Pick up the correct statement from the following:
(A) Programme Evaluation and Review Technique, is event oriented
(B) Programme Evaluation and Review Technique is not event oriented
(C) Critical Path Method is event oriented
(D) Critical Path method is event oriented

1 Answer

Answer :

(A) Programme Evaluation and Review Technique, is event oriented

Related questions

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : PERT stand for: a. Performance Evaluation Review Technique b. Programme Evaluation Review Technique c. Programme Evaluation Research Technique

Last Answer : b. Programme Evaluation Review Technique

Description : For a project manager to have an effective means of identifying and communicating the planned activities and their interrelationships, he must use a network technique. One of the network ... evaluation review technique c. Path evaluation review technique d. Project execution review technique

Last Answer : b. Program evaluation review technique

Description : In PERT (Project Evaluation and Review Technique) method Expected time (Te) is  A. (To+Tp+4Tm)/6  B. (To+Tp+2Tm)/6  C. (To+Tp+Tm)/6  D. (Tm+Tp+4To)/6

Last Answer : A. (To+Tp+4Tm)/6

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : PERT stands for __________. A. Programme Evaluation and Research Techniques. B. Project Evaluation and Review Techniques. C. Programme Evaluation and Review Techniques. D. Project Evaluation and Research Techniques.

Last Answer : C. Programme Evaluation and Review Techniques.

Description : PERT (Project Evaluation and Review Technique) analysis is based on  A. Optimistic time, Pessimistic time and Most likely time  B.Pessimistic time, Optional time, Maximum time  C.Optimistic time, Efficient time, Most likely time  D.Minimax time, Optimistic time and harmonic time

Last Answer : A. Optimistic time, Pessimistic time and Most likely time

Description : . The PERT in project management means program evaluation and _____ technique. (A) resource (B) reconciliation (C) reconsideration (D) review

Last Answer : (D) review

Description : The technique for establishing and maintaining priorities among the various jobs of a project, is known (A) Event flow scheduling technique (B) Critical ratio scheduling (C) Slotting technique for scheduling (D) Short interval scheduling

Last Answer : (B) Critical ratio scheduling

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : CPM is (A) Synthesising in concepts (B) Is built of activities oriented programme (C) Is based on time estimate (D) All the above

Last Answer : (D) All the above

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Pick up the correct statement from the following: (A) The direction of the littoral drift depends upon the direction of the wave with respect to the coastline (B) The direction of a river opening to the sea ... avoid a build up of sand on one side and erosion on the other (D) all of the above

Last Answer : (D) all of the above

Description : Pick up the correct statement from the following: (A) In remote sensing technique, the observation place, is called a platform (B) Platforms may be either stationary or mobile (C) Spatial resolution of the imaging system becomes poorer with increase of platform height (D) All of these

Last Answer : Answer: Option D

Description : Pick up the correct statement from the following: (A) The phenomenon of quicksand generally occurs in the cohesionless soil (B) At critical hydraulic gradient, the saturated sand becomes quick (C) The critical gradient depends on the void ratio and the specific gravity (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : PERT is (A) An analytic in concept (B) Limited of event oriented diagrams (C) Used for research and development projects (D) All the above

Last Answer : (D) All the above

Description : Air-Vac Cleaning systems rents a stand in a shopping centre. Passers by are asked to register for a draw for a free ventilation evaluation. This contest is part of Air -Vac's: A)sales promotion efforts. B)advertising campaign. C)personal selling programme. D)corporate publicity

Last Answer : A)sales promotion efforts

Description : What is a requirement for setting pricing objectives? A)The objectives should be short-term oriented. B)There should be only one pricing objective. C)An evaluation of competitors' prices should be made. D)The cost structure should be identified. E)The objectives should be explicitly stated.

Last Answer : E)The objectives should be explicitly stated.

