Subsequent to preparing ____, the team plans the project schedule and budget

1 Answer

Answer :

Ans. Work Breakdown Structure

Related questions

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : Approximately what percentage of the project manager's time is spent in some form of  communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project  team members, upper ... other stalk holders? 1. 10-20%  2. 50-70%  3. 75-90%  4. 21-45%

Last Answer : 3. 75-90%

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description :  The project team has just determined that the deadline for completion will not be met.  In order to deliver a high quality system on schedule, the team has requested that the  features be ... that a fixed deadline be imposed for the project. This technique  is referred to as SDLC methodology.

Last Answer : Ans: False

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : Which of the following is not project management goal? a) Keeping overall costs within budget b) Delivering the software to the customer at the agreed time c) Maintaining a happy and well-functioning development team

Last Answer : d) Avoiding customer complaints

Description : This set of Software Engineering Multiple Choice Questions & Answers (MCQs) focuses on Project  Management . 1. Which of the following is not project management goal? a) Keeping overall ... agreed time c) Maintaining a happy and well-functioning development team d) Avoiding customer complaints

Last Answer : d) Avoiding customer complaints

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : What is the first step in project planning? Select one: a. Establish the objectives and scope. b. Determine the budget. c. Select the team organizational model. d. Determine project constraints. e. Inspect the deliverables.

Last Answer : a. Establish the objectives and scope.

Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above

Last Answer : c. Track progress

Description : Which of the following is not project management goal? a) Keeping overall costs within budget. b) Delivering to the customer at the agreed time. c) Maintaining a happy and well-functioning development team. d) Avoiding costumer complaints.

Last Answer : d) Avoiding costumer complaints.

Description : Which of these is not one of the constraints of a project? a. Scope b. Resources c. Team d. Budget

Last Answer : c. Team

Description : Which of these is not one of the constraints of a project? A. Scope B. Resources C. Team D. Budget

Last Answer : C. Team

Description : Ahmed is actively initiating a project, so he plans to invite all relevant  internal and external stakeholders including sponsors, customers, project  teams, etc. for a kick-off meeting. To ensure all ... b. Scope statement c. Project charter d. Work packages e. Project funding agents

Last Answer : c. Project charter

Description : A ____ needs to possess excellent analytical and organizational skills to manage a project team

Last Answer : Ans. Project Manager

Description : In ____ style, project manager shares his or her vision with the team but permits them to  use their respective ideas to come up with a solution.

Last Answer : Ans. Authoritative

Description : The project team documents its charge in the form of a ____, which is based on the  project proposal and business case

Last Answer : Ans. Project charter

Description : A project charter does not include ____ of the project. (A) scope (B) objectives (C) team (D) all above are included

Last Answer : (D) all above are included

Description : A schedule performance index (SPI) of 0.76 means:  A. You are over budget B. You are ahead of schedule  C. You are only progressing at 76 percent of the rate originally planned  D. You are only progressing at 24 percent of the rate originally planned

Last Answer : C. You are only progressing at 76 percent of the rate originally planned

Description : To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______  level of the WBS 1. Highest  2. Lowest  3. Major work effort  4. Third

Last Answer : 2. Lowest

Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer

Last Answer : (B) Features, Quality, Cost, Schedule, Staff

Description : Which one of the following is a valid project Key Performance Indicator (KPI)? a. Staff appraisals. b. Management buy in. c. Milestone achievement. d. Master schedule.

Last Answer : c. Milestone achievement.

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description : Scope, cost, and schedule are some of the parameters used for project negotiation.  (True/False)

Last Answer : Ans. True

Description : dimensions that must be managed on a project (A)Constraint, Quality, Cost, Schedule, Staff (B)Features, Quality, Cost, Schedule, Staff (C)Features, priority, Cost, Schedule, Staff (D)Features, Quality, Cost, Schedule, customer

Last Answer : (B)Features, Quality, Cost, Schedule, Staff

Description : The most common reason for schedule and cost overruns that surface after the project  is underway is scope creep.

Last Answer : Ans: True

Description : Jim Smith, the project manager for a high-profile project, has permitted the users to  add additional features to the systems project. The schedule and costs are now running  over. This project suffers from poor standards.

Last Answer : Ans: False

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing