The latest finish time for an activity:

A. Equals the min. of LFT − t for al immediate successors

B. Equals the max. of LFT − t for al immediate predecessors.

C. Equals the max. of EST + t for all immediate predecessors.

D. Equals the min. of EST + t for all immediate successors

1 Answer

Answer :

A. Equals the min. of LFT − t for al immediate successors

Related questions

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : A schedule activity may begin 10 days before the predecessor activity finishes. This is an  example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Let R and S be two fuzzy relations defined as: Then, the resulting relation, T, which relates elements of universe x to elements of universe z using max-min composition is given by

Last Answer : Answer: C

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : To calculate early start (ES) and early finish (EF) perform a:  A. Backward pass B. Forward pass  C. Lateral pass D. Critical pass

Last Answer : B. Forward pass

Description : You are a project manager for Cinema Snicker Productions. Your company  specializes in producing comedy films for the big screen. Your latest project has just been  cancelled because of budget cuts ... elsewhere. D. This project ended due to integration because the funding was cut off.

Last Answer : A. This project ended due to starvation because the funding was cut off.

Description : Maximum fluctuation of energy = 1. Max KE – Min KE 2. Max KE + Min KE 3. Max KE > Min KE 4. Max KE < Min KE

Last Answer : 1. Max KE – Min KE

Description : Maximum fluctuation of energy = (A) Max. KE – Min. KE (B) Max. KE + Min. KE (C) (Max. KE – Min. KE)/2 (D) (Max. KE + Min. KE)/2

Last Answer : (A) Max. KE – Min. KE

Description : Which of the following conditions is true for repeated stress? 1. σ m = 0 2. σ m = σ max / 2 3. σ m = σ a 4. σ min = 0 5. σ min = - σ max 6. σ a = σ max / 2 where σ m = mean ... amplitude a. condition 2 and 3 b. condition 1, 3 and 5 c. condition 2, 4, and 6 d. condition 3,4, 5 and 6

Last Answer : c. condition 2, 4, and 6

Description : Which value is assigned to alpha and beta in the alpha-beta pruning? a) Alpha = max b) Beta = min c) Beta = max d) Both Alpha = max & Beta = min

Last Answer : d) Both Alpha = max & Beta = min

Description : General algorithm applied on game tree for making decision of win/lose is ____________ a) DFS/BFS Search Algorithms b) Heuristic Search Algorithms c) Greedy Search Algorithms d) MIN/MAX Algorithms

Last Answer : d) MIN/MAX Algorithms

Description : When will Hill-Climbing algorithm terminate? a) Stopping criterion met b) Global Min/Max is achieved c) No neighbor has higher value d) All of the mentioned

Last Answer : c) No neighbor has higher value

Description : When will Hill-Climbing algorithm terminate? A : Stopping criterion met B : Global Min/Max is achieved C : No neighbour has higher value D : no criteria to terminate

Last Answer : C : No neighbour has higher value

Description : Mark the correct option a) A RD account can be opened with min deposit of Rs 10/- and multiple of Rs 5/- b) No max deposit will be prescribed in RD account c) Rebate will be paid on 6 advance ... fails to deposit his/her monthly deposit up to last working day of a calendar month, d) All the above

Last Answer : d) All the above

Description : Min and Max cash balance for each SO will be fixed by a) Head post master b) Inspector/ ASP of the Sub division c) PMG d) Divisional Supdt.

Last Answer : d) Divisional Supdt.

Description : The min and max dimension of a foreign parcel prescribed is a) 100 X 140 & 1mtr X 2 mtr b) 90 X 140 & 1.5mtr X 2 mtr c) 90 X 140 & 1mtr X 2 mtr d) None of the above

Last Answer : c) 90 X 140 & 1mtr X 2 mtr

Description : Insured boxes dimensions and weight limit is a) Max 200X200X100, min as per letter & 2 Kg a) Max 300X200X100, min as per letter & 1 Kg a) Max 100X200X100, min as per letter & 4 Kg a) None of the above

Last Answer : a) Max 300X200X100, min as per letter & 1 Kg

Description : The min and max size permissible for folded aerogramme is a) 100 X 140 & 120 X 120 b) 90 X 140 & 110 X 120 c) 80 X 140 & 100 X 120 d) None of the above

Last Answer : b) 90 X 140 & 110 X 120

Description : Dimensions of Postcards is a) Max 100 X 150 mm & min 80 X 140 mm b) Max 105 X 149 mm & min 90 X 140 mm c) Max 150 X 200 mm & min 70X 140 mm d) None of these

