Which one of the following is a valid project Key Performance Indicator (KPI)?

a. Staff appraisals.

b. Management buy in.

c. Milestone achievement.

d. Master schedule.

1 Answer

Answer :

c. Milestone achievement.

Related questions

Description : Which one of the following is a valid project Key Performance Indicator (KPI)?  a. Staff appraisals.  b. Management buy in.  c. Milestone achievement.

Last Answer : c. Milestone achievement.

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Which of the following is typically a written document that defines what work  will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure

Last Answer : a. Scope of work (SOW)

Description :  A project budget estimate that is developed with the least amount of  knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate

Last Answer : c. Conceptual estimate

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : KPI Stands for 1. Key Performance Indicator 2. Key Performance Index 3. Key Product Indicator 4. Key Process Index

Last Answer : Key Performance Indicator

Description : Five dimensions that must be managed on a project (A) Constraint, Quality, Cost, Schedule, Staff (B) Features, Quality, Cost, Schedule, Staff (C) Features, priority, Cost, Schedule, Staff (D) Features, Quality, Cost, Schedule, customer

Last Answer : (B) Features, Quality, Cost, Schedule, Staff

Description : dimensions that must be managed on a project (A)Constraint, Quality, Cost, Schedule, Staff (B)Features, Quality, Cost, Schedule, Staff (C)Features, priority, Cost, Schedule, Staff (D)Features, Quality, Cost, Schedule, customer

Last Answer : (B)Features, Quality, Cost, Schedule, Staff

Description : Five dimensions that must be managed on a project A. Constraint, Quality, Cost, Schedule, Staff B. Features, Quality, Cost, Schedule, Staff C. Features, priority, Cost, Schedule, Staff D. Features, Quality, Cost, Schedule, customer

Last Answer : B. Features, Quality, Cost, Schedule, Staff

Description : Which one of the following illustrates why effective project management is beneficial to an organization? a. It utilizes resources as and when required under direction of a project manager. b. ... d. It ensures that the chief executive is accountable for the achievement of the defined benefits.

Last Answer : a. It utilizes resources as and when required under direction of a project manager.

Description : Which one of the following best describes project success criteria? a. Actively seeking some senior management support. b. Measures by which the success of the project is judged. c. Achievement of milestones. d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.

Description : Which one of the following best describes project success criteria?  a. Actively seeking some senior management support.  b. Measures by which the success of the project is judged.  c. Achievement of milestones.  d. A motivated project team.

Last Answer : b. Measures by which the success of the project is judged.

Description : The project manager works with the project sponsor to identify the necessary resources  and team members needed to further develop the key project parameters – Cost, Scope,  Schedule, and Quality (CSSQ). (True/False)

Last Answer : Ans. True

Description : What are the key components in the "Triple constraint Triangle"?  A. Scope, Schedule, Cost, Project Manager B. Scope, Time, Cost, Project (Ans.) C. Time, Money, Scope, Project D. Project Manager, Time, Scope, Money

Last Answer : B. Scope, Time, Cost, Project (Ans.)

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a) Specification delays b) Product competition c) Testing d) Staff turnover

Last Answer : c) Testing

Description : Which of the following is not considered as a risk in project management? a. Specification delays b. Product competition c. Testing d. Staff turnover

Last Answer : c. Testing

Description : A review undertaken to decide whether a project should proceed into its next phase is known as a: a. gate review. b. feasibility study. c. milestone review. d. evaluation review.

Last Answer : a. gate review.

Description : Work that continues throughout the project and does not relate to  any specific phase of development is termed a(n) a) Milestone b) Project function c) Activity d) Task e) Baseline.

Last Answer : b) Project function

Description : A review undertaken to decide whether a project should proceed into its next phase is known  as a:  a. gate review.  b. feasibility study.  c. milestone review.  d. evaluation review.

Last Answer : a. gate review.

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : The most significant challenge to project managers is _____.  a. lack of project management training  b. no one really understands how to manage a complex systems development project  ... tools that can assist in controlling project progress  d. unrealistic schedule demands by project sponsors

Last Answer : d. unrealistic schedule demands by project sponsors

Description : What is the definition of Earned Value Management? A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.  B. ... approach that combines the scope and cost baseline into a project performance and  progress measurement tool.

