Answer : [ C ] 450 kg/m3

Description : According to IS:456 minimum cement content inclusive of admixtures is [ A ] 200 kg/m3 [ B ] 300 kg/m3 [ C ] 450 kg/m3 [ D ] 550 kg/m3

Last Answer : [ B ] 300 kg/m3

Description : The weight of reinforced concrete, is generally taken as (A) 2200 kg/m3 (B) 2300 kg/m3 (C) 2400 kg/m3 (D) 2500 kg/m

Last Answer : Answer: Option C

Description : The weight of reinforced concrete is generally take as (a) 2300 kg/m3 (b) 2400 kg/m3 (c) 2500kg/m3 (d) 2800kg/m3

Last Answer : (d) 2800kg/m3

Description : Maximum quantity of water needed per 50 kg of cement for M 15 grade of concrete is (A) 28 liters (B) 30 liters (C) 32 liters (D) 34 liters

Last Answer : Answer: Option C

Description : For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are: (A) 70 litres of sand and 120 litres of aggregates (B) 70 kg of sand and 140 litres of ... C) 105 litres of sand and 140 litres of aggregates (D) 105 litres of sand and 210 litres of aggregates

Last Answer : Answer: Option D

Description : For a homogeneous earth dam 50 m high having 2 m free broad, a flow net was constructed and the results were : Number of potential drops = 2.4 Number of flow channels = 0.4. If co-efficiency of permeability of the dam material is ... 24 10-3 m3 /sec (C) 6 10-5 m3 /sec (D) 24 10-5 m3 /sec

Last Answer : (D) 24 × 10-5 m3 /sec

Description : Utilizing the answer to the previous problem, estimate the overall or average increase in temperature ( ΔT) of the concrete roof from the energy absorbed from the sun during a12hour day. Assume that all of the radiation absorbed goes into ... °C  b. 8.9°C  c. 9.9°C  d. 10.9°C formula: ΔQ = m c ΔT

Last Answer : 7.9 °C

Description : Which of the following cements is expected to have the highest compressive strength after 3 days (a) Ordinary Portland cement (b) Rapid hardening cement (c) High alumina cement (d) Sulphate resisting cement.

Last Answer : (c) High alumina cement

Description : If d is the economic designed depth of a slab, the thickness of the cement concrete pavement slab at interior, is kept (A) 1.275 d (B) 1.125 d (C) 0.85 d (D) 0.75 d

Last Answer : Answer: Option C

Description : If 50 kg of fine aggregates and 100 kg of coarse aggregates are mixed in a concrete whose water cement ratio is 0.6, the weight of water required for harsh mix, is (A) 8 kg (B) 10 kg (C) 12 kg (D) 14 kg

Last Answer : Answer: Option C

Description : Minimum required water cement ratio for a workable concrete, is (A) 0.30 (B) 0.40 (C) 0.50 (D) 0.60

Last Answer : Answer: Option B

Description : Pick up the correct statement from the following: (A) For thin structures subjected to wetting and drying, the water cement ratio should be 0.45 (B) For mass concrete structures subjected to wetting and ... under water, the water-cement ratio by weight should be 0.55 (D) All the above

Last Answer : Answer: Option D

Description : High strength of concrete requires a water cement ratio of [ A ] 0.10 to 0.15 [ B ] 0.25 to 0.30 [ C ] 0.45 to 0.60 [ D ] 0.75 to 0.90

Last Answer : [ B ] 0.25 to 0.30

Description : If is the angle of repose of soil of weight w kg/m3 , the horizontal pressure p at a depth of h metres per metre length of wall, is (A) wh × [(1 - sin )/(1 + )] (B) (wh/2) × [(1 - sin )/(1 + )] (C) wh - sin )/(1 + )] (D) wh )/(1 - )

Last Answer : Answer: Option A

Description : In case of hand mixing of concrete, the extra cement to be added is (A) 5 % (B) 10 % (C) 15 % (D) 20 %

Last Answer : (B) 10 %

Description : For providing a raft foundation, the following activities are involved 1. Ramming the foundation bed 2. Excavation of the soil upto required depth 3. Laying the reinforcement over the foundation bed 4. Curing the cement concrete placed over ... 2, 1 (C) 2, 1, 3, 5, 4 (D) 3, 2, 5, 1, 4

Last Answer : Answer: Option C

Description : The ratio of differenct ingredients (cement, sand and aggregate) in concrete mix of grade M20 is. (a) 1:1:2 (b) 1:1.5:2 (c) 1:2:4 (d) 1:3:6

Last Answer : (b) 1:1.5:2

Description : The strength of concrete using air entraining cement gets reduced by (a) 5 to 10% (b) 10 to 15% (c) 15 to 20% (d) 20 to 25%

Last Answer : (b) 10 to 15%

Description : The maximum shear stress (q) in concrete of a reinforced cement concrete beam is (A) Shear force/(Lever arm × Width) (B) Lever arm/(Shear force × Width) (C) Width/(Lever arm × Shear force) (D) (Shear force × Width)/Lever arm

Last Answer : Answer: Option A

Description : The allowable tensile stress in mild steel stirrups, reinforced cement concrete, is (A) 1400 kg/cm2 (B) 190 kg/cm2 (C) 260 kg/cm2 (D) 230 kg/cm

Last Answer : Answer: Option A

Description : In cement concrete pavements, tensile stress is due to: (A) Bending or deflection under wheel loads (B) Difference in temperature of the top and bottom of pavement (C) Contraction of slab during falling temperature (D) All the above

Last Answer : Answer: Option D

Description : For the design of cement concrete pavement for corner loading, Indian Road Congress recommends the use of (A) Westergaard's formula (B) Kelly's formula (C) Goldbeck's formula (D) Picker's formula

Last Answer : Answer: Option D

Description : When each particle of aggregates is thinly coated with cement paste, a heterogeneous solid is formed, which is known as (A) Hydration (B) Gel (C) Concrete (D) None of these

Last Answer : Answer: Option C

Description : In case of cement concrete pavements, pick up the incorrect statement (A) Tractive resistance is low (B) Initial cost of construction is high (C) Initial cost of construction is low (D) Visibility during nights is high

Last Answer : Answer: Option C

Description : The desirable camber for straight cement concrete roads, is (A) 1 in 33 to 1 in 25 (B) 1 in 40 to 1 in 33 (C) 1 in 150 to 1 in 140 (D) 1 in 160 to 1 in 140

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following. If water cement ratio is (A) Increased, strength of concrete increases (B) Decreased, strength of concrete increases (C) Increased, strength of concrete is not affected (D) None of these

Last Answer : Answer: Option C

Description : In ideal pavement is constructed with (A) Bricks (B) Hard soil (C) Portland cement concrete (D) Tar

Last Answer : Answer: Option C

Description : Reinforcement in cement concrete slab of road pavements, is placed (A) Longitudinally (B) Transversely (C) Longitudinally and transversely (D) In the form of welded wire mesh

Last Answer : Answer: Option D

Description : Tie bars in cement concrete pavements are at (A) Expansion joints (B) Contraction joints (C) Warping joints (D) Longitudinal joints

Last Answer : Answer: Option D

Description : The critical combination of stresses for corner region in cement concrete roads is (A) Load stress + warping stress frictional stress (B) Load stress + warping stress + frictional stress (C) Load stress + warping stress (D) Load stress + frictional stress

Last Answer : Answer: Option C

Description : When the bituminous surfacing is done on already existing black top road or over existing cement concrete road, the type of treatment given is (A) Seal coat (B) Tack coat (C) Prime coat (D) Spray of emulsion

Last Answer : Answer: Option B

Description : The measurement is made in square metre in case of (A) Cement concrete in foundation (B) R.C.C. structure (C) Hollow concrete block wall (D) None of these

Last Answer : (D) None of these

Description : Pick up the correct statement from the following: (A) Water enables chemical reaction to take place with cement (B) Water lubricates the mixture of gravel, sand and cement (C) Strength of concrete structure largely depends upon its workability (D) All the above

Last Answer : (D) All the above