PERT stands for __________.
A. Programme Evaluation and Research Techniques.
B. Project Evaluation and Review Techniques.
C. Programme Evaluation and Review Techniques.
D. Project Evaluation and Research Techniques.

1 Answer

Answer :

C. Programme Evaluation and Review Techniques.

Related questions

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : PERT stand for: a. Performance Evaluation Review Technique b. Programme Evaluation Review Technique c. Programme Evaluation Research Technique

Last Answer : b. Programme Evaluation Review Technique

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : _____________ is primarily concerned with the identification, qualification and evaluation of the project resources. A. Techno-economic analysis. B. Feasibility analysis. C. Input analysis. D. Financial analysis.

Last Answer : B.Feasibility analysis.

Description : __________________ is the systematic development of a project idea for the eventual purpose of arriving at an investment decision. A. Project identification. B. Project formulation. C. Project feasibility. D. Project evaluation.

Last Answer : B. Project formulation.

Description : ______________ is the analysis of costs and benefits of a proposed project with the goal of assuming a rational allocation of limited funds. A. Project formulation. B. Project evaluation. C. Project appraisal . D. Project Design.

Last Answer : C. Project appraisal .

Description : ______________ is an activity-oriented approach. A. CPM B. PERT C. GERT D. WASP

Last Answer : A. CPM

Description : _____________ is an event-oriented approach . A. CPM. B. GERT. C. PERT. D. WASP.

Last Answer : 1

Description : The content of the final report typically includes the following topics __________. A. Executive summary B. review and analysis C. recommendations D. If all the above are correct.

Last Answer : D. If all the above are correct.

Description : DGTD stands for __________. A. Directorate General of Technical Development. B. District General of Technical Development. C. District General of Taxation Deduction. D. Directorate General of Taxation Deduction.

Last Answer : A. Directorate General of Technical Development.

Description : Which of the following is the reason for business failure __________. A. Lack of market research. B. Poor financial control. C. Poor management. D. All the above.

Last Answer : D. All the above.

Description : Why PERT is preferred over CPM for evaluation of project ?

Last Answer : PERT is based on the approach of multiple time estimates for each activity.

Description : Today, many companies are using managerial techniques that are designed to encourage _________. A. increasing profits B. legal compliances C. Ethical behaviour D. shareholders value

Last Answer : C. Ethical behaviour

Description : Large investment is made in fixed assets, the project will be termed as __________. A. Capital Intensive. B. Labour Intensive. C. Product Intensive. D. Market Intensive.

Last Answer : A. Capital Intensive.

Description : Pick up the correct statement from the following: (A) Programme Evaluation and Review Technique, is event oriented (B) Programme Evaluation and Review Technique is not event oriented (C) Critical Path Method is event oriented (D) Critical Path method is event oriented

Last Answer : (A) Programme Evaluation and Review Technique, is event oriented

Description : LOB stands for____________. A. Line of Business. B. Line of Balance. C. Loss of Business. D. Loss of Balance

Last Answer : B. Line of Balance.

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : EST stands for ____________. A. Earliest Start Time. B. Event Start Time. C. Effective Start Time. D. Essential Start Time.

Last Answer : A. Earliest Start Time.

Description : IFCI stands for_____________. A. Industrial finance corporation of India. B. Institutional finance corporation of India. C. Industrial funding corporation of India. D. Indian finance corporation and institution

Last Answer : A. Industrial finance corporation of India.

Description : NABARD is a Bank for _____________ development A. Urban B. Agricultural and Rural C. Scientific D. Agriculture and research

Last Answer : B. Agricultural and Rural

Description : The use of informal networks by entrepreneurs to gather information is known as _______. A. Secondary research. B. Entrepreneurial networking. C. Informal parameters. D. Marketing

Last Answer : Entrepreneur network

Description : ______________ describes the direction, the enterprise is going in, what its goals are, where it wants to be,and how it is going to get there. A. project report B. technical anlaysis C. market analysis D. financial analysis

Last Answer : A. project report

Description : Every entrepreneur should draw an _______ for his project to ensure the timely completion of all activities involved in setting up an enterprise. A. cost structure B. implementation plan C. market structure D. production structure

Last Answer : B. implementation plan

Description : market potential of the project report includes ________. A. demand and supply conditions B. market strategy C. after sales service D. all the above

Last Answer : D. all the above

Description : what are the components of then project report ________. A. requirement of funds B. location C. manpower D. all the above

Last Answer : All

Description : Project mission and objectives, procedures and systems used, and organization resources used typically appear in the _____ section of the final project report. A. Analysis B. Recommendation C. lessons learned D. financial feasibility

Last Answer : A. Analysis

Description : Integration of project management with the organization takes place with the _______________. A. master budjet B. strategic plan C. Process of managing actual projects D. both b and c

Last Answer : D. both b and c

Description : Project management is ideally suited for a business environment requiring all of the following except _________. A. Flexibility B. Innovation C. speed D. Repetability

Last Answer : A. Flexibility

Description : Which of the following is not considered to be a characteristic of a project? A. An established objective B. Complex tasks C. A clear beginning and end D. Only for internal use

Last Answer : D. Only for internal use

Description : The minimum amount of------------------,irrespective of such private participation,could be specified at a minimum 17.5 per cent of project costs by lending institutions. A. bank loans B. promotors contribution C. fixed capital D. working capital

Last Answer : B. promotors contribution

Description : ____________, which is included in the project cost, is estimated on the basis of the year when the enterprise breaks even. A. working capital B. cost of capital C. cost of production D. cost of equity

Last Answer : A. working capital

Description : A project, which may not add to the existing profits, should be financed by _________ A. debentures. B. preference share capital. C. equity capital. D. public deposits.

Last Answer : A. debentures.

Description : Underestimation of project cost leads to ___________. A. Time under run. B. Cost under run C. Time over run. D. Cost over run

Last Answer : D. Cost over run

Description : The process of preparing an inventory of skills needed for effective implementation of the project is called as ____________. A. Economic viability. B. Financial feasibility. C. Technical feasibility. D. Managerial competence.

Last Answer : D. Managerial competence.

Description : _____________ may be defined as the excess of present value of project cash inflows over that of out flows. A. Net present value technique. B. Average rate of return. C. Benefit-Cost ratio. D. Internal rate of return

Last Answer : A. Net present value technique.

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : ____________ is a graphical representation of the various activity and event relating to a project. A. Network analysis. B. Scheduling technique. C. Logical Model. D. Network Diagram

Last Answer : D. Network Diagram

Description : ____________ is primarily concerned with the identification of the project demand potential and the selection of the optimal technology. A. Techno-economic analysis. B. Feasibility analysis. C. Input analysis. D. Financial analysis.

Last Answer : A. Techno-economic analysis.

Description : _____________ is used to accomplish the project economically in the minimum available time with limited resources A. Project Scheduling. B. Network Analysis. C. Budget Analysis. D. Critical Planning.

Last Answer : A. Project Scheduling.

Description : _____________ can be defined as a specifically evolved work plan densed to achieve a specific objective within a specific period of time A. Idea generation. B. Opportunity Scanning. C. Project. D. Strategy.

Last Answer : C. Project.

Description : Primary data is________. A. the most important data. B. the data that is collected first. C. new data specifically collected for a project. D. data that is collected second.

Last Answer : C. new data specifically collected for a project.

Description : CIET stands for (A) Centre for Integrated Education and Technology (B) Central Institute for Engineering and Technology (C) Central Institute for Education Technology (D) Centre for Integrated Evaluation Techniques.

Last Answer : (C) Central Institute for Education Technology

Description : Entrepreneurial development is the key to achieve all-round __________ through A. economic development B. increase in profits C. shareholders value D. business development

Last Answer : A. economic development

Description : Under-capitalization arises due to __________. A. excess of assets over the liabilities. B. excess of liabilities over the assets. C. actual capitalization is higher than the proper capitalization. D. actual capitalization is lower than the proper capitalization.

Last Answer : D. actual capitalization is lower than the proper capitalization.

Description : EXIM bank is a __________. A. State-level institution. B. Regional -level institution. C. All India institution. D. International institution.

Last Answer : C. All India institution.

Description : A provisional SSI registration certificate is valid for a period of __________. A. four Years. B. three Years. C. two Years. D. one year.

Last Answer : D. one year.

Description : New Small Scale industries are exempted from the payment of income tax under section 80J is called __________ A. Development Rebate.. B. Investment Allowance. C. Rehabilitation Allowance. D. Tax Holiday

Last Answer : B. Investment Allowance.