Last Answer : A. An approach that combines the scope, schedule, and cost baseline into a project  performance and progress measurement tool.

Description : Earned value management integrates scope, cost, and schedule measures to:  A. assess project performance and progress.  B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.

Last Answer : A. assess project performance and progress.

Description : A Project with a total funding of $100,000 finished with a BAC value of $95,000. What term  can BEST describe the difference of $5,000? A. Cost Variance B. Management Overhead C. Management Contingency Reserve D. Schedule Variance

Last Answer : C. Management Contingency Reserve

Description : In the project management theory, balancing scope, schedule, and cost goals is often termed as (A) triangular dilemma (B) triple constraint (C) fundamental trade-off (D) project portfolio management

Last Answer : (B) triple constraint

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : What is a key aspect of Project Manger leadership?  A. Great management skills  B. Negotiation  C. Creating a clear vision for the team to follow  D. Time management

Last Answer : C. Creating a clear vision for the team to follow

Description : Which one of the following is the last step of project closings? Select one: a. The client has accepted the product. b. Archives are complete. c. The client appreciates your product. d. Lessons learned are documented. e. Temporary staff is released.

Last Answer : b. Archives are complete.

Description : Adding staff to a project to shorten the project’s length is usually a wise move,  because adding staff normally translates into increased productivity

Last Answer : Ans: False

Description : To complete a 20 person-month project in 10 months, a team should have 4 full-time  staff members assigned to the project.

Last Answer : Ans: False

Description : To identify the tasks for a work plan the project manager can _____.  a. control and direct the project  b. estimate the size, staff the project, and remember technical skills  c. establish a ... of the SDLC and the steps that occur in each  e. set conservative numbers for the project software

Last Answer : d. list the four phases of the SDLC and the steps that occur in each

Description : People participated in or affected by project activities are known as (A) staff (B) stakeholders (C) project team (D) project managers

Last Answer : (B) stakeholders

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : . If the Earned Value is equal to Actual Cost, it means: A. Project is on budget and on schedule B. Schedule Variance Index is 1 C. There is no schedule variance D. There is no cost variance

Last Answer : D. There is no cost variance

Description : In the project planning, which of the following is considered as the most basic parameter  based on which all other estimates are made? A. project size B. project effort C. project duration D. project schedule

Last Answer : A. project size

Description : When calculating EVM, Peter noticed that the cumulative planned value is 150%  of the cumulative earned value. What does this mean? Select one: a. SPI1, so the project is OK to complete on time. c. SPI1, so the project is behind schedule. e. SPI>1, so the project is on schedule.

Last Answer : a. SPI

Description : Which of the following project baselines provides the basis for measurement of  the expected cash flow against requirements over time and is often displayed as an  S curve? Select one: a. Schedule baseline b. Cost performance baseline c. Scope baseline d. Plan baseline e. Initiation baseline

Last Answer : b. Cost performance baseline

Description : Subsequent to preparing ____, the team plans the project schedule and budget

Last Answer : Ans. Work Breakdown Structure

Description : Scope, cost, and schedule are some of the parameters used for project negotiation.  (True/False)

Last Answer : Ans. True

Description : The most common reason for schedule and cost overruns that surface after the project  is underway is scope creep.

Last Answer : Ans: True

Description : Jim Smith, the project manager for a high-profile project, has permitted the users to  add additional features to the systems project. The schedule and costs are now running  over. This project suffers from poor standards.

Last Answer : Ans: False

Description :  The project team has just determined that the deadline for completion will not be met.  In order to deliver a high quality system on schedule, the team has requested that the  features be ... that a fixed deadline be imposed for the project. This technique  is referred to as SDLC methodology.

Last Answer : Ans: False

Description : Estimates from the planning stage will need to be refined as the project progresses,  because it is virtually impossible to develop an exact assessment of the project’s schedule  before the analysis and design phases are conducted.

Last Answer : Ans: True

Description : The _____ is a dynamic schedule that logs and monitors all of the tasks that need to be  accomplished for the length of the project.  a. margin of error  b. project manager  c. project objective d. timebox  e. work plan

Last Answer : e. work plan