Pick up the correct statement from the following:
(A) The duration between the earliest start time of the preceding event and latest finish time of
the succeeding event, is called 'float'
(B) The duration of time by which an activity can be delayed without affecting the succeeding
activity, is called free float
(C) The difference between total float and free float, is called interfering float
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : Free float is mainly used to (A) Identify the activities which can be delayed without affecting the total float of preceding activity (B) Identify the activities, which can be delayed ... which can be delayed without affecting the total float of either the preceding or succeeding activities

Last Answer : (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : The independent float affects only (A) Preceding activities (B) Succeeding activities (C) The particular activity involved (D) None of the above

Last Answer : (C) The particular activity involved

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good (A) EF = ES + D (B) LS = LF - D (C) LF = LS + D (D) All the above

Last Answer : (D) All the above

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Interfering float is the difference between (A) Total float and free float (B) Total float and independent float (C) Free float and independent float (D) None of the above

Last Answer : (A) Total float and free float

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : Pick up the correct statement from the following: (A) Earliest expected time is denoted by TE (B) Latest occurrence time is denoted by TL (C) Contractual obligation time is denoted by Ts (D) All the above

Last Answer : (D) All the above

Description : The difference between the time avail-to do a job and the time required to do the job, is known as (A) Event (B) Float (C) Duration (D) Constraint

Last Answer : (B) Float

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : Total float in a planning network is (a) Late start time – Early start time (b) Early start time – Late start time (c) Late start time – Late finish time (d) Late finish time – Early finish time

Last Answer : Ans: (a & d)

Description : Pick up the correct statement from the following: (A) The tides at any place occur a little less than 1 hour later, each succeeding day (B) The influence of the earth's gravity alone produces level-tidal ... ) The spinning force is maximum at the equator and zero at the poles (D) All of the above

Last Answer : (D) All of the above

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : The following statements relate to CPE credit units. Which is incorrect? a. One credit hour of CPE program, activity or source shall be equivalent to one (1) credit unit. b. Any excess ... carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Last Answer : Excess credit units earned may be carried over to the next three-year period including credit units earned for doctoral and master's degrees.

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : If I drink two energy drinks a day (generally sugar-free redbull), what is the absolute latest I could drink the second one before it would start affecting my sleep?

Last Answer : i would just stay away from that junk really

Description : The latest finish time for an activity: A. Equals the min. of LFT − t for al immediate successors B. Equals the max. of LFT − t for al immediate predecessors. C. Equals the max. of EST + t for all immediate predecessors. D. Equals the min. of EST + t for all immediate successors

Last Answer : A. Equals the min. of LFT − t for al immediate successors

Description : Pick up the correct statement from the following: (A) Roasting is not necessary if iron ore is an oxide (B) Impurities float on the molten iron as slag (C) The slag contains lime about 45% (D) All the above

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : Activities which must be finished before a given event can occur are termed as _________. A. Preceeding Activities. B. Succeeding Activities C. Concurrent Activities D. Dummy Activities.

Last Answer : A. Preceeding Activities.

Description : Pick up the correct statement from the following: (A) The specified duration of unit hydrograph, is called unit duration (B) The rain during specified duration, is called unit storm (C) The number of unit hydrographs for a given basin, is theoretically infinite (D) All the above

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The intensity of rain is the rate at which it falls (B) The duration of rain is the time for which it falls with a given intensity (C) The frequency of rain is the number of times, if falls (D) All the above

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The unit hydrograph of a specified unit duration obtained from the past data can be used to obtain the hydrograph of future storms of like duration (B) ... hydrograph may be obtained by dividing the run off in mm by 25 mm (D) All the above

Last Answer : Answer: Option D

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Under the Insolvency and Bankruptcy Code, 2016, debts owed to a secured creditor in the event such secured creditor has relinquished security ranks equally with ___________. a) insolvency ... period of twelve months preceding the liquidation commencement date d) dues to Central Government

Last Answer : b) workmen’s dues for a period of 24 months prior to liquidation commencement date

Description : Digitalis in creases the force of contraction of ventricles by: A. Increasing the duration of systole B. Increasing the rate of contraction without affecting the duration of systole C. Increasing the rate ... of systole D. Increasing both the rate of contraction as well as the duration of systole

Last Answer : C. Increasing the rate of contraction, but reducing the duration of systole

Description : EST stands for ____________. A. Earliest Start Time. B. Event Start Time. C. Effective Start Time. D. Essential Start Time.

Last Answer : A. Earliest Start Time.

Description : Choose the correct statement about the action of nitrates on coronary vessels (a) They mitigate angina pectoris by increasing total coronary flow (b) They preferentially dilate conducting ... the larger arteries (d) They increase subepicardial blood flow without affecting subendocardial blood flow

Last Answer : Ans: B

Description : Choose the correct statement about the action of nitrates on coronary vessels: A. They mitigate angina pectoris by increasing total coronary flow B. They preferentially dilate conducting ... the larger arteries D. They increase subepicardial blood flow without affecting subendocardial blood flow

Last Answer : B. They preferentially dilate conducting arteries without affecting resistance arterioles

Description : Long-term thiazide therapy can cause hyperglycaemia by: A. Reducing insulin release B. Interfering with glucose utilization in tissues C. Increasing sympathetic activity D. Increasing corticosteroid secretion

Last Answer : A. Reducing insulin release