Which of the following statements is true?

A. PERT is considered as a deterministic approach and CPM is a probabilis t ic

techniques.

B. PERT is considered as a probabilistic techniques and CPM is considered as a

deterministic approach.

C. PERT and CPM are both probabilistic techniques.

D. PERT and CPM are both considered as deterministic approachs

1 Answer

Answer :

B. PERT is considered as a probabilistic techniques and CPM is considered as a

deterministic approach

Related questions

Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP

Last Answer : A. CPM

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : ......................... models involve more risks and uncertainties. a. Probabilistic b. Deterministic c. Both a and b d. None of these

Last Answer : a. Probabilistic

Description : In .................. models, everything is defined and the results are certain. a. Probabilistic b. Deterministic c. Both a and b d. None of these

Last Answer : b. Deterministic

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : Is human thought deterministic or probabilistic?

Last Answer : answer:False dichotomy. Even if a series of events is probabilistic, there's still no room for agency' under the current understanding of Physics (yes; capital P). Therefore, the problem of ... by invoking quantum theory. We're still just along for the ride, except the ride is unpredictable.

Description : 25. Operations Research models in which some or all values of variables are random in nature are called _____ a. Physical b. Symbolic c. Deterministic d. Probabilistic

Last Answer : d. Probabilistic

Description : Operations Research models in which values of all variables and all possible outcomes are known with certainty are called _____ a. Physical b. Symbolic c. Deterministic d. Probabilistic

Last Answer : c. Deterministic

Description : In ……………… system the interaction between various subsystems cannot be defined with certainty A) Open System B) Closed System C) Deterministic System D) Probabilistic System

Last Answer : D) Probabilistic System

Description : Decision making under certainty refers to .............................. situation. a. Deterministic b. Probabilistic c. Competitive d. None of these

Last Answer : a. Deterministic

Description : Probabilistic models are also called ........................... a. Deterministic models b. Dynamic models c. Stochastic models d. None of these

Last Answer : c. Stochastic models

Description : Why PERT is preferred over CPM for evaluation of project ?

Last Answer : PERT is based on the approach of multiple time estimates for each activity.

Description : What is the benefit of using PERT/CPM network as integral component of project management? a. They furnish a consistent framework for planning, scheduling, monitoring and controlling project b. They illustrate ... that the project will be completed by a specific date d. All of the above

Last Answer : d. All of the above

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : _________ technique helps to make a choice from numerous available alternatives a. PERT b. CPM c. Linear Programming d. Transportation

Last Answer : d. Transportation

Description : ................... is an event oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : b. PERT

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : PERT technique of network analysis is mainly useful for (A) Small projects (B) Large and complex projects (C) Research and development projects (D) Deterministic activities

Last Answer : (C) Research and development projects

Description : The particular task performance in CPM is known  A.Dummy  B.Event  C.Activity  D.Contract.

Last Answer : C.Activity

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : PERT chart can be used to track the tasks of a project when task time estimates are  fairly uncertain.

Last Answer : Ans: True

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : Which one of the following statements best describes a project? a. A project is a set of tools and techniques often used when delivering organisational change. b. A project is the sum of activities ... endeavor undertaken to achieve a desired outcome. d. A project is a method of planning work.

Last Answer : c. A unique transient endeavor undertaken to achieve a desired outcome.

Description : Which one of the following statements best describes a project?  a. A project is a set of tools and techniques often used when delivering organisational change.  b. A project is the sum of ... endeavour undertaken to achieve a desired outcome.  d. A project is a method of planning work.

Last Answer : c. A unique transient endeavour undertaken to achieve a desired outcome.

Description : Which one of the following statements best defines procurement? a. A technique to establish the best approach for obtaining the resources for the project. b. A group of interrelated resources and ... product. d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which one of the following statements best defines procurement?  a. A technique to establish the best approach for obtaining the resources for the project.  b. A group of interrelated resources and ... product.  d. The process by which products and services required for the project are acquired.

Last Answer : d. The process by which products and services required for the project are acquired.

Description : Which of the following statements is most correct? A. For small companies, long-term debt is the principal source of external financing. B. Current assets of the typical manufacturing firm account ... the financial manager to make a decision and not address the issue again for several months.

Last Answer : B. Current assets of the typical manufacturing firm account for over half of its total assets.

Description : One of the reasons a project life cycle is split into phases is to: a. facilitate formal go/no-go decision making during the project. b. balance the costs of work in each phase of ... the major deployments of resources throughout the project. d. chunk work into time periods of similar durations.

Last Answer : a. facilitate formal go/no-go decision making during the project.

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.

Last Answer : C. Programme Evaluation and Review Techniques.

Description : Algorithmic cost estimation in different organisations may be different for the same application development, because a) Different organisations consider complexity factors differently b) Different organisations may use ... measurement of productivity may vary e) All of the above may be true.

Last Answer : e) All of the above may be true.

Description : Which of the following is true?  A. Discounted cash flow analysis is the least precise of the cash flow techniques, because  it does not consider the time value of money. B. NPV is ... least precise of the cash flow analysis techniques, because it assumes  reinvestment at the cost of capital.

Last Answer : C. Payback period is the least precise of the cash flow analysis techniques, because it  does not consider the time value of money.

Description : Given the following two statements: A. L = {w|na(w) = nb(w)} is deterministic context free language, but not linear B. L = {an bn} U {an b2n} is linear, but not deterministic context free language. Which of the following ... are true. (3) (A) is true, (B) is false. (4) (A) is false, (B) is true.

Last Answer : Both (A) and (B) are true. 

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time. b. to deliver the project objectives to ... benefits. d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : According to the Project Management Institute (PMI), project  management is defined as the application of knowledge, _____, _____, and  techniques to project activities to meet the project requirements . Select ... b. tools, analysis c. analysis, theories d. skills, tools e. skills, theories

Last Answer : d. skills, tools

Description : The advantage of following the IEEE Standard for drawing up a Project Management Plan (SPMP) - see IEEE Standard 1059.1 1987 - is a) It is drawn up by representatives from major  ... each organisation for a  particular applicationarea, development team or  technique. e) All of the above.

Last Answer : e) All of the above.

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : Project management includes the tools, techniques, and essential to  deal with the growth of products a. Knowledge b. Skill c. Attitude d. Confidence

Last Answer : a. Knowledge

Description : Monte Carlo analysis can help predict the impact of risks on project deliverables.  This is an element of one of the tools and techniques of which of the following processes? A. Risk Response Planning B. Quantitative Risk Analysis C. Risk Identification D. Qualitative Risk Analysis

Last Answer : B. Quantitative Risk Analysis

Description : Which statement best describes a responsibility of the project manager: a. to be the sole source of expertise for estimating techniques on cost and time.  b. to deliver the project objectives to ... benefits.  d. to delegate all accountability for managing time, cost and quality to team leaders.

Last Answer : b. to deliver the project objectives to enable benefits to be realised.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Which one of the following statements in not correct? [CDS 2003] (a) India is the highest oil-seeds and vegetable oil producing country in the world (b) India is the second largest exporter of ... silk in world (d) India is the second largest producer of three-wheeler motor vehicles in the world

Last Answer : Ans: (c)

Description : Do it because I said to” is the mantra for project managers who use _____ as the  default approach to resolve conflict. Select one: a. collaborating b. compromising c. accommodating d. forcing e. avoiding

Last Answer : d. forcing