In which of the following cases project is in better shape? 

A.When both CPI and SPI are less than 1 

B.When CPI is more than 1 and SPI is less than one 

C.When CPI is less than one and SPI is more than one 

D.When both CPI and SPI are more than one

1 Answer

Answer :

D.When both CPI and SPI are more than one

Related questions

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : A cost performance index (CPI) of 0.89 means:  A. At this time, we expect the total project to cost 89 percent more than planned  B. When the project is completed we will have spent 89 ... at 89 percent of the rate planned  D. The project is only getting 89 cents out of every dollar invested

Last Answer : D. The project is only getting 89 cents out of every dollar invested

Description : The three different service models are together known as the _____ model of cloud computing. a) SPI b) SIP c) CPI d) All of the mentioned

Last Answer : SIP

Description : A schedule performance index (SPI) of 0.76 means:  A. You are over budget B. You are ahead of schedule  C. You are only progressing at 76 percent of the rate originally planned  D. You are only progressing at 24 percent of the rate originally planned

Last Answer : C. You are only progressing at 76 percent of the rate originally planned

Description : A project has a Profitability Index of 1.30. What does it mean?  A.The NPV is less than zero B.The payback period is more than one year  C.That the project returns Rs 1.30 for every Re 1 invested in the project  D.That IRR is 1.30 times that of the Hurdle Rate

Last Answer : C.That the project returns Rs 1.30 for every Re 1 invested in the project

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : A project has the following cash inflows Rs.34,444; Rs.39,877; Rs.25,000; and Rs.52,800 for years 1 through 4, respectively. The initial cash outflow is Rs.104,000. Which of the following four statements ... than or equal to 14%, but less than 18%. D. The IRR is greater than or equal to 18%.

Last Answer : C. The IRR is greater than or equal to 14%, but less than 18%.

Description : Which of the following statements is incorrect regarding a normal project? A. If the NPV of a project is greater than 0, then its PI will exceed 1. B. If the IRR of a project is 8%, its NPV, using ... the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Last Answer : D. If the IRR of a project is greater than the discount rate, k, then its PI will be greater than 1.

Description : A profitability index (PI) of .92 for a project means that . A. The project's costs (cash outlay) are (is) less than the present value of the project's benefits B. The project's NPV is ... is greater than 1 D. The project returns 92 cents in present value for each current rupee invested (cost)

Last Answer : C. The project's NPV is greater than 1

Description : Assume a systems development project effort calculation determines that the system  will require 240 function points. If the developers choose to implement this system in the  C programming language, approximately ... without more information  c. exactly the same  d. much greater  e. much less

Last Answer : e. much less

Description : The hurricane model implies that project estimates become more accurate as the  project's product becomes better understood.

Last Answer : Ans: True

Description : Who among the following are less able to influence a project? (A) Consultants (B) Contractors (C) Stakeholders (D) Project team

Last Answer : (B) Contractors

Description : )Which of the following is NOT one of the primary needs for good project scheduling? 1. Cutting costs and reducing time  2. Decreasing the time required for decision making  3. Eliminating idle time  4. Developing better trouble shooting procedures.

Last Answer : 4. Developing better trouble shooting procedures.

Description : In the maintenance phase the product must be tested against  previous test cases. This is known as testing. (a) Unit (b) Integration (c)Regression (d) Module (e) Beta

Last Answer : (c)Regression

Description : Which one of the following best describes users? a. Providers of both strategic and tactical direction to the project. b. Those intended to receive benefits or operate outputs. c. Facilitators of an appropriate issue resolution procedure. d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : Which of the following can estimate size of project directly from problem specification? A. LOC B. Function Point Metric C. Both D. None

Last Answer : B. Function Point Metric

Description : Marco is an investor, and Jon is a project team member. Both have  intensive technical background for the project that you are managing.  However, recently they have disagreed on the next step to take ... b. Stakeholders c. The project team d. Investors e. The board of trustees of this company

Last Answer : c. The project team

Description : In tracking, reporting and controlling, the process engage whether the project results are in accordance with a. project plans b. performance specification c. both a, b d. none of the above

Last Answer : c. both a, b

Description : In resource allocation, the resources are allocated to a project in  order that the…...............are attained a. Goals b. Objectives c. Both a, b d. None of the above

Last Answer : c. Both a, b

Description : In project planning, it explains.....................that are needed to for the growth of product. a. a series of actions b. steps c. both a, b d. none of the above

Last Answer : c. both a, b

Description : Contract documentation is an input to both the Close Project and Contract Closure  processes. Contract documentation might include all of the following except for which  one?  A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents

Last Answer : D. Procurement audit documents

Description : Which one of the following best describes users?  a. Providers of both strategic and tactical direction to the project.  b. Those intended to receive benefits or operate outputs.  c. ... of an appropriate issue resolution procedure.  d. Those providing full-time commitment to the project.

Last Answer : b. Those intended to receive benefits or operate outputs.

Description : To successfully manage a project, the PM must play both a manager and leadership role. In the manager role the PM will do all but which of the following: 1. Develop procedures  2. Align people  3. Produce results for stakeholder  4. Focus on the organization and its structure 5. Both b and d

Last Answer : 2. Align people

Description : From HR perspective, the project manager's responsibility in the planning role includes: 1. Hiring the team  2. Developing work schedules 3. Forecasting  4. Feedback sessions  5. Both b and c

Last Answer : 5. Both b and c

Description : (1)Milestones established by the customer must be adhered to by: 1. Project manager  2. Functional managers  3. The customer 4. Both a and b

Last Answer : 4. Both a and b

Description : The basic nature of a project is a/an _____ one. (A) permanent (B) temporary (C) (A) or (B) (D) Both (A) and (B)

Last Answer : (B) temporary

Description : The basic nature of a project is a/an _____ one. (A) permanent (B) temporary (C) (A) or (B) (D) Both (A) and (B)

Last Answer : (B) temporary

Description : Cash inflows from a project include: A. tax shield of depreciation B. after tax operating profits C. raising of funds D. Both (a) and (b)

Last Answer : D. Both (a) and (b)

Description : Which one of the following statements is true? a. Business-as-usual activities cannot be improved. b. Business-as-usual activities are more difficult to manage than projects. c. Projects are ... change to business-as-usual. d. A project is always the starting point for operation refinement

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual.

Description : Which of the following statements is true regarding contracts? Select one: a. They are the filters through which project members screen information that is shared. b. They do not lend ... information-rich  environment will suffer. e. Contracts promote the growth of a trusting project culture.

Last Answer : b. They do not lend themselves to create an environment of trust.

Description : Sergei, the project manager, is worried about completing the project on time. To  increase the productivity of his 15-person team he should create subteams with no more  than 10 people on a sub team.

Last Answer : Ans: True

Description : All of the following statements are true regarding risk events except which one?  Choose the least correct answer. A. Project risks are uncertain events.  B. If risks occur, they can ... that have more perceived rewards to the organization than the consequences of  the risk should be accepted.

Last Answer : C. Unknown risks are threats to the project objectives, and nothing can be done to  plan for them.

Description : How does a project differ from an ongoing work effort?  A. It is unique B. It involves more than one person C. It has a project manager D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Last Answer : D. It is not a repetitive process that follows an organization’s existing procedures  (Ans.)

Description : Which one of the following statements is true?  a. Business-as-usual activities cannot be improved.  b. Business-as-usual activities are more difficult to manage than projects.  c. Projects are ... change to business-as-usual.  d. A project is always the starting point for operation refinement.

Last Answer : c. Projects are transient endeavours that bring about change to business-as-usual

Description : Expert power is the power that comes from the amount of knowledge a person has obtained in  a specific area. This type ofpower is: 1. Critical to a project manager because the PM has to have ... by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Last Answer : 4. Used sparingly if at all by the PM because the PM cannot stay current on all areas of  expertise and also manage the project

Description : The estimated benefits from a capital budgeting project are expected as cash flows rather than income flows because . A. it is more difficult to calculate income flows than cash flows B. it ... is central to the firm's capital budgeting decision C. this is required by the accounting profession

Last Answer : B. it is cash, not accounting income, that is central to the firm's capital budgeting decision

Description : What is a Serial Peripheral Interface (SPI) in Arduino?

Last Answer : Serial Peripheral Interface (SPI) in Arduino is a synchronous communication protocol used to transfer data between microcontrollers and peripheral devices.

Description : What is a SPI bus in Arduino?

Last Answer : A SPI bus in Arduino is a communication protocol used to connect multiple devices to an Arduino board using four wires.

Description : If my DDWRT SPI firewall is enabled on the router, do I need to also engage the Windows (or another) firewall?

Last Answer : Here’s good article on this topic why you need separate firewall on how to geek

Description : The appearance of an image on a website is dependent upon? A. The DPI of the printer B. The SPI of the printer C. The PPI of the monitor D. The SPI of the monitor

Last Answer : C. The PPI of the monitor

Description : Which protocol is lightweight? A. MQTT B. HTTP C. CoAP D. SPI

Last Answer : A. MQTT

Description : Which protocol is lightweight? A. MQTT B. HTTP C. CoAP D. SPI

Last Answer :  A. MQTT 

Description : _____________ is a computing concept that describes the idea of everyday physical objects being connected to the internet. A. IOT (Internet of Things) B. MQTT C. COAP D. SPI

Last Answer : A. IOT (Internet of Things) 

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : The conceptual estimate is developed with the least amount of knowledge. When  more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate

Last Answer : c. rough order of magnitude (ROM) estimate

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities