The Assistant Divisional Engineer should inspect the equipment at every manned level  crossing on the subdivision once in
a) 2 months
b) 3 months
c) 4 months
d) 6 months*

1 Answer

Answer :

d) 6 months

Related questions

Description : On Indian Railways a new level crossing can be provided with the approval of a) Chief engineer b) General Manager c) Commissioner of Railway Safety d) None of the above*

Last Answer : d) None of the above

Description : The ______RMS must inspect every ______at intervals of about ____such offices and sections in his sub division as are assigned to him by the ______ a) ASP, twelve months six months, Head of the Circle ... c) Sub divisional Inspector, twelve months six months, Head of the Circle d) None of these

Last Answer : c) Sub divisional Inspector, twelve months six months, Head of the Circle

Description : The frequency of census at a level crossing having TVU between 75000 to 1 lakh will be once a) In 2 years b) In 3 years* c) In 4 years d) Every year

Last Answer : b) In 3 years*

Description : Special inspection of distressed bridges shall be carried out by Asst. Engineer is a) Once in three months b) Once in two months* c) Once in a month d) Once in six months

Last Answer : b) Once in two months*

Description : Survey of the major projects is done by (a) Chief Engineer (b) Chief Administrative Officer (CAO) construction* (c) Divisional Railway Manager (d) Railway Board

Last Answer : (b) Chief Administrative Officer (CAO) construction*

Description : What is the highest post in Railway a. General Manager b. Chief Engineer c. Chairman Railway Board* d. Divisional Railway Manager

Last Answer : c. Chairman Railway Board*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : Periodical Census of traffic at unmanned level Crossings should be done once in a) Once in 6 years b) Every year c) Once in 3 years* d) Once in 5 years

Last Answer : c) Once in 3 years*

Description : In case of Shot Welded Rails the fish plated joint should be avoided on Level Crossings within a distance of --------- from end of level crossing a) 3 meters b) 4 meters c) 5 meters d) 6 meters*

Last Answer : d) 6 meters*

Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters

Last Answer : a) 5 meters*

Description : The rail joint should be located at ----------- from the end of level crossing a) 2 meters b) 3 meters * c) 5 meters d)6 meters

Last Answer : b) 3 meters

Description : On an unmanned level crossing stop board should be provided at a distance of --------- from the centre of nearest track a) 5 meters * b) 6 meters c) 3 meters d) 7.5 meters

Last Answer : a) 5 meters

Description : In case of distressed bridge category II, ADEN shall inspect the bridge

Last Answer : once in 6 months

Description : The village sorting list once in a month should be examined by a) Sub divisional inspector b) Supdt of postoffice c) Sub account assistant d) Postmaster

Last Answer : c) Sub account assistant

Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.

Last Answer : c) Duty hut should be on the outside of the curve.*

Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.

Last Answer : c) Level crossing should not fall within the breathing length of LWR*

Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000

Last Answer : b) 1, 00,000*

Description : Traffic census at a level crossing shall be done by a) A team of SSE/ P Way and SSE/ Works b) A team of SSE/ P Way and Traffic inspector c) A team of SSE/ P Way and Signal Inspector d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Last Answer : d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Description : The Height Gauge for a level crossing should be located at least --------- from the gate post a) 3 meters b) 5 meters c) 8 meters* d) 10 meters

Last Answer : c) 8 meters*

Description : There should not be any combination joint on level crossing proper and its approaches up to a) 15 meters b) 30 meters c) 40 meters d) 50 meters

Last Answer : d) 50 meters

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters

Last Answer : a) 3 meters*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : Level crossing is classified on the basis of a) Class of road b) TVU* c) Volume of road traffic d) Volume of rail traffic

Last Answer : b) TVU*

Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters

Last Answer : c) 20 meters*

Description : Level Crossing beyond the outermost stop signals is called a) Engineering Gate* b) Traffic Gate c) Engineering and Signal Gate d) Signal Gate

Last Answer : a) Engineering Gate

Description : For protection of level crossing gate in an emergency on BG double line the Gateman should place one detonator at one place and 3 detonators at a subsequent place at a distance of ------- a) and------ ... c) 500 meters and 1000 meters d) 600 meters and 1200 meters* e) 800 meters in 1500 meters

Last Answer : d) 600 meters and 1200 meters*

Description : Indication post for detonator should be provided at a distance of ---------meter and --------- meter for BG level crossing a) 400 meters in 800 meters b) 500 meters and 1200 meters c) 600 meters and 1200 meter * d)600 meters and 1000 meters

Last Answer : c) 600 meters and 1200 meter *

Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted

Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*

Description : Minimum clearance of check rails for B.G. at level crossing should be (a) 48mm (b) 57mm (c) 51mm* (d) 44mm

Last Answer : (c) 51mm*

Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51 mm (b) 57mm* (c) 65mm (d) 70mm

Last Answer : (b) 57mm*

Description : Maximum clearance of check rails at level crossing for B.G. should be (a) 48mm (b) 57mm* (c) 51mm (d) 44mm

Last Answer : (b) 57mm*

Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51mm ( b ) 57mm* (c) 65mm (d) 54mm

Last Answer : ( b ) 57mm*

Description : .Minimum check rail clearance at Level crossing a. 45 mm b. 51 mm* c. 50 mm d. 57 mm

Last Answer : b. 51 mm*

Description : When maintenance personnel are working on electrical equipment, all supply switches should be secured in the open position and tagged specifically by the _____________. A. watch engineer B. chief engineer or first assistant C. chief electrician D. person performing the repair

Last Answer : Answer: D

Description : Sensitivity calibration against temp. variation shall be carried out. (i) At least once in month* (ii) quarterly. (iii) at least once in six months (iv) Any of above.

Last Answer : i) At least once in month*

Description : Special inspection of distressed bridges Group II shall be carried out by Inspector (Concerned) is a) Once in three months* b) Once in two months c) Once in a month d) Once in six months

Last Answer : a) Once in three months*

Description : Curve inspection shall be carried out by Sectional PWI a. Once in three months b. Once in six months c. Once in four months* d. None of above

Last Answer : c. Once in four months

Description : As part of a routine maintenance program for deck machinery, you should ___________. A. inspect electrical wiring and pushbutton switches for evidence of corrosion or burned insulation B. disassemble ... covers and ventilate as weather permits D. Check drum switch contact pressure every three months

Last Answer : Answer: A

Description : As per GCC Engineer shall mean_____

Last Answer : DEN / XEN

Description : Coast Guard Regulations (46 CFR 199) require that each lifesaving appliance, including lifeboat equipment, must be inspected at least once every _____________. A. week B. 2 weeks C. month D. 3 months

Last Answer : Answer: C

Description : Which of the facilities do not exist at halt station? (a) Facilities for stopping the train (b) Facilities for a small waiting (c) Facilities for crossing of train* (d) Facilities for book of passengers

Last Answer : (c) Facilities for crossing of train*

Description : Minimum length of check rail for square crossing shall be -------- more than the width of gate a) 1 meters b) 2 meters* c) 3 meters d) 5 meters

Last Answer : b) 2 meters*

Description : When the railway crosses a deep vally without perinial water,it is called……. a)Aqueduct * b)Cause way c)Via-duct d)River crossing

Last Answer : a)Aqueduct *

Description : CC Crib stands for a) Cement concrete b) Criss crossing c) Christ church* d) None of the above

Last Answer : c) Christ church*

Description : One of the following works does not require CRS sanction a) Regirdering/ Rebuilding b) Erection of new FOB c) Erection of platform shelter* d) Pipe line crossing

Last Answer : c) Erection of platform shelter*

Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier

Last Answer : a) C.L. of water course/road to C.L. of track*

Description : Service life of CMS crossing ( 52 Kg rail) is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT. (d) 150 GMT.*

Last Answer : (d) 150 GMT.*

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*

Description : Points & Crossing is laid at a cant of a. 1 in 20 b. 1 in 10 c. 1 in 15 d. NIL*

Last Answer : d. NIL*