The time with which direct cost does not reduce with the increase in time is known as 

A.crash time

B.normal time

C.optimistic time

D.standard time

1 Answer

Answer :

B.normal time

Related questions

Description : The time with which direct cost does not reduce with the increase in time is known as (A) Crash time (B) Normal time (C) Optimistic time (D) Standard time

Last Answer : (B) Normal time

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time D. between normal time and crash time

Last Answer : D. between normal time and crash time

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time

Last Answer : D. between normal time and crash time

Description : The time corresponding to minimum total project cost is (A) Crash time (B) Normal time (C) Optimistic time (D) Between normal time and crash time

Last Answer : (D) Between normal time and crash time

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : When planning a systems project, overly optimistic timetables are the cause of project  completion delays.

Last Answer : Ans: True

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : The time which results in the leasi, possible construction cost of an activity, is known as (A) Normal time (B) Slow time (C) Crash time (D) Standard time

Last Answer : (B) Slow time

Description : By what percentage can airbags reduce the risk of dying in a direct frontal crash? a) 30% b) 40% c) 50% d) 60%

Last Answer : a) 30%

Description : )Resource leveling attempts to : 1. Reduce resource requirements by smoothing out period-to period resource assignments.  2. Ensure that the budget abnormalities are overcome. 3. Reduce the ... Increase the amount of the project manager's authority so that budget dollars can be  appropriated.

Last Answer : 1. Reduce resource requirements by smoothing out period-to period resource assignments.

Description : Adding people to a project team in order to speed up total development time _____.  a. is a standard task in timeboxing  b. is a useful way to meet a tight deadline  c. may actually increase total development time  d. simplifies communication within the team  e. none of the above

Last Answer : c. may actually increase total development time

Description : )A new project was initiated that involves new technology and subsequently has never been  done before. What type of contract would to owner want to issue to reduce or eliminate as much  risk as possible. 1. Firm ... 2. Cost plus fix fee  3. Cost plus incentive fee  4. Lump sum  5. A and D

Last Answer : 5. A and D

Description : In Project crashing, rent and overheads are treated as  A.Significant Cost  B.Insignificant costs  C.Direct Costs  D.Indirect Costs

Last Answer : D.Indirect Costs

Description : Which of the following is a direct project cost? 1. Lighting and heating for the corporate office  2. Workers Compensation insurance  3. Piping for an irrigation project  4. A and B

Last Answer : 3. Piping for an irrigation project

Description : In project crashing, as we systematically, crash the project, direct cost of project ______ a. Increases b. Decreases c. Remain same d. None of the above

Last Answer : a. Increases

Description : Which one of the following statements is true? a. An increase in project scope is likely to increase project cost. b. A decrease in the project time is likely to increase project quality. c. ... to decrease project cost. d. A decrease in the project cost is likely to decrease project time.

Last Answer : a. An increase in project scope is likely to increase project cost.

Description : Which one of the following statements is true?  a. An increase in project scope is likely to increase project cost.  b. A decrease in the project time is likely to increase project quality.  c. ... to decrease project cost.  d. A decrease in the project cost is likely to decrease project time.

Last Answer : a. An increase in project scope is likely to increase project cost.

Description : During the planning development process, at times it is necessary to make certain assumptions to enhance the project plan when the data is not available. In regard to making those assumptions, ... upon historical data used for the project.  4. Senior management predefines the budget constraints.

Last Answer : 1. The assumptions will be considered as true, real, or certain.

Description : What is the most accurate method of obtaining project information that can reduce the amount  of risk? 1. Observations on the current project  2. Determining the risk by using brainstorming ... from previous projects that were similar in nature  4. Sensitivity analysis  5. Delphi technique.

Last Answer : 3. The use of historical data from previous projects that were similar in nature

Description : Identify the incorrect statement in connection with working capital management. A. Long-term funds are more expensive than short-term funds but also riskier B. The objectives of ... fluctuating current assets E. Aggressive financing policies increase profitability at the cost of higher risk

Last Answer : A. Long-term funds are more expensive than short-term funds but also riskier

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : What do leaders do?  A. Inspire, trust, and challenge the status quo.  B. Dictate the team C. Direct people and behavior. D. Control people

Last Answer : A. Inspire, trust, and challenge the status quo.

Description : Setting the number of defects before the lot is rejected, is a direct responsibility of : 1. a functional worker  2. the project manager  3. management  4. the accounting department

Last Answer : 3. management

Description : Which one is a true statement relating to project communications? a. A project sponsor is responsible for all communication methods and media. b. Different stakeholders typically have different communication needs ... project. d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : ____ structures are typically used in businesses that primarily sell and produce standard  products and seldom conduct external projects.