Description : Which of the following is false regarding the evaluation of computer programming languages? (A) Application oriented features (B) Efficiency and Readability (C) Software development (D) Hardware maintenance cost

Last Answer : (D) Hardware maintenance cost

Description : To orient a plane table at a point roughly south of the mid-point of two inaccessible conical hill stations and in the plains, a point is selected in line with AB and table is oriented at by bringing ab ... , is (A) Unique and correct (B) Incorrect (C) Manifold and correct (D) Not reliable

Last Answer : (C) Manifold and correct

Description : The main cognitive objective of seminar is Options: A) To develop critical and analytical capacities in a researcher B) To develop observational and experiential presenting capabilities in a researcher C ... and evaluation related abilities in a researcher D) All of the above are correct statements

Last Answer : D) All of the above are correct statements 

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : Point out the correct statement. a) Service Oriented Architecture (SOA) describes a standard method for requesting services from distributed components and managing the results b) SOA provides the ... written in different languages and can use multiple messaging protocols d) All of the mentioned

Last Answer : All of the mentioned

Description : Point out the correct statement. a) Service Oriented Architecture (SOA) describes a standard method for requesting services from distributed components and managing the results b) SOA provides the ... written in different languages and can use multiple messaging protocols d) All of the mentioned

Last Answer : All of the mentioned

Description : Which committee was formed to review “Community Development Programme” of 1952?

Last Answer : Balwan Rai Mehta Committee

Description : . Which of the following is empirical estimation technique? (i) expert judgement (ii) Delphi estimation (iii) COCOMO (iv) Critical path Method A. only i, ii & iii B. only i & ii C. only i, iii & iv D. All of the above

Last Answer : B. only i & ii

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : A review undertaken to decide whether a project should proceed into its next phase is known as a: a. gate review. b. feasibility study. c. milestone review. d. evaluation review.

Last Answer : a. gate review.

Description : A review undertaken to decide whether a project should proceed into its next phase is known  as a:  a. gate review.  b. feasibility study.  c. milestone review.  d. evaluation review.

Last Answer : a. gate review.

Description : A process designed to provide an objective evaluation, before the report is issued, of the significant judgments the engagement team made and the conclusions they reached in formulating the report is called: a. Inspection b. Documentation c. Monitoring d. Engagement quality control review

Last Answer : Engagement quality control review

Description : A process comprising an ongoing consideration and evaluation of the firm's system of quality control, including a periodic inspection of a selection of completed engagements, designed to enable the firm ... effectively. a. Inspection b. Monitoring c. Peer review d. Engagement quality control review

Last Answer : Monitoring

Description : A process designed to provide an objective evaluation, before the report is issued, of the significant judgments the engagement team made and the conclusions they reached in formulating the report. a. Peer review b. Inspection c. Engagement quality control review d. Monitoring

Last Answer : Engagement quality control review

Description : It involves a study or evaluation of the quality of audit of financial statements through a review of quality control measures established by on CPA firms and individual CPAs in public practice to ... standards and practices a. External audit b. Compliance audit c. Peer review d. Quality review

Last Answer : Quality review

Description : The review of unaudited financial statements consists of: a. Inquiry of management and analytical procedures. b. Inquiry of management and documentation of internal controls. c. Analytical ... and compliance with laws and regulations. d. Internal control evaluation and management representation.

Last Answer : Inquiry of management and analytical procedures

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : The process of incorporating changes and rescheduling or replanning is called (A) Resource levelling (B) Resource smoothening (C) Updating (D) Critical path scheduling

Last Answer : (C) Updating

Description : Critical path (A) Is always longest (B) Is always shortest (C) May be longest (D) May be shortest

Last Answer : (A) Is always longest

Description : A CPM family includes (A) CPA (Critical Path Analysis) (B) CPP (Critical Path Plotted) (C) MCE (Minimum Cost Expenditure) (D) All the above

Last Answer : (D) All the above

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : Updating may result in (A) Change of critical path (B) Decrease of project completion time (C) Increase of project completion time (D) All of the above

Last Answer : (D) All of the above

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : Pick up the correct statement from the following: (A) In hydrometer method, weight Wd per ml of suspension is found directly (B) In pipette analysis, weight Wd per ml of suspension is found indirectly (C) In pipette analysis, weight Wd per ml of suspension is found directly (D) None of these

Last Answer : (C) In pipette analysis, weight Wd per ml of suspension is found directly