Total float for any activity is defined as the difference between
(A) Its latest finish time and earliest start time for its successor activity
(B) Its latest start time and earliest start time
(C) Its latest start time and earliest finish time
(D) Its earliest finish time and earliest start time for its successor activity

1 Answer

Answer :

(B) Its latest start time and earliest start time

Related questions

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good (A) EF = ES + D (B) LS = LF - D (C) LF = LS + D (D) All the above

Last Answer : (D) All the above

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : Total float in a planning network is (a) Late start time – Early start time (b) Early start time – Late start time (c) Late start time – Late finish time (d) Late finish time – Early finish time

Last Answer : Ans: (a & d)

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : The latest finish time for an activity: A. Equals the min. of LFT − t for al immediate successors B. Equals the max. of LFT − t for al immediate predecessors. C. Equals the max. of EST + t for all immediate predecessors. D. Equals the min. of EST + t for all immediate successors

Last Answer : A. Equals the min. of LFT − t for al immediate successors

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Earliest expected time is denoted by TE (B) Latest occurrence time is denoted by TL (C) Contractual obligation time is denoted by Ts (D) All the above

Last Answer : (D) All the above

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : Free float is mainly used to (A) Identify the activities which can be delayed without affecting the total float of preceding activity (B) Identify the activities, which can be delayed ... which can be delayed without affecting the total float of either the preceding or succeeding activities

Last Answer : (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : A game can be formally defined as a kind of search problem with the following components. a) Initial State b) Successor Function c) Terminal Test d) All of the mentioned

Last Answer : d) All of the mentioned

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : An activity which does not consume either resource or time is called ............................. a. Predecessor activity b. Successor activity c. Dummy activity d. Terminal activity

Last Answer : c. Dummy activity

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : An activity which must be completed before commencement of one or more other activities is called................................. a. Successor activity b. Predecessor activity c. Dummy activity d. None of these

Last Answer : b. Predecessor activity

Description : The independent float affects only (A) Preceding activities (B) Succeeding activities (C) The particular activity involved (D) None of the above

Last Answer : (C) The particular activity involved

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : What are the earliest and latest possible dates, on the common Roman calendar, for the Hebrew Festival of Shabuot, the Feast of Weeks, or Pentecost?

Last Answer : It always falls 49 days from the second day of Passover. (7 weeks ). Those 49 days are known as the Counting of the Omer. (The 33rd day - Lag B'omer) is considered a holiday to spend ... Pesach can be anywhere between mid-March and late April. Quick consult a Jewish calendar. The date is variable.

Description : What are your personal guidelines as far as the earliest in the day you'll call someone and the latest in the evening you'll call, if you don't know their sleep/wake habits?

Last Answer : 10am, 9pm.

Description : Why doesn't the summer solstice have the earliest sunrise or latest sunset of the year?

Last Answer : It's supposed to be the longest day of the year, right? What gives?

Description : Backward pass calculations are done to find ________ occurrence times of events a. Tentative b. Definite c. Latest d. Earliest

Last Answer : c. Latest

Description : Forward pass calculations are done to find _____ occurrence times of events a. Exact b. Earliest c. Latest d. Approximate

Last Answer : b. Earliest

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : In Activity-Selection problem, each activity i has a start time si and a finish time fi where si≤fi. Activities i and j are compatible if: (A) si≥fj (B) sj≥fi (C) si≥fj or sj≥fi (D) si≥fj and sj≥fi

Last Answer : (C) si≥fj or sj≥fi 

Description : Interfering float is the difference between (A) Total float and free float (B) Total float and independent float (C) Free float and independent float (D) None of the above

Last Answer : (A) Total float and free float

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : A schedule activity may begin 10 days before the predecessor activity finishes. This is an  example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : How much money does it take a canidate to possibly become president. I mean everything from start to finish, tv ads, staff, cars, planes, protection, hotels on and on and on. Could someone tell me the total cost of all this for just one politician?

Last Answer : Around $500 million USD.

Description : Where is the expression of earliest volcanic activity in India found? -Do You Know?

Last Answer : answer:

Description : Where is the expression of earliest volcanic activity in India found?

Last Answer : Dalmia hill

Description : The difference between the time avail-to do a job and the time required to do the job, is known as (A) Event (B) Float (C) Duration (D) Constraint

Last Answer : (B) Float