To crash a schedule you should:

1. Increase the time allowed on those tasks that have float. 

2. Try to increase expenditures of time only those tasks that are behind schedule. 

3. Replace those worker that are not performing up to par with the busy. 

4. Increase work efforts on those tasks that are on the critical path.

1 Answer

Answer :

4. Increase work efforts on those tasks that are on the critical path.

Related questions

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan

Description : )In a program or project plan, there are always revisions to account for new or missing data.  Which one of the following provides the best reason for performing a revision of the plan? 1. ... 4. Historical data on a similar project suggests that risk events are not included in the current  plan.

Last Answer : 2. Project tasks are crashed to meet their end dates

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : A critical success factor for project management is to _____.  a. create a work plan  b. follow the three steps of project management  c. identify most project tasks  d. manage the hundreds of tasks

Last Answer : e. start with a realistic assessment of the work

Description : If a production gets behind schedule, one can add more  programmers and catch up. (A) True (B)False

Last Answer : (B)False

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Marketing strategy during a recession should include 1. a reduction in the number of sales personnel 2. a reduction in the expenditures for new product development 3. a reduction in ... 4. promotional efforts that promote value and utility 5. increase in expenditures for marketing operations

Last Answer : promotional efforts that promote value and utility

Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above

Last Answer : B. only i & ii

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : The time with which direct cost does not reduce with the increase in time is known as  A.crash time B.normal time C.optimistic time D.standard time

Last Answer : B.normal time

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : The critical path  A. Is a path that operates from the starting node to the end node  B. Is a mixture of all paths.  C.Is the longest path  D.Is the shortest path

Last Answer : C.Is the longest path

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What would be the critical path if the duration of activity C increased to 10? A. ABCF B. ABCEF C. ABGHIF D. ABGHIF & ABDEF

Last Answer : A. ABCF

Description : What is the critical path through the network above? A. ABGHIF B. ABDEF C. ABGHIF& ABDEF D. AB CEF

Last Answer : B. ABDEF

Description : What Is Critical Path?

Last Answer : Critical Path is the longest path from the beginning event to the end event. The minimum time required for completing the project is the duration on the critical path.

Description : Which of the following is least likely to be part of the calculation of the terminal- year incremental net cash flow for an energy-related expansion project? A. An initial working capital ... Disposal/reclamation costs C. Capitalized expenditures D. Salvage value of any sold or disposed assets

Last Answer : D. Salvage value of any sold or disposed assets

Description : Engineering: a) Is a set of rules about developing products b) Has been around as a discipline since the early 50's c) Started as a response to the so-called Crisis' of the ... with all the  aspects of production e) Is now a mature discipline on par with other established  engineeringfields

Last Answer : d) Is an engineering discipline concerned with all the  aspects of production

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : ....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis

Last Answer : d. Network analysis

Description : CASE tool is a popular graphic depiction of the work plan that lists project tasks along a y-axis, time along an x-axis, and uses shaded boxes to represent tasks.

Last Answer : Ans: False

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : The three steps of project management are _____. a. controlling the project, directing the project, and creating the work plan  b. creating the work plan, staffing the project, and controlling ... the deliverables  e. setting the start date, estimating the time, and reading the actual time

Last Answer : b. creating the work plan, staffing the project, and controlling and directing the  project

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.

Last Answer : c. The scope of the project.

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  A.The life cycle phases  B.The logical order of tasks  C.The scope of the project  D. Project costs

Last Answer : C.The scope of the project

Description : . It is not wise to identify tasks for a current project using existing methodology,  because methodologies that have been used by an organization for other projects probably will not work for this project without extensive changes.

Last Answer : Ans: False

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True

Description : Ryan, a newly hired systems analyst/consultant, is about to begin a systems project.  Where will Ryan look first to locate the identifiable tasks he will record in his work plan?  a. ... . the project planning software available at the local bookstore  e. the website of his old college professor

Last Answer : c. the company training materials for the company methodology

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : Which one of the following is captured in the Work Breakdown Structure (WBS)?  a. The life cycle phases.  b. The logical order of tasks.  c. The scope of the project.  d. Project costs

Last Answer : c. The scope of the project.

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : In present times, the prestige level of teachers is recognized by the general public as Options: A) Above that of professional worker B) On a par with the professional class of workers C) On a par with the wage earner or labour D) Somewhere between wage earner and professional worker

Last Answer : D) Somewhere between wage earner and professional worker 

Description : What is a critical path in schedule network diagram?

Last Answer : When activity scheduling is done there will be activities whose start time and/or end times are not critical. It may be possible, due to dependencies, to start a task later than the date on the ... time. This chain of activities or the path from start to finish is known as the critical path.

Description : The time corresponding to minimum total project cost is  A. crash time B. normal time C. optimistic time D. between normal time and crash time

Last Answer : D. between normal time and crash time