What is the default view of a new project in MS project? 

A. Gantt View

B. Resource Graph 

C. Network View 

D.: Workbook View

1 Answer

Answer :

A. Gantt View

Related questions

Description : If you would like to see a list of resources and the tasks that people are assigned to.  What view best displays this information?  A.Resource Sheet  B. Task Usage  C. Gantt Chart  D.: Resource Usage

Last Answer : C. Gantt Chart

Description : Risk Event Graph is having following on X axis  A.Gantt Chart  B.Work Break Down Structure  C.Project Life Cycle  D.Splitting

Last Answer : C.Project Life Cycle

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : A Gantt chart is used to show a project timeline diagrammatically. A. True B. Fa lse

Last Answer : A. True

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : The network diagram is the best tool for demonstrating:  A. Schedule variances B. Resource requirements C. The sequence of project activities  D. Schedule performance over time

Last Answer : C. The sequence of project activities

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description : The statistical tool that depicts a project’s tasks and the relationships between those tasks is  known as (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (D) PERT chart

Description : What Is A Gantt Chart?

Last Answer : A Gantt Chart is a way of illustrating multiple, time-based activities on a horizontal time-line.

Description : Do it because I said to” is the mantra for project managers who use _____ as the  default approach to resolve conflict. Select one: a. collaborating b. compromising c. accommodating d. forcing e. avoiding

Last Answer : d. forcing

Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... .  A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar

Last Answer : A. Crashing

Description : By default, a workbook in Excel contains how many worksheets? -Technology

Last Answer : (b) 3 worksheets are present in every workbook by default.

Description : Ctrl + Page up (In Ms - Excel) is used for: a) Move to the previous worksheet in the workbook b) Insert a new worksheet into the current workbook c) Select the current worksheet and the next worksheet d) None of These

Last Answer : a) Move to the previous worksheet in the workbook

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description :  Which of the following is the most important element of Project Management Plan that is useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : Project Human Resource Management ensures that the most appropriate manpower with necessary skills is deployed for effective execution of the desired project. (True/False)

Last Answer : Ans. True

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : In resource allocation, the resources are allocated to a project in  order that the…...............are attained a. Goals b. Objectives c. Both a, b d. None of the above

Last Answer : c. Both a, b

Description : What are decision models?  A. Project selection criteria B. Project selection methods C. Project selection committees D. Project resource and budget selection methods

Last Answer : B. Project selection methods

Description : Which of the following types of Organizational Charts can be BEST used to track project  costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Which of the following is the most important element of Project Management Plan that is  useful in HR Planning process: A. Risk Management activities B. Quality Assurance activities C. Activity Resource requirements D. Budget Control activities

Last Answer : C. Activity Resource requirements

Description : )Resource leveling attempts to : 1. Reduce resource requirements by smoothing out period-to period resource assignments.  2. Ensure that the budget abnormalities are overcome. 3. Reduce the ... Increase the amount of the project manager's authority so that budget dollars can be  appropriated.

Last Answer : 1. Reduce resource requirements by smoothing out period-to period resource assignments.

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : In MS - Excel, Move to the next worksheet in the workbook can be done through: a) Ctrl + Page Down b) Ctrl + Page Up c) Ctrl + F3 d) None of These

Last Answer : a) Ctrl + Page Down

Description : Project closure involves releasing the final product to the customer, handing over the  project documentation, manuals, source code, and network layouts. (True/False)

Last Answer : Ans. True

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : In corporate costs, cost incurred to finance construction of new equipment are classified as A. treasury costs B. discretionary costs C. human resource management costs D. corporate administration costs

Last Answer : A. treasury costs

Description : )The process control charts are used: 1. to graph what typically focuses on the prevention of a problem  2. to detect the problem  3. to reject the problem  4. to determine the acceptability of the same

Last Answer : 1. to graph what typically focuses on the prevention of a problem

Description : Which one of the following is not considered in resource management?  a. Identifying resources.  b. Influencing resources.  c. Assigning resources to activities.  d. Matching resources to the schedule.

Last Answer : b. Influencing resources.

Description : The strategy used to correct resource over-allocations by balancing demand for resources and  the available supply is known as (A) resource assignment (B) resource leveling (C) resource splitting (D) resource scheduling

Last Answer : (B) resource leveling

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : Explain how Gantt chart is used in project planning with proper example. 

Last Answer : Use of Gantt Chart in Project Planning: Gantt Chart is a project planning tool that can be used to represent the timing of tasks required to complete a project. Because Gantt chats are simple to ... a chart, which are used to record the actual operating times and delays of workers and machines.

Description : Explain GANTT chart and its application for project tracking with an example. 

Last Answer : When creating software project schedule, we begin with a set of tasks. If automated tools are used, the work breakdown is input as a task network or task outline. Effort, duration and start date are then ... can also use Gantt charts to get an overview of how things are rolling on the work front. 

Description : Is there a way to change my default font in MS Word for mac?

Last Answer : When you go into the fonts menu, is there a “Set as Default” button on the bottom right?

Description : What kind of documents does MS-Word allow to be created by default ?

Last Answer : MS-Word allows creation of Document file (.doc) by default.

Description : What kind of documentation is allowed by MS - Excel default worksheet ( .xls) ?

Last Answer : MS-Excel allows creation of Worksheet (.xls) documents by default worksheet ( .xls ).

Description : What kind of documentation does MS-PowerPoint allow to create by default presentation file ( .ppt) ?

Last Answer : MS-PowerPoint allows creation of Presentation file (.ppt) by default presentation file (.ppt) .

Description : What is created when you use F11 shortcut key while creating a chart in MS Excel: a) A default chart b) A 2 dimensional column chart c) A 2 dimensional bar chart d) A 3 dimensional line chart e) None of The Above

Last Answer : b) A 2 dimensional column chart

Description : Why are changes to the project scope necessary? Select one: a. To understand reports b. To reflect new information c. To begin planning the project d. To teach team members what they need to know about their jobs e. To establish a trusting project culture

Last Answer : b. To reflect new information

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : When a project manager starts to plan a new project budget, the cost  of which project management process group is expected to be lowest? Select one: a. Initiating b. Executing c. Monitoring and controlling d. Closing e. Planning

Last Answer : d. Closing