While finalizing the IRBM, which of the following have been taken into account. a) Indian RailwaysGeneral Rules 1976
b) Indian Railways Code for Engineering Department 1993
 c) Bridge Rules and Substructure d) All the above*

1 Answer

Answer :

d) All the above*

Related questions

Description : Foundation and substructure of the bridge should be inspected by SE/P.Way/Works a) Once a year any time b) Once a year before monsoon* c) Once a year after monsoon d) Once in 3 month

Last Answer : b) Once a year before monsoon*

Description : The medium to transfer loads from superstructure to substructure is called a) Abutment b) Bed block c) Bearing d) Pier

Last Answer : c) Bearing

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : Number of model stations identified for development on Indian Railways is about (a) 55 (b) 110* (c) 265 (d) 320

Last Answer : b) 110*

Description : On Indian Railways a new level crossing can be provided with the approval of a) Chief engineer b) General Manager c) Commissioner of Railway Safety d) None of the above*

Last Answer : d) None of the above

Description : The maximum permissible speed recommended for Indian Railways for 1 in 8 and half crossing is a)16 kmph* b) 20 kmph c)24 kmph

Last Answer : a)16 kmph*

Description : The number of stations on Indian Railways is a) 6000 approximately b) 7070 approximately* c) 8000 proximately d) 9000 approximately

Last Answer : b) 7070 approximately*

Description : Which Indian state is known as 'Land of Five Rivers' ? [Railways 1993] (a) U.P. (b) Punjab (c) Haryana (d) Jammu and Kashmir

Last Answer : Ans: (b)

Description : Which para of Engineering code deals with cost sharing of ROB/RUBs a) 1716 b) 1814 c) 1816* d) 1819

Last Answer : c) 1816*

Description : Longest Railway Bridge on Indian Railway is 1. Sone Bridge at Dehri on Sone* 2. Yamuna Bridge at Kalpi 3. Ganga Bridge near Patna 4. Pamban Bridge

Last Answer : 1. Sone Bridge at Dehri on Sone*

Description : A model stations on railways should have (a) Minimum essential facilities (b) Desirable facilities* (c) Recommended facilities (d) All the above

Last Answer : b) Desirable facilities*

Description : Which of the following is a part of Test Closure Activities? i. Checking which planned deliverables have been delivered ii. Defect report analysis. iii. Finalizing and archiving testware. iv. Analyzing lessons. a) i , ii , ... false c) i , iii , iv are true and ii is false d) All of above are true

Last Answer : c) i , iii , iv are true and ii is false

Description : In which institution the training of electric work is being given? A. Indian Railways Institute of Mechanical and Electrical Engineering B. Indian Railways Institute of Electrical Engineering C. Railway Staff College D. Indian Railways Institute of Civil Engineering

Last Answer : A [Indian Railways Institute of Mechanical and Electrical Engineering]

Description : 1. When was the Ninth Schedule of the Constitution of India added? 2. National Environmental Engineering Research Institute is located at which city? 3. From where does Indian Railways earn the maximum ... has the largest area under forests? 20. What is the birth place of Guru Gobind Singh?

Last Answer : Answer : 1. By the first Amendment 2. Nagpur 3. Freight 4. Strait of Dover 5. Rana Ratan Singh 6. 0° 7. 8 8. 52nd 9. Rann of Kutch 10. Bahlol Lodi 11. Wings of Fire 12. Wetland 13. Acid to water 14. Mediterranean Sea 15. Guru Teg Bahadur 16. Jonas Salk 17. 12 18. RBI 19. Madhya Pradesh 20. Patna

Description : Level Crossing beyond the outermost stop signals is called a) Engineering Gate* b) Traffic Gate c) Engineering and Signal Gate d) Signal Gate

Last Answer : a) Engineering Gate

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above

Description : The bifurcation of Posts and telegraph department was happened a. 1985 b. 1976 c. 1990

Last Answer : b. BSNL

Description : From ----------- the accounts work relating to the postal branch of the P& T department was separated from P& T audit a. 01.04.1977 b.01.04.1976 c. 01.08.1980

