Amount of work completed to date compared with planned in the Earned Value 

Management method is 

A. Schedule Performance Index 

B. Cost Performance Index 

C. Percentage Complete 

D .Percentage Spent

1 Answer

Answer :

C. Percentage Complete

Related questions

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : A schedule performance index (SPI) of 0.76 means:  A. You are over budget B. You are ahead of schedule  C. You are only progressing at 76 percent of the rate originally planned  D. You are only progressing at 24 percent of the rate originally planned

Last Answer : C. You are only progressing at 76 percent of the rate originally planned

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : Which of the following represents the estimated value of the work actually  accomplished?  A. Earned value (EV)  B. Planned value (PV)  C. Actual cost (AC  D. Cost variance (CV)

Last Answer : A. Earned value (EV)

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control  Account and ultimately the Project  B. Multiply the percent complete by ... that package  C. Estimate a percent complete for each WBS Work Package  D. All of the above

Last Answer : D. All of the above

Description : Approximately what percentage of the project manager's time is spent in some form of  communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project  team members, upper ... other stalk holders? 1. 10-20%  2. 50-70%  3. 75-90%  4. 21-45%

Last Answer : 3. 75-90%

Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Which one of the following is least likely to be a success criterion?  a. A target for the project to receive zero change requests.  b. The date by which the project is to be completed.  c. Delivery of products that meet required specifications.  d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term  can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : Normally a performance bond, depending upon the state, only stipulates that the contractor will guarantee the work for a certain period of time.  Answer: D  (8)Which contract type places the most risk on ... fee  3. Cost plus fixed fee  4. Fixed price plus incentive fee  5. Firm fixed price

Last Answer : 5. Firm fixed price

Description : A Unit Price (UP) contract provides: 1. a reimbursement of allowable costs plus a fixed fee which is paid proportionately as the  contract progresses  2. a reimbursement of allowable cost of services ... unit rates and the  final price is dependent on the quantities needed to carry out the work.

Last Answer : 4. a fixed price where the supplier agrees to furnish goods and services at unit rates and the  final price is dependent on the quantities needed to carry out the work

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : In the project management theory, balancing scope, schedule, and cost goals is often termed as (A) triangular dilemma (B) triple constraint (C) fundamental trade-off (D) project portfolio management

Last Answer : (B) triple constraint

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : Project management is a rationally planned and organised effort to achieve a specific  goal. (True/False)

Last Answer : Ans. True

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is not considered in resource management? a. Identifying resources. b. Influencing resources. c. Assigning resources to activities. d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : Which one of the following is a valid project Key Performance Indicator (KPI)? a. Staff appraisals. b. Management buy in. c. Milestone achievement. d. Master schedule.

Last Answer : c. Milestone achievement.

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is not considered in resource management?  a. Identifying resources.  b. Influencing resources.  c. Assigning resources to activities.  d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : Fill in the blank. The _____ is the difference between the additional money spent on  prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis

Last Answer : c. cost of quality

Description : Which technique is applicable when other projects in the same analogy application domain have been completed? a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : c) Estimation by analogy

Description : Project Manager must ensure that it develops appropriate trade off/s as  A. Time, cost and performance  B. Time, value and performance  C.Men, Materials and Machines  D.Money, Cost and Return on Investment

Last Answer : A. Time, cost and performance

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True