Last Answer : b) Max 105 X 149 mm & min 90 X 140 mm

Description : Min copies and max size to be accepted in direct post is a) 5000 & A4 Size b) 1000 & A3 size c) 500 & Postcard size d) None of these

Last Answer : b) 1000 & A3 size

Description : Size limit of book packet roll and other than roll is a) Min 10X17 cm & max 80X100, 10X7 cm & 60X30X30 cm b) Max 15 cm x 10.5 Cm min 10X7 cm c) Min11X22cm & max 60X40cm, min 20X17cm &max 90X100cm d) None of these

Last Answer : a) Min 10X17 cm & max 80X100, 10X7 cm & 60X30X30 cm

Description : Post card of private manufacture size limit is a) Min10X7cm & max 50X100cm, min 15X25cm &max 80X100cm b) Max 15 cm x 10.5 Cm min 10X7 cm c) Min11X22cm & max 60X40cm, min 20X17cm &max 90X100cm d) None of these

Last Answer : b) Max 15 cm x 10.5 Cm min 10X7 cm

Description : Size limit of Inland letter card folded and unfolded is a) Min15.2X9cm & max 21X10cm, min 28.2X18.2cm max 30X21cm b) Min10X7cm & max 50X100cm, min 15X25cm &max 80X100cm c) Min11X22cm & max 60X40cm, min 20X17cm &max 90X100cm d) None of these

Last Answer : a) Min15.2X9cm & max 21X10cm, min 28.2X18.2cm max 30X21cm

Description : Size limit of letter and roll is a) Min11X7cm & max 60X90cm, min 10X17cm & max 88X100cm b) Min10X7cm & max 50X100cm, min 15X25cm &max 80X100cm c) Min11X22cm & max 60X40cm, min 20X17cm &max 90X100cm d) None of these

Last Answer : a) Min11X7cm & max 60X90cm, min 10X17cm & max 88X100cm

Description : Explain Min-Max method of generating the game tree.

Last Answer : Ans. The Minmax search procedure is a depth-first, depth-limited procedure. The ideas is to start at the current position & use the plausible-move generator to generate the set of possible successor ... its child values - 4. When value reaches the root: choose max value and the corresponding move.

Description : In 8086 microprocessor one of the following statements is not true.a)Coprocessor is interfaced in MAX mode b)Coprocessor is interfaced in MIN mode c)I/O can be interfaced in MAX / MIN moded)Supports pipelining

Last Answer : b)Coprocessor is interfaced in MIN mode

Description : 8088 microprocessor differs with 8086 microprocessor in a) Data width on the output b) Address capability c) Support of coprocessor d) Support of MAX / MIN mode

Last Answer : a) Data width on the output

Description : In 8086 microprocessor one of the following statements is not true. a) Coprocessor is interfaced in MAX mode b) Coprocessor is interfaced in MIN mode c) I/O can be interfaced in MAX / MIN mode

Last Answer : b) Coprocessor is interfaced in MIN mode

Description : Given two sorted list of size 'm' and 'n' respectively. The number of comparison needed in the worst case by the merge sort algorithm will be (A) m x n (B) max (m, n) (C) min (m, n) (D) m + n – 1

Last Answer :  (D) m + n – 1

Description : ................ is used in game trees to reduce the number of branches of the search tree to be traversed without affecting the solution. (A) Best first search (B) Goal stack planning (C) Alpha-beta pruning procedure (D) Min-max search

Last Answer : (C) Alpha-beta pruning procedure

Description : Let f(n) and g(n) be asymptotically non-negative functions. Which of the following is correct? (A) θ(f(n) * g(n)) = min(f(n), g(n)) (B) θ(f(n) * g(n)) = max(f(n), g(n)) (C) θ(f(n) + g(n)) = min(f(n), g(n)) (D) θ(f(n) + g(n)) = max(f(n), g(n))

Last Answer : (D) θ(f(n) + g(n)) = max(f(n), g(n))

Description : In a one Kilometer race A beats B by 28 meters or 7 seconds. Find out the time taken by A to finish the race. A. 4 Mins 3 secs B. 3 min 4 secs C. 5 mins D. 4 mins 20 secs

Last Answer : ANSWER: A

Description : In a one Kilometer race A beats B by 28 meters or 7 seconds. Find out the time taken by A to finish the race. A. 4 Mins 3 secs B. 3 min 4 secs C. 5 mins D. 4 mins 20 secs

Last Answer : ANSWER: A

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : In the context of the reign of Guptas and their successors, what is Vishti'? -Do You Know?

Last Answer : answer: