In which of the following cases project is in better shape?
A.When both CPI and SPI are less than 1
B.When CPI is more than 1 and SPI is less than one
C.When CPI is less than one and SPI is more than one
D.When both CPI and SPI are more than one
A.When both CPI and SPI are less than 1
B.When CPI is more than 1 and SPI is less than one
C.When CPI is less than one and SPI is more than one
D.When both CPI and SPI are more than one