Last Answer : b.01.04.1976

Description : CCS conduct Rules not apply to a) A member of All India Service b) A holder of any post in respect of which the president has, by a general or special order c) A Railway servant as defined in Section 3 of the Indian Railways act 1890 d) All the above

Last Answer : d) All the above

Description : Foot over bridge must be provided on the following type of stations as per minimum essential facility criteria (a) A, B, C, & D class station (b) A,B & C class station* (c) A, & B class station (d) Only A class station

Last Answer : b) A,B & C class station*

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : Which of the following stone is best suited for construction of piers and abutments of Railway Bridge a) Granite* b) Sandstone c) Limestone d) Quartzite

Last Answer : a) Granite*

Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000

Last Answer : b) 1, 00,000*

Description : In case of bridge is distressed category I then special restriction of___hall be imposed

Last Answer : 15 kmph

Description : In case of distressed bridge category II, ADEN shall inspect the bridge

Last Answer : once in 6 months

Description : In important bridge the total linear waterway is

Last Answer : 300 m or the total water way is 1000 sq.m.

Description : The URN of minor bridge shall be represented by its

Last Answer : ORN

Description : bridge foundation having less then 2M depth below bed level in case of arch bridges and 1.2M depth below bed level in case of other bridges is termed as

Last Answer : …Shallow foundation..

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : Payment to bridge staff on the section will be made by the pay clerk in the presence of a) SSE/SE/JE/ P.Way b) SSE/SE/JE/ Br.* c) SSE/SE/JE/ Works d) Office clerk

Last Answer : b) SSE/SE/JE/ Br.*

Description : At locations where access to the new bridge construction is available by rail, the launching of girders upto 18.3 m which method is ideal. a) slew in slew out method b) gantry method c) Launching of girders with the help of a BFR*: d) Pantoon method

Last Answer : c) Launching of girders with the help of a

Description : Which cement should not be used for bridge slabs ro RCC frames a) OPC b) Portland Pozzolana cement * c) Portland furnace slag cement d) Rapid hardening cement

Last Answer : b) Portland Pozzolana cement *

Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None

Last Answer : b) Lifting*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : The clear distance between consecutive sleepers laid over unballasted bridge on BG should not exceed a)300mm b)400mm c)450mm* d)550mm

Last Answer : c)450mm*

Description : Permitted wind velocity for running of trains on the bridge a) 72 km/h* b) 58 km/h c) 64 km/h d) No limits

Last Answer : a) 72 km/h*

Description : Definition of minor bridge e) Single span less than 12m f) Total linear water way less than 18m g) Both a) & b)* h) None of the above

Last Answer : g) Both a) & b)*

Description : Definition of major bridge a) Single span of 12m & above b) Total linear water way more than 18m c) Both a) & b)* d) None of the above

Last Answer : c) Both a) & b)*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : Rail joints should be avoided within ……………of a bridge abutment. a) 6 m b) 3 m* c) 4 m d) 10 m

Last Answer : b) 3 m*

Description : The size of bridge timber required for the standard spans up to 18.3 m a) 250 x 150mm*. b) 250 x 180mm. c) 250 x 240mm d) 250 x 200mm

Last Answer : a) 250 x 150mm*.

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting b) periodical through painting* c) Any of the above d) None of the above

Last Answer : b) periodical through painting*

Description : In arch bridges, Cracks/ lean/ bulge in parapet walls, Bulging or separation of spandrel from arch barrel, are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Cracks in return walls/ wing walls or Slight tilting/ bulging of abutments are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Settlement of foundations or Tilted piers and abutments will be considered as distressed bridge as a) Group I* b) Group II c) Both of the above d) None of the above

Last Answer : a) Group I*

Description : For a major bridge, the URN would comprise of a) single digit b)eight digits* c) six digits d) four digits

Last Answer : b)eight digits*

Description : An important bridge is one which has total waterway of equal to or more than a) 1000 sq.metres.* b) 800 sq. metres c) 500 sq. metres d) 300 sq. metres

Last Answer : a) 1000 sq.metres.*

Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted

Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*