Renewal of loose rivet shall be taken up in end bearing stiffener when the % of  hammer loose rivet is

1 Answer

Answer :

30%

Related questions

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : The weight of rivet testing hammer is

Last Answer : 110 gm

Description : Rebound hammer is used for a) To find the strength of concrete* b) To form rivet heads c) To break the concrete structures d) None of the above

Last Answer : a) To find the strength of concrete*

Description : The diameter of hole for 20 dia rivet shall be a) 23 mm b) 18 mm c) 21.5 mm* d) 22 mm

Last Answer : c) 21.5 mm*

Description : In flange splices when the number of hammer and hand loose rivets is 30% or more of the total rivets on any side of the splice location, a) Need no be renewed b) wait for 100% loose rivets c) all the rivets should be renewed.* d) None of the above

Last Answer : c) all the rivets should be renewed.*

Description : For end bearing piles, the minimum spacing of piles of diameter ‘d’ shall be a) 3d b) 2d c) 2.5d* d) 5d

Last Answer : c) 2.5d*

Description : The length of the countersunk head rivet shank is, when L = length of the rivet, G = length of grip in mm; D = Dia of rivet in mm a) L =G +0.5 D + 1mm for every 4 mm of grip or part thereof * b) b) L =G +0.5 D + 1mm c) L =G +0.5 D d) None of the above

Last Answer : a) L =G +0.5 D + 1mm for every 4 mm of grip or part thereof *

Description : he length of the snap head rivet shank is, when L = length of the rivet, G = length of grip in mm; D = Dia of rivet in mm a) L =G +1.5 D + 1mm for every 4 mm of grip or part thereof * b) b) L =G +0.5 D + 1mm c) L =G +0.5 D d) None of the above

Last Answer : a) L =G +1.5 D + 1mm for every 4 mm of grip or part thereof *

Description : Greasing of bearing shall be done with

Last Answer : grease graphite

Description : Minimum speed restriction to be imposed for Track renewal is:- (a) Stop dead & 10 Kmph (b) 10 Kmph (c) 15 Kmph (d) 20 Kmph*

Last Answer : (d) 20 Kmph*

Description : Lowest level of staff/supervisor competent for Renewal/recoupment of fastenings requiring lifting in LWR/CWR. a. PWS b. Gangmate* c. Keyman d. Gangman

Last Answer : b. Gangmate*

Description : Lowest level of staff/supervisor competent of Renewal of fastenings not requiring lifting in LWR/CWR. a. PWS b. Gangmate c. Keyman* d. Gangman

Last Answer : c. Keyman

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : What is the full form of PQRS used for Track renewal works. a. Plasser quick Relaying system* b. Please quick return services c. Poor Quality renewal system d. None of above

Last Answer : a. Plasser quick Relaying system*

Description : An accident has taken place at out station and main line is blocked and relief train is to be turned out without medical car. The hooter shall be: a. 3 long b. 4 long* c. 4 long, 1 short d. 3 long, and 1 short

Last Answer : b. 4 long

Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters

Last Answer : a) 3 meters*

Description : The maximum pressure which the soil can carry safely without the risk of shear failure is called a) Safe bearing capacity b) Ultimate bearing capacity* c) Allowable bearing capacity d) Shear bearing capacity

Last Answer : b) Ultimate bearing capacity*

Description : The side slope of formation in embankment /cutting depends on a) Shearing strength of soil and its angle of repose* b) Angle of repose c) Bearing capacity of the soil d) Optimum moisture content of the soil

Last Answer : a) Shearing strength of soil and its angle of repose*

Description : To provide inverted filter to improve the bearing capacity of soil the liquid limit of blanketing material should not be greater than a) 5 b) 20 c) 27 d) 35

Last Answer : d) 35

Description : Bearings for plate girders are -- a) roller bearing b) sliding bearings c) centralised articulated bearings* d) None of the above

Last Answer : c) centralised articulated bearings*

Description : The medium to transfer loads from superstructure to substructure is called a) Abutment b) Bed block c) Bearing d) Pier

Last Answer : c) Bearing

Description : The chairman and the members of the AASC and FRSC shall have a term of a. 1 year. b. 3 years. c. 3 years with no renewal. d. 3 years renewable for another term

Last Answer : 3 years renewable for another term

Description : Individual CPAs, Firms or Partnerships of CPAs, including partners and staff members thereof shall register with the BOA and the PRC. If the accreditation of Velasco and Co., CPAs, was renewed on September 30, ... . September 30, 2010 b. September 30, 2011 c. December 31, 2010 d. December 31, 2011

Last Answer : September 30, 2011

Description : Members of the Professional Regulatory Board of Accountancy shall serve for: a. Three years, subject to renewal. b. Seven years, not subject to renewal. c. Three years, subject to reappointment. d. Three years, not subject to reappointment

Last Answer : Three years, subject to reappointment

Description : The most effective method of locating a loose commutator bar in a D.C. motor is by _____________. A. visual inspection B. jiggling each by hand C. sounding each bar with a light weight hammer D. checking with a calibrated torque wrench

Last Answer : Answer: C

Description : The wash hand basin shall be fixed at a height of (a) 75-80 cm* (b) 75 cm (c) 80 cm (d) Not specified

Last Answer : (a) 75-80 cm*

Description : The capacity of automatic flushing cistern connected with three urinal shall be (a) 05 litrs. (b) 10 litrs. (c) 12.5 litrs.* (d) None of these

Last Answer : (c) 12.5 litrs.*

Description : The capacity of automatic flushing cistern connected with two urinal shall be (a) 10 litrs.* (b) 12.5 litrs. (c) 05 litrs. (d) None of these

Last Answer : (a) 10 litrs.*

Description : The capacity of automatic flushing cistern connected with one urinal shall be (a) 05 litrs. (b) 10 litrs. (c) 12.5 litrs. (d) None of these

Last Answer : (a) 05 litrs.

Description : The urinal basin shall be connected with (a) High level floating cistern* (b) Low level floating cistern (c) Automatic floating cistern (d) Any one of the above

Last Answer : (a) High level floating cistern*

Description : For high level flush the nominal dia of flush pipe shall be (a) 32 mm* (b) 40 mm (c) 25 mm (d) None of these

Last Answer : a) 32 mm*

Description : Indian type W.C. pan shall have 10cm. S.C.I. trap P or S type with effective seal of (a) 5 cm.* (b) 10 cm. (c) 7.5 cm (d) None of these

Last Answer : (a) 5 cm.*

Description : DFWR weld shall be replaced. (i) Within 2 months of detection. (ii) Within 1 year of detection. (iii) Within 3 months of detection.* (iv) after 3 days of detection.

Last Answer : (iii) Within 3 months of detection.*

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : The increased gain of 10 dbs for single line & ‘D’ marks rails on double/multiple lines shall be employed for classification of defects. (i) defect in weld (ii) defects in rail. * (iii) for both defects on weld & rail. (iv) None of above.

Last Answer : ii) defects in rail. *

Description : Rails used for A T Welding shall not normally be welded? (i) 20 years old . (ii) 30 years old (iii) 40 years old (iv) 50 years old*

Last Answer : iv) 50 years old*

Description : What is the speed restriction to be observed for train passing? (i) Necessary speed restriction shall be observed until the grinding operation is over.* (ii) 30KMPH (iii) 45 KMPH (iv) Not required

Last Answer : (i) Necessary speed restriction shall be observed until the grinding operation is over.*

Description : Pressure of Oxygen during pre-heating shall be? (i) 4.0 – 5.0 kg/ sq cm (ii) 5.0 – 6.0 kg/ sq cm (iii) 6.0 – 7.0 kg/ sq cm (iv) 7.0 – 8.0 kg/ sq cm *

Last Answer : (iv) 7.0 – 8.0 kg/ sq cm *

Description : ressure of LPG during pre-heating shall be? (i) 2.0 - 2.5 kg/ sq cm (ii) 2.0 - 2.5 kg/ sq cm (iii) 2.0 - 2.5 kg/ sq cm* (iv) 2.0 - 2.5 kg/ sq cm

Last Answer : (iii) 2.0 - 2.5 kg/ sq cm*

Description : Finished tolerance on 10 cm. long st. edge on surface of head shall be? (i) 0 to 0.1 mm (ii) 0 to 0.2 mm (iii) 0 to 0.4 mm* (iv) 0 to 0.3 mm

Last Answer : (iii) 0 to 0.4 mm*

Description : Finished tolerance on 10 cm long st. edge at the centre on gauge side shall be? (i) ± 0.4 mm (ii) ± 0.1 mm (iii) ± 0.2 mm (iv) ± 0.3 mm*

Last Answer : iv) ± 0.3 mm*

Description : Finished tolerance on 1 Mt. long st. edge on surface of head shall be? (i) 0 to .1 mm (ii) 1 to 1.5 mm (iii) 0 mm (iv) 0 to 1 mm*

Last Answer : (iv) 0 to 1 mm*

Description : Finished tolerance on 1 Mt. st. edge at the centre on gauge side shall be? (i) ± 0.2 mm (ii) ± 0.3 mm (iii) ± 0.5 mm* (iv) ± 1.0 mm

Last Answer : (iii) ± 0.5 mm*

Description : What is the validity after supervisors course (TW-3)? (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.* (ii) 2 years (iii) 5 Years (iv) 10 Years

Last Answer : (i) Normally, supervisors shall not be required to undergo the course again. However, they may be sent for course on performance basis.*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : Traffic census at a level crossing shall be done by a) A team of SSE/ P Way and SSE/ Works b) A team of SSE/ P Way and Traffic inspector c) A team of SSE/ P Way and Signal Inspector d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Last Answer : d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Description : The minimum and maximum clearances of check rails at all BG level crossings shall be a) 51 to 57 mm* b) 44 to 48 mm c) 41 to 45 mm d) 55 to 70 mm

Last Answer : a) 51 to 57 mm*

Description : Minimum length of check rail for square crossing shall be -------- more than the width of gate a) 1 meters b) 2 meters* c) 3 meters d) 5 meters

Last Answer : b) 2 meters*

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters