A cost performance index (CPI) of 0.89 means: 

A. At this time, we expect the total project to cost 89 percent more than planned 

B. When the project is completed we will have spent 89 percent more than planned 

C. The project is only progressing at 89 percent of the rate planned 

D. The project is only getting 89 cents out of every dollar invested

1 Answer

Answer :

D. The project is only getting 89 cents out of every dollar invested

Related questions

Description : A schedule performance index (SPI) of 0.76 means:  A. You are over budget B. You are ahead of schedule  C. You are only progressing at 76 percent of the rate originally planned  D. You are only progressing at 24 percent of the rate originally planned

Last Answer : C. You are only progressing at 76 percent of the rate originally planned

Description : Amount of work completed to date compared with planned in the Earned Value  Management method is  A. Schedule Performance Index  B. Cost Performance Index  C. Percentage Complete  D .Percentage Spent

Last Answer : C. Percentage Complete

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : A project has a Profitability Index of 1.30. What does it mean?  A.The NPV is less than zero B.The payback period is more than one year  C.That the project returns Rs 1.30 for every Re 1 invested in the project  D.That IRR is 1.30 times that of the Hurdle Rate

Last Answer : C.That the project returns Rs 1.30 for every Re 1 invested in the project

Description : In which of the following cases project is in better shape?  A.When both CPI and SPI are less than 1  B.When CPI is more than 1 and SPI is less than one  C.When CPI is less than one and SPI is more than one  D.When both CPI and SPI are more than one

Last Answer : D.When both CPI and SPI are more than one

Description : Considers the total cost of ownership, or development plus support costs, for a project. A. Learning Curve Theory B. Life Cycle Costing C. Parametric Modeling D. Rate of Performance

Last Answer : B. Life Cycle Costing

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Kathryn has little experience estimating the time it will take to complete a systems  project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points  c. industry standards  d. Microsoft Project  e. more complex approach

Last Answer : c. industry standards

Description : from 1980 to 1990, the consumer price index (cpi) increased from 82.4 to 130.7 if a gallon of apple juice cost $0.95 in 1980 and the price of apple juice increased at the same rate as the cpi from 1980 to 1990 approximately how much did a gallon of apple?

Last Answer : 1.51

Description : Approximately what percentage of the project manager's time is spent in some form of  communication, such as: conferences, meetings, writing memos, reading and preparing reports, and talking with project  team members, upper ... other stalk holders? 1. 10-20%  2. 50-70%  3. 75-90%  4. 21-45%

Last Answer : 3. 75-90%

Description : Project management is a rationally planned and organised effort to achieve a specific  goal. (True/False)

Last Answer : Ans. True

Description : Why Should The Project Be Planned?

Last Answer : The main reason for planning a project is for cost expediency. Proper project planning will insure that the amount of work to be accomplished, the time allotted to satisfactory complete the work ... Proper planning allows for the assessment of the impact of change prior to implementing the change.

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 10 person-months for a systems project where the planning phase was completed in 7.5 person-months.

Last Answer : Ans: True

Description : Using typical industry standards for estimating project time schedules, the estimated  analysis phase would be 25 person-months for a systems project where the planning phase was completed in 30 person-months.

Last Answer : Ans: False

Description : . When estimating project time schedules using industry standards, the estimated  project completion time for a systems project would be _____ person-months if the actual  planning phase were completed in 6 person-months.  a. 30  b. 40  c. 17.14  d. 9  e. 50

Last Answer : b. 40

Description : How much is 2 lbs of apples each cost for 89 cents?

Last Answer : There is not enough information to answer this question. we needto know if the apples are .89 cents a pound or 89 cents each. Ifthey are 89 cents each we need to know how many are in a pound

Description : How much is 2 lbs of apples each cost for 89 cents?

Last Answer : There is not enough information to answer this question. we needto know if the apples are .89 cents a pound or 89 cents each. Ifthey are 89 cents each we need to know how many are in a pound

Description : When a project has completed the handover and closure phase: a. the project deliverables are ready for commissioning. b. the project deliverables are ready for handing over to the users. c. the project ... must be disposed of. d. the capability is now in place for the benefits to be realized.

Last Answer : d. the capability is now in place for the benefits to be realized.

Description : Which one of the following is least likely to be a success criteria? a. A target for the project to receive zero change requests. b. The date by which the project is to be completed. c. Delivery of products that meet required specifications. d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : A project includes a number of activities that must be completed in some ………… a. particular order b. sequence c. both d. all the above

Last Answer : d. all the above

Description : The work plan records and keeps track of all of the tasks that need to be accomplished  over the life of the project, listing each task, along with important information about it,  such as when it needs to be completed, the person assigned to do the work, and any  deliverables that will result.

Last Answer : Ans: True

Description : Which of the following is true regarding the project scope statement? A. The project scope statement includes a change control system that describes how to  make changes to the ... reliability of the project scope and describes  the process for verifying and accepting completed deliverables.

Last Answer : B. The project scope further elaborates the Initiating processes and serves as a basis  for future project decisions.

Description : When a project has completed the handover and closure phase:  a. the project deliverables are ready for commissioning.  b. the project deliverables are ready for handing over to the users.  c. the ... must be disposed of.  d. the capability is now in place for the benefits to be realised.

Last Answer : d. the capability is now in place for the benefits to be realised.

Description : Which one of the following is least likely to be a success criterion?  a. A target for the project to receive zero change requests.  b. The date by which the project is to be completed.  c. Delivery of products that meet required specifications.  d. The awarding of bonuses to senior management.

Last Answer : d. The awarding of bonuses to senior management.

Description : Project performance consists of (A) Time (B) Cost (C) Quality (D) All of the above

Last Answer : (C) Quality

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : Project performance consists of (A)Time (B)Cost (C)Quality (D)All of the above

Last Answer : (D)All of the above

Description : Project Manager must ensure that it develops appropriate trade off/s as  A. Time, cost and performance  B. Time, value and performance  C.Men, Materials and Machines  D.Money, Cost and Return on Investment

Last Answer : A. Time, cost and performance

Description :  A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance

Last Answer : A. Cost Baseline

Description : Fill in the blanks. It is during the ______________ phase that the decision should be  made regarding whether the project should continue. During this phase, ____________  must be considered and weighed ... . closeout, resources c. execution, performance d. planning, timing e. initiation, risk

Last Answer : e. initiation, risk

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : Which of these characteristics are used to determine the scope of a project? a. Only performance. b. Only context. c. Information objectives, function, performance d. None of the above.

Last Answer : c. Information objectives, function, performance

Description : The criteria for acceptance of a project on the basis of Profitability Index (PI) is   A.PI=0 B. PI > 0   C. PI < 0   D. PI > 1

Last Answer : D. PI > 1

Description : A performance bond should always provide what part of the contract value? 1. 10 percent  2. 25 percent  3. 50 percent  4. 100 percent

Last Answer : 4. 100 percent

Description : Which of the following represents the estimated value of the work actually  accomplished?  A. Earned value (EV)  B. Planned value (PV)  C. Actual cost (AC  D. Cost variance (CV)

Last Answer : A. Earned value (EV)

Description : Fill in the blank. The _____ is the difference between the additional money spent on  prevention and the corresponding reduction in the cost of failure. Select one: a. cost-benefit analysis b. implicit cost c. cost of quality d. variable cost e. cost-utility analysis

Last Answer : c. cost of quality

Description : Which technique is applicable when other projects in the same analogy application domain have been completed? a) Algorithmic cost modelling b) Expert judgement c) Estimation by analogy d) Parkinson’s Law

Last Answer : c) Estimation by analogy