A schedule performance index (SPI) of 0.76 means: 

A. You are over budget

B. You are ahead of schedule 

C. You are only progressing at 76 percent of the rate originally planned 

D. You are only progressing at 24 percent of the rate originally planned

1 Answer

Answer :

C. You are only progressing at 76 percent of the rate originally planned

Related questions

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Amount of work completed to date compared with planned in the Earned Value  Management method is  A. Schedule Performance Index  B. Cost Performance Index  C. Percentage Complete  D .Percentage Spent

Last Answer : C. Percentage Complete

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description :  A project with total budget cost of 30 crores is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given:  Budgeted cost of work performed (EV) = 17 ... crores What is the cost performance index?  A.0.895  B.0.81  C.0.90  D.1.12

Last Answer : A.0.895

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : In which of the following cases project is in better shape?  A.When both CPI and SPI are less than 1  B.When CPI is more than 1 and SPI is less than one  C.When CPI is less than one and SPI is more than one  D.When both CPI and SPI are more than one

Last Answer : D.When both CPI and SPI are more than one

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Subsequent to preparing ____, the team plans the project schedule and budget

Last Answer : Ans. Work Breakdown Structure

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : The Scope Baseline is: 1. the original description of the project's end results  2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data 3. the original project budget and schedule  4. a and c

Last Answer : 2. a summary description of the project's original content and end product, including basic  budgetary and time constraint data

Description : The Scope Statement should contain which of the following? 1. Project schedule  2. Project budget constraints  3. Summary of project tasks , deliverables and resources required  4. Project objectives

Last Answer : 4. Project objectives

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description :  A time-phased budget that project managers use to measure and monitor cost performance. A. Cost Baseline B. Cost Budgeting C. Cost Estimating D. Cost Variance

Last Answer : A. Cost Baseline

Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by  an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit

Last Answer : e. quality audit

Description : A performance bond should always provide what part of the contract value? 1. 10 percent  2. 25 percent  3. 50 percent  4. 100 percent

Last Answer : 4. 100 percent

Description : Scope creep is only a minor factor in projects running over schedule, and every effort  should be made to incorporate any changes into the present system if they would truly be  beneficial.

Last Answer : Ans: False

Description : The work was directed by Tribonian from 529 to 534. Originally planned as three parts (Code, Digest and Institutes), further additions are now considered as a fourth part (Novels). The present name was only adopted in 1583 when it was printed by Dionysius Gothofredus. What?

Last Answer : Corpus Juris Civilis. (Also accept Code of Justinian.)

Description :  According to PMBOK, project management process groups are iterative, which  was originally defined by Walter Shewhart and later modified by Edward Deming.  Generally, one outcome from a previous process can serve ... -Do-Check-Act cycle c. Project phases d. PM processes e. HR process cycle

Last Answer : b. Plan-Do-Check-Act cycle

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : Jim Smith, the project manager for a high-profile project, has permitted the users to  add additional features to the systems project. The schedule and costs are now running  over. This project suffers from poor standards.

Last Answer : Ans: False

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Which one of the following best describes a project stakeholder? a. A party who is concerned about the project going ahead. b. A party with an interest or role in the project or is impacted by ... of the project. d. A party who has a financial stake in the organization managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Project management is a rationally planned and organised effort to achieve a specific  goal. (True/False)

Last Answer : Ans. True

Description : Which of the following represents the estimated value of the work actually  accomplished?  A. Earned value (EV)  B. Planned value (PV)  C. Actual cost (AC  D. Cost variance (CV)

Last Answer : A. Earned value (EV)

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Why Should The Project Be Planned?

Last Answer : The main reason for planning a project is for cost expediency. Proper project planning will insure that the amount of work to be accomplished, the time allotted to satisfactory complete the work ... Proper planning allows for the assessment of the impact of change prior to implementing the change.

Description : A Project control system: 1. Monitors and controls the project's schedule, costs, scope, budgets etc  2. Is a mechanism which reacts to the current project status in order to endure ... 4. Is a system for controlling and executing project documentation in an uniform and timely  manner

Last Answer : 1. Monitors and controls the project's schedule, costs, scope, budgets etc

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : Operational audits generally have been conducted by internal and COA auditors, but may be performed by certified public accountants. A primary purpose of an operational audit is to provide: ... statements. d. A means of assurance that internal accounting controls are functioning as planned

Last Answer : A measure of management performance in meeting organizational goals

Description : Considers the total cost of ownership, or development plus support costs, for a project. A. Learning Curve Theory B. Life Cycle Costing C. Parametric Modeling D. Rate of Performance

Last Answer : B. Life Cycle Costing

Description : A project has a Profitability Index of 1.30. What does it mean?  A.The NPV is less than zero B.The payback period is more than one year  C.That the project returns Rs 1.30 for every Re 1 invested in the project  D.That IRR is 1.30 times that of the Hurdle Rate

Last Answer : C.That the project returns Rs 1.30 for every Re 1 invested in the project

Description : When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their in order to give yourself the best chance to select the mix of ... net present value (NPV) C. internal rate of return (IRR) D. payback period (PBP)

Last Answer : B. net present value (NPV)

Description : When operating under a single-period capital-rationing constraint, you may first want to try selecting projects by descending order of their in order to give yourself the best chance to select the mix of ... net present value (NPV) C. internal rate of return (IRR) D. payback period (PBP)

Last Answer : B. net present value (NPV)

Description : In case of the indivisible projects, which of the following may not give the optimum result? A. Internal Rate of Return B. Profitability Index C. Feasibility Set Approach D. All of the above

Last Answer : C. Feasibility Set Approach

Description : According to the PMBOK guide which of the following statements is right in terms  of using reserve analysis to determine a project budget ? a. Reserve analysis always plans contingency reserves ... not practical. e. Contingency reserves have never been a concern when planning a project budget.

Last Answer : . Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : According to the PMBOK guide, which of the following statements is  right in terms of using reserve analysis to determine a project budget? Select one: A. Reserve analysis always plans ... not practical. E. Contingency reserves have never been a concern when planning a project budget.

Last Answer : A. Reserve analysis always plans contingency reserves for unexpected project scope and  project costs, which are part of your project budget.

Description : Has the futility of life ever made you give up on something or not even go ahead with something you had planned?

Last Answer : answer:What futility? I find life fulfilling and highly enjoyable. There was this one time when I was close to giving up, but that’s when I met creator and, well, no one wants to hear that story…

Description : When the indication for surgery is without delay, the nurse recognizes that the surgery will be classified as a) emergency. Emergency surgery means that the patient requires immediate attention and the ... there is an indication for surgery, but failure to have surgery will not be catastrophic.

Last Answer : a) emergency. Emergency surgery means that the patient requires immediate attention and the disorder may be life-threatening.

Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer

Last Answer : (B) Features, Quality, Cost, Schedule, Staff

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which one of the following is not considered in resource management? a. Identifying resources. b. Influencing resources. c. Assigning resources to activities. d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : Which one of the following is a valid project Key Performance Indicator (KPI)? a. Staff appraisals. b. Management buy in. c. Milestone achievement. d. Master schedule.

Last Answer : c. Milestone achievement.