Last Answer : Ans. Functional-type organisation

Description : The advantage of following the IEEE Standard for drawing up a Project Management Plan (SPMP) - see IEEE Standard 1059.1 1987 - is a) It is drawn up by representatives from major  ... each organisation for a  particular applicationarea, development team or  technique. e) All of the above.

Last Answer : e) All of the above.

Description : Which one is a true statement relating to project communications?  A. A project sponsor is responsible for all communication methods and media.  B.Different stakeholders typically have different communication ... project.  D. Email is the only way to communicate with large numbers of people

Last Answer : B.Different stakeholders typically have different communication needs

Description : Unlike traditional Work Breakdown Structures (WBS), evolutionary WBSs are  a. organized in a standard manner across all projects  b. created in an iterative and incremental manner  c. designed so one can compare the current project to past projects  d. all of the above  e. none of the above

Last Answer : d. all of the above

Description : A(n) ____________ is a measure of program size based on the number and  complexity of inputs, outputs, queries, files, and program interfaces.  a. function point  b. line of code  c. project plan  d. standard module  e. workplan

Last Answer : a. function point

Description : Which one is a true statement relating to project communications?  a. A project sponsor is responsible for all communication methods and media.  b. Different stakeholders typically have different communication ... project.  d. Email is the only way to communicate with large numbers of people.

Last Answer : b. Different stakeholders typically have different communication needs.

Description : A project planning methodology is any structured approach used to guide the project team  during development of the project plan. What is an example of this methodology? 1. Standard forms or templates.  2. Upper management involvement  3. Functional work authorizations 4. Stakeholders skills

Last Answer : 1. Standard forms or templates.

Description : The major type(s) of standard warranty(ies) that are used in the business environment is(are): 1. express  2. implied  3. negotiated  4. a and b

Last Answer : 4. a and b

Description : Political unrest, budget overruns, size and complexity of the project  Answer: B  (8)Decision trees are best used for : 1. Determining the interaction of the amount at stake and the expected ... and the associated events  4. A flow chart which determines the standard deviation of the risk event

Last Answer : 3. An illustration of how to see the interactions between decisions and the associated events

Description : Which is the Estimation size should be known? a. Time estimation b. Effort estimation c. Cost estimation d. size estimation

Last Answer : b. Effort estimation

Description : )The fixed price contract is advantageous to the buyer because it: 1. requires extremely well defined specifications  2. requires formal procedures for scope changes  3. contractor assumes financial and technical risk  4. has a known cost

Last Answer : 3. contractor assumes financial and technical risk

Description : The return available by investing the capital elsewhere is known as (A) profit rate (B) discount rate (C) opportunity cost (D) return on investment

Last Answer : (C) opportunity cost

Description : The probability of completing the project can be estimated based upon the ____ . (A) Uniform distribution curve (B) Normal distribution curve. (C) U-shaped distribution curve (D) None of the above

Last Answer : (B) Normal distribution curve.

Description : The probability of completing the project can be estimated based  upon the . (A)Uniform distribution curve (B)Normal distribution curve. (C)U-shaped distribution curve (D)None of the above

Last Answer : (B)Normal distribution curve.

Description : Michelle has decided to use a shortcut to determine the complexity of the project she  is currently managing. She has assigned the adjusted project complexity (PCA) a value  of .65. She has determined that ... _____.  a. bi-lateral  b. complex c. microconvergent  d. normal  e. very simple

Last Answer : e. very simple

Description : . A normal system with 400 unadjusted function points would have _____ adjusted  function points when the shortcut method is use to determine the complexity of the  project.

Last Answer : c. 400

Description : Communication management: 1. Is important only in projects involving telephone, television, radio, or newspaper production  facilities and operations  2. Is not a big problem for people with normal ... . Involves the originator, the message, the medium and the receiver  4. Preparing an agenda

Last Answer : 3. Involves the originator, the message, the medium and the receiver

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : Sergei, the project manager, is worried about completing the project on time. To  increase the productivity of his 15-person team he should create subteams with no more  than 10 people on a sub team.

Last Answer : Ans: True

Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.

Last Answer : b. increase as a project progresses through its life cycle.

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description :  If the break-even point lies ____ anticipated demand, implying a loss on the product, and then the product may be discontinued or, may receive additional advertising and/or be re- priced to increase demand.

Last Answer : Ans. Above

Description : You are working in CareerRide as a project manager. What will you do to minimize the risk of failure? a. Request a large budget b. You will increase the team size c. Track progress d. None of the above

Last Answer : c. Track progress