In ideal pavement is constructed with
(A) Bricks
(B) Hard soil
(C) Portland cement concrete
(D) Tar

1 Answer

Answer :

Answer: Option C

Related questions

Description : Pavement is said to be flexible if it contains (A) Water bound macadam surface (B) Stabilised soil base constructed of lime cement or tar (C) Bitumen-bound stone layer of varying aggregates (D) All the above

Last Answer : Answer: Option D

Description : Newly constructed pavement with ordinary Portland cement attains its working strength after (A) 7 days (B) 14 days (C) 21 days (D) 28 days

Last Answer : Answer: Option D

Description : Brick nogging type of partition wall, is constructed by (A) Laying bricks as stretchers in cement mortar (B) Laying bricks as headers in cement mortar (C) Reinforcing brick wall with iron straps (D) Constructing brick work within a wooden framework

Last Answer : Answer: Option D

Description : Which of the following is the most widely used heat insulating material for pipelines carrying steam? (A) Tar dolomite bricks followed by asbestos (B) Fireclay refractory followed by aluminium sheet (C) Cotton followed by aluminium foil (D) 85% magnesia cement and glass wool

Last Answer : (D) 85% magnesia cement and glass wool

Description : Following type of pavement is generally known as flexible pavement (A) Water-bound macadam roads (B) Stabilised soil roads (C) Road constructed with various layers of building material well compacted (D) All the above

Last Answer : Answer: Option D

Description : In cement concrete pavements, tensile stress is due to: (A) Bending or deflection under wheel loads (B) Difference in temperature of the top and bottom of pavement (C) Contraction of slab during falling temperature (D) All the above

Last Answer : Answer: Option D

Description : For the design of cement concrete pavement for corner loading, Indian Road Congress recommends the use of (A) Westergaard's formula (B) Kelly's formula (C) Goldbeck's formula (D) Picker's formula

Last Answer : Answer: Option D

Description : If d is the economic designed depth of a slab, the thickness of the cement concrete pavement slab at interior, is kept (A) 1.275 d (B) 1.125 d (C) 0.85 d (D) 0.75 d

Last Answer : Answer: Option C

Description : Pick up the incorrect statement from the following: (A) The width of the wall is constructed thicker at the base in a stepped fashion (B) A long vertical load transferring concrete structure is ... ) The pile which transfers the load to a hard rock bed at certain depth is called load bearing

Last Answer : Answer: Option D

Description : Which of the following cements is suitable for use in massive concrete structures such as large dams? (A) Ordinary Portland cement (B) Low heat cement (C) Rapid hardening cement (D) Sulphate resisting cement

Last Answer : Answer: Option B

Description : For Ordinary Portland cement concrete exposed to dry and hot weather conditions, good moist curing period is [ A ] 7 days [ B ] 10 days [ C ] 14 days [ D ] None of the above

Last Answer : [ B ] 10 days

Description : For mass concrete work, the type of cement preferable is [ A ] Ordinary Portland cement [ B ] Rapid hardening cement [ C ] Low heat cement [ D ] Blast furnace slag cement

Last Answer : [ C ] Low heat cement

Description : Write the procedure of construction of cement concrete pavement showing its components. 

Last Answer : Construction procedure of Concrete Roads: 1) Preparation of subgrade by proper compaction 2) Provision of sub base to support subgrade 3) Placing of forms i.e. Steel channels 4) Batching and ... method 11) Filling of joints using joint sealers 12) Opening of traffic after cleaning

Description : The surface of a "desert pavement" is composed mainly of which of the following? w) loose sand x) sand and clay y) pebbles and boulders z) concrete and cement

Last Answer : ANSWER: Y -- PEBBLES AND BOULDERS

Description : Pick up the correct statement from the following: (A) A soil having pH value more than 7 is an acidic soil (B) A soil having pH value less than 7 is an acidic soil (C) A soil ... more than 7 is an alkaline soil (D) A soil containing chemicals for the manufacture of Portland cement is preferred

Last Answer : Answer: Option B

Description : (1) Calcium silicate and calcium alurninate Explanation: Portland cement is the most common type of cement in general use around the world because it is a basic ingredient of concrete, mortar, stucco ... limited amount of calcium sulfate (which controls the set time) and up to 5% minor constituents.

Last Answer : Milk is a colloidal system in which: (1) Water is dispersed in fat (2) Fat is dispersed in water (3) Fat and water are dispersed in each other (4) Fat is dissolved

Description : 221 For non-scouring velocity 5 m/sec, the type of sewers generally preferred to, is A. Cast iron sewers B. Cement concrete sewers C. Glazed bricks sewers D. Stone ware sewers

Last Answer : ANS: C

Description : In sewers the highest non-scouring velocity is achieved in A. Glazed bricks sewers B. Cast iron sewers C. Cement concrete sewers D. Stone ware sewers

Last Answer : ANS: A

Description : Cement grouted pavement is classified as (A) Rigid pavement (B) Semi-rigid pavement (C) Flexible pavement (D) None of these

Last Answer : B

Description : The binder normally used in flexible pavement construction is (A) Cement (B) Lime (C) Bitumen (D) None of the above

Last Answer : Answer: Option C

Description : Coke oven walls are lined with __________ bricks. (A) Silica (B) Tar-dolomite (C) Low thermal conductivity (D) Fire clay

Last Answer : (A) Silica

Description : Depth of reinforcement below the surface of a concrete pavement, is generally kept (A) 5 cm (B) 6 cm (C) 7 m (D) 9 m

Last Answer : Answer: Option A

Description : To indicate proper control of consistency of a freshly mixed concrete for pavement construction, the slump should be between (A) 3 to 5 cm (B) 4 to 6 cm (C) 5 to 7 cm (D) 7 to 10 cm

Last Answer : Answer: Option D

Description : If d is the thickness of a concrete pavement, the equivalent radius b of resisting section for an interior loading, is (A) b = d 2 ) - 0.675 d (B) b = d 2 ) + 0.675 d (C) b = d 2 ) - 3.675 d (D) b = d 2 ) - 0.675 d

Last Answer : Answer: Option D

Description : Concrete pavement is provided if daily traffic per lane exceeds (A) 500 tonnes (B) 750 tonnes (C) 1000 tonnes (D) 1250 tonnes

Last Answer : Answer: Option C

Description : To prevent compressive stresses in a rigid concrete pavement, the joint provided, is (A) Expansion joint (B) Contraction joint (C) Hinged joint (D) All the above

Last Answer : Answer: Option D

Description : When load is applied on concrete pavement (A) Away from edges, the maximum bending moment is negative (B) Away from edges, the maximum bending moment cause compression (C) On the edges, the maximum stress is parallel to the edge of the slab (D) None of these

Last Answer : Answer: Option C

Description : The aggregate impact value of the aggregate used in (A) Building concrete is less than 45 (B) Road pavement concrete is less than 30 (C) Runway concrete is less than 30 (D) All the above

Last Answer : Answer: Option D

Description : In a concrete pavement, during summer, at and soon after mid-day, the combined stress at the interior of the slab is equal to : (a) Wheel load stress + Temperature warping stress + Sub ... + Sub grade resistant stress (d) Wheel load stress - Temperature warping stress − Sub grade resistant stress

Last Answer : (b) Wheel load stress + Temperature warping stress – Sub grade resistant stress

Description : An ordinary Portland cement when tested for its fineness, should not leave any residue on I.S. sieve No. 9, more than (A) 5 % (B) 10 % (C) 15 % (D) 20 %

Last Answer : (B) 10 %

Description : For an ordinary Portland cement (A) Residual does not exceed 10% when sieved through IS Sieve No. 9 (B) Soundness varies from 5 to 10 mm (C) Initial setting time is not less than 30 minutes (D) Compressive stress after 7 days, is not less than 175 kg/cm2

Last Answer : (C) Initial setting time is not less than 30 minutes

Description : For quality control of Portland cement, the test essentially done is (A) Setting time (B) Tensile strength (C) Consistency (D) All the above

Last Answer : D

Description : Ordinary Portland cement is manufactured from (A) Lime stone and clay (B) Gypsum and lime (C) Pozzolana (D) Lime, pozzolana and clay

Last Answer : Answer: Option B

Description : You are asked to construct a massive dam, the type of cement you will use, is (A) Ordinary Portland cement (B) Rapid hardening cement (C) Low heat cement (D) Blast furnace slag cement

Last Answer : Answer: Option C

Description : As compared to ordinary Portland cement, use of pozzolana cement (A) Reduces workability (B) Increases bleeding (C) Increases shrinkage (D) Increases strength

Last Answer : Answer: Option C

Description : As compared to ordinary Portland cement, high alumina cement has (A) Higher initial setting time but lower final setting time (B) Lower initial setting time but higher final setting time (C) Higher initial and final setting times (D) Lower initial and final setting times

Last Answer : Answer: Option A

Description : The cement whose strength is a little lower than the ordinary cement during the first three months but attains afterwards the same strength, is known as (A) Low-heat Portland cement (B) Rapid hardening Portland cement (C) Portland blast slag cement (D) Portland pozzolana cement

Last Answer : Answer: Option A

Description : For the construction of thin R.C.C. structures, the type of cement to be avoided, is (A) Ordinary Portland cement (B) Rapid hardening cement (C) Low heat cement (D) Blast furnace slag cement

Last Answer : Answer: Option D

Description : For construction of structures in sea water, the cement generally preferred to, is (A) Portland-pozzolana cement (B) Quick setting cement (C) Low heat Portland cement (D) Rapid hardening cement

Last Answer : Answer: Option A

Description : For road pavements, the cement generally used, is (A) Ordinary Portland cement (B) Rapid hardening cement (C) Low heat cement (D) Blast furnace slag cement

Last Answer : Answer: Option B

Description : The compound of Portland cement which reacts immediately with water and also sets first is (A) Tri-calcium silicate (B) Di-calcium silicate (C) Tri-calcium aluminate (D) Tetra calcium alumino ferrite

Last Answer : Answer: Option C

Description : The compound of Portland cement which contributes to the strength after two to three years is (A) Tri-calcium silicate (B) Di-calcium silicate (C) Tri-calcium aluminate (D) Tetra-calcium alumino ferrite

Last Answer : Answer: Option B

Description : Portland pozzolana cement possesses (A) Higher resistance to chemical attack (B) Lower heat of hydration (C) Lower shrinkage on drying (D) All the above

Last Answer : Answer: Option D

Description : Portland cement manufactured from pure white chalk and clay but free from iron-oxide, is known as (A) Quick setting cement (B) Rapid hardening cement (C) White cement (D) Low heat Portland cement

Last Answer : Answer: Option C

Description : The normal consistency of ordinary Portland cement is about (A) 10 % (B) 20 % (C) 30 % (D) 40 %

Last Answer : Answer: Option C

Description : Addition of pozzolana to ordinary Portland cement increases (A) Bleeding (B) Shrinkage (C) Permeability (D) Heat of hydration

Last Answer : Answer: Option B

Description : According to IS specifications, the compressive strength of ordinary Portland cement after three days should not be less than (A) 7 MPa (B) 11.5 MPa (C) 16 MPa (D) 21 MPa

Last Answer : Answer: Option C

Description : As per IS specifications, the maximum final setting time for ordinary Portland cement should be (A) 30 minutes (B) 1 hour (C) 6 hours (D) 10 hour

Last Answer : Answer: Option D

Description : For the manufacture of Portland cement, the proportions of raw materials used, are (A) Lime 63% ; silica 22% ; other ingredients 15% (B) Lime 22% ; silica 63% ; other ingredients 15% (C) Silica 40% ; lime 40% ; other ingredients 20% (D) Silica 70% ; lime 20% ; other ingredients 10%

Last Answer : Answer: Option A

Description : The initial setting time for ordinary Portland cement as per IS specifications should not be less than (A) 10 minutes (B) 30 minutes (C) 60 minutes (D) 600 minutes

Last Answer : Answer: Option B