The matrix organisation is conducive for __

1 Answer

Answer :

Ans. Project management

Related questions

Description : In the matrix-type organisation, ____ provide the resources needed and the ____ is  responsible for the project results.

Last Answer : Ans. The functional managers, project manager

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Project planning involves three processes:____ review, and __

Last Answer : Ans. Identification, analysis

Description : ____ is the most common type of project organisation.

Last Answer : Ans. Matrix-type organisation

Description : helps an organisation to prevent failures in projects.

Last Answer : Ans. Project management

Description : Project cycle is a collection of generally sequential project phases whose description and  order of occurrence are determined by the control needs of the organisation or  organisations involved in the project. (True/False)

Last Answer : Ans. True

Description : The advantage of following the IEEE Standard for drawing up a Project Management Plan (SPMP) - see IEEE Standard 1059.1 1987 - is a) It is drawn up by representatives from major  ... each organisation for a  particular applicationarea, development team or  technique. e) All of the above.

Last Answer : e) All of the above.

Description : Which of the following items should not be included in the  project management plan? a) The techniques and case tools to be used b) Detailed schedules, budgets and resource ... development  organisation, project responsibilities, managerial  objectives and priorities e) None of the above.

Last Answer : c) The life cycle model to be used

Description : The individual or organisation who wants a product to be  developed is known as the: a) Developer (b) User (c)Contractor (d) Initiator (e) Client

Last Answer : (e) Client.

Description : . A portfolio can best be defined as:  a. a group of projects and programmes carried out within an organisation.  b. a group of programmes carried out under the sponsorship of an organisation ... the sponsorship of an organisation.  d. a range of products and services offered by an organisation.

Last Answer : a. a group of projects and programmes carried out within an organisation.

Description : Configuration management is best described as:  a. control in the implementation of changes to project schedules.  b. an organisation to review proposed changes to the project deliverables ... and documentation.  d. creation, maintenance and controlled change of the project deliverables.

Last Answer : d. creation, maintenance and controlled change of the project deliverables.

Description : Which one of the following best describes a project stakeholder?  a. A party who is concerned about the project going ahead.  b. A party with an interest or role in the project or is impacted by ... of the project.  d. A party who has a financial stake in the organisation managing the project.

Last Answer : b. A party with an interest or role in the project or is impacted by the project.

Description : Which of the following best describes a project environment? a. The type of organisation concerned with implementation.  b. The structured method used to control the project.  c. The context within which a project is undertaken.  d. An understanding of the risks involved in the project.

Last Answer : c. The context within which a project is undertaken.

Description : A Cost Breakdown Structure (CBS) shows costs assigned to: a. individual work packages using the Work Breakdown Structure (WBS). b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM). d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : A Responsibility Assignment Matrix (RAM) can be used to: a. define the terms of reference of the project manager. b. define the limits of the project sponsor's responsibilities. c ... response activities to project personnel. d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The document that identifies what information needs to be shared, to whom, why, when and how is called the: a. communication management plan. b. stakeholder mapping grid. c. document distribution schedule. d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Shauna has recently been appointed as a project manager for Project SkyNorth,  which is regarded as an important project in her organization. During the project  planning meeting, ... b. Matrix organization c. Functional organization d. Projectized organization e. Hierarchical organization

Last Answer : d. Projectized organization

Description : Complete the following statement. In a weak matrix environment, the  project manager, Eric, has to constantly make an effort to influence his  project team and stakeholders to ensure project success. ... managers. d. there are no functional managers. e. Eric has flexibility on authority.

Last Answer : b. Eric has no or little authority.

Description : What is considered to be the most useful skill for a project manager  who works in a matrix environment in order to achieve project goals? Select one: a. Leadership skill b. Influencing c. Conflict management skill d. Time management e. Planning skill

Last Answer : b. Influencing

Description : All of the following are true regarding the Qualitative Risk Analysis process except  which one?  A. Probability and impact and expert interview are used to help correct biases that occur  in the data ... of this process used to determine  which risks need near-term response plans.

Last Answer : C. Qualitative Risk Analysis is an easy method of determining risk probability and  impact that usually takes a good deal of time to perform.

Description : Which of the following is not true for a Responsibility Assignment Matrix (RAM): A. Defines what project team is responsible for each WBS component B. Defines what project member is ... . Text description of roles, responsibilities, authorities D. Defines all people associated with each activity

Last Answer : C. Text description of roles, responsibilities, authorities

Description : Which of the following types of Organizational Charts can be BEST used to track project  costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description :  A Cost Breakdown Structure (CBS) shows costs assigned to:  a. individual work packages using the Work Breakdown Structure (WBS).  b. individual resources using the Work Breakdown Structure ... Assignment Matrix (RAM).  d. individual deliverables using the Responsibility Assignment Matrix (RAM)

Last Answer : a. individual work packages using the Work Breakdown Structure (WBS).

Description : A Responsibility Assignment Matrix (RAM) can be used to:  a. define the terms of reference of the project manager.  b. define the limits of the project sponsor's responsibilities.  ... response activities to project personnel.  d. allocate work packages to those responsible for project work.

Last Answer : d. allocate work packages to those responsible for project work.

Description : The document that identifies what information needs to be shared, to whom, why, when and  how is called the: a. communication management plan.  b. stakeholder mapping grid.  c. document distribution schedule.  d. responsibility assignment matrix.

Last Answer : a. communication management plan.

Description : The project manager has the most authority in the __________________ type of  organization. 1. Project expediter  2. Matrix  3. Projectized organization  4. Functional

Last Answer : 3. Projectized organization

Description : What material, color, and other features would be most conducive to keeping a countertop that is both beautiful and sanitary?

Last Answer : Off white quartz. Mild cleanser.

Description : Is it me, or is sitting in a car conducive with being gassy?

Last Answer : Why was this question on my “Questions for You”?! Anyway, I’ve never really had that problem.

Description : What is basic form of competition is most conducive to the use of marketing mix?

Last Answer : So, what does competition mean in the field of marketing? Competition is the rivalry between companies selling similar products and services with the goal of achieving revenue, profit, and ... a competitive advantage, such as product offerings at lower prices or value added benefits. Identifyin

Description : Which one of the following is not conducive to the formation of deltas? (a) Currents and Tides (b) Calm winds (c) Absence of large lakes along the course of the river (d) Sheltered coastline

Last Answer : Ans: (a)

Description : The most conducive surface for dropwise condensation to occur is the __________ surface. (A) Coated (B) Oily (C) Glazed & polished (D) Smooth

Last Answer : (B) Oily

Description : The education aims at the fullest realization of all the potentialities of children. It implies that (a) They should provide suitable opportunities and favorable environmental facilities, which are conducive to ... that their attitudes are helpful, encouraging and sympathetic. (d) All of the above

Last Answer : (a) They should provide suitable opportunities and favorable environmental facilities, which are conducive to the maximum growth of children.

Description : What is the basis of the Scientific Method? a. To test hypotheses in conditions that are conducive to its success b. To formulate a research problem and disprove the hypothesis c. To formulate a ... the hypothesis. d. To test hypotheses and if they are disproved, they should be abandoned completely

Last Answer : c. To formulate a research problem, test the hypothesis in carefully controlled conditions that challenge the hypothesis.

Description : comparing the lecture and developmental lessons which one of the following is false? Options: A) There is more public developmental lesson B) It t is more difficult to ascertain public learning in ... to largest class D) Slow children derive more benefits form a lecture than brighter children do

Last Answer : D) Slow children derive more benefits form a lecture than brighter children do 

Description : For harmonious development of the personality of the child, parent should Options: A) overprotect the child. B) regularly compare the child with other children. C) provide conducive environment at home. D) engage qualified teachers.

Last Answer : C) provide conducive environment at home. 

Description : In which of the following systems, few rules over all

Last Answer : Oligarchy

Description : Herodatus is considered as

Last Answer : Father of History

Description : Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job. (A) Algorithmic model (B) Expert judgment (C) Bottom-up (D) Top down

Last Answer : (C) Bottom-up

Description : Tool used for comparison of the proposed project to complete projects of a similar nature whose costs are known. (A) Algorithmic model (B) Expert judgment (C) Top down (D) Analogy

Last Answer : (D) Analogy

Description : The entire process of a project may be considered to be made up on number of sub process placed in different stage called the (A) Technical key resources (B) Work key structure (C) Work Breakdown Structure (WBS). (D) None of the above

Last Answer : (C) Work Breakdown Structure (WBS).

Description : In the initial stage of the project the probability of completing the project is ___ . (A) Zero (B) High (C) Low (D) Any of the above

Last Answer : (C) Low

Description : The probability of completing the project can be estimated based upon the ____ . (A) Uniform distribution curve (B) Normal distribution curve. (C) U-shaped distribution curve (D) None of the above

Last Answer : (B) Normal distribution curve.

Description : Resorce requirement in project becomes constant while the project is in its _____ progress stage. (A) 40 to 55% (B) 55 to 70% (C) 70 to 80% (D) 80 to 95%

Last Answer : (D) 80 to 95%

Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer

Last Answer : (B) Features, Quality, Cost, Schedule, Staff

Description : Project performance consists of (A) Time (B) Cost (C) Quality (D) All of the above

Last Answer : (C) Quality

Description : Design phase consist of (A) Input received (B) Output received (C) Both (A) and (B) (D) None of the above

Last Answer : (C) Both (A) and (B)

Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1

Last Answer : (A) 3-2-1-4