Level Crossing beyond the outermost stop signals is called  
a) Engineering Gate*
b) Traffic Gate  
c) Engineering and Signal Gate
d) Signal Gate

1 Answer

Answer :

a) Engineering Gate

Related questions

Description : On Broad Gauge tracks Banner flag at a level crossing shall be provided at a distance of--- ---------- from ends of check rail before opening the gate for road traffic. a) 5 meters* b) 3 meters c) 6 meters d) 30 meters

Last Answer : a) 5 meters*

Description : Traffic census at a level crossing shall be done by a) A team of SSE/ P Way and SSE/ Works b) A team of SSE/ P Way and Traffic inspector c) A team of SSE/ P Way and Signal Inspector d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Last Answer : d) A multidisciplinary team of SSE/ P Way, Signal Inspector and Traffic Inspector*.

Description : The Height Gauge for a level crossing should be located at least --------- from the gate post a) 3 meters b) 5 meters c) 8 meters* d) 10 meters

Last Answer : c) 8 meters*

Description : For protection of level crossing gate in an emergency on BG double line the Gateman should place one detonator at one place and 3 detonators at a subsequent place at a distance of ------- a) and------ ... c) 500 meters and 1000 meters d) 600 meters and 1200 meters* e) 800 meters in 1500 meters

Last Answer : d) 600 meters and 1200 meters*

Description : Level crossing is classified on the basis of a) Class of road b) TVU* c) Volume of road traffic d) Volume of rail traffic

Last Answer : b) TVU*

Description : In case of water crossing danger level in bridges a) speed restriction be imposed b) traffic be suspended till water recedes c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic* d) bridge watchman is to be posted

Last Answer : c) traffic be suspended till a responsible person inspects the site and declares it safe for running traffic*

Description : Minimum length of check rail for square crossing shall be -------- more than the width of gate a) 1 meters b) 2 meters* c) 3 meters d) 5 meters

Last Answer : b) 2 meters*

Description : On an unmanned level crossing stop board should be provided at a distance of --------- from the centre of nearest track a) 5 meters * b) 6 meters c) 3 meters d) 7.5 meters

Last Answer : a) 5 meters

Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.

Last Answer : c) Duty hut should be on the outside of the curve.*

Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.

Last Answer : c) Level crossing should not fall within the breathing length of LWR*

Description : On Indian Railways a new level crossing can be provided with the approval of a) Chief engineer b) General Manager c) Commissioner of Railway Safety d) None of the above*

Last Answer : d) None of the above

Description : A level crossing qualifies for construction of Road Over Bridge/ Under Bridge on Cost sharing basis with State Government when the Train Vehicle Unit is more than a) 50,000 b) 1, 00,000* c) 3, 00,000 d) 5, 00,000

Last Answer : b) 1, 00,000*

Description : Frequency of overhauling for a level crossing with PRC sleepers shall be a) Every year c) Every 2 years* c) Every 3 years d) Every 5 years

Last Answer : c) Every 2 years*

Description : There should not be any combination joint on level crossing proper and its approaches up to a) 15 meters b) 30 meters c) 40 meters d) 50 meters

Last Answer : d) 50 meters

Description : In case of Shot Welded Rails the fish plated joint should be avoided on Level Crossings within a distance of --------- from end of level crossing a) 3 meters b) 4 meters c) 5 meters d) 6 meters*

Last Answer : d) 6 meters*

Description : Speed breaker of approved design shall be provided on either side of level crossing at ------ within Railway boundary a) 5 meters b) 15 meters c) 20 meters* d0 30 meters

Last Answer : c) 20 meters

Description : Fish plated joint shall be avoided in check raisl and on the running rails within--------- from the end of level crossing a) 3 meters* b) 5 meters c) 10 meters d) 12 meters

Last Answer : a) 3 meters*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : The Assistant Divisional Engineer should inspect the equipment at every manned level crossing on the subdivision once in a) 2 months b) 3 months c) 4 months d) 6 months*

Last Answer : d) 6 months

Description : The frequency of census at a level crossing having TVU between 75000 to 1 lakh will be once a) In 2 years b) In 3 years* c) In 4 years d) Every year

Last Answer : b) In 3 years*

Description : The rail joint should be located at ----------- from the end of level crossing a) 2 meters b) 3 meters * c) 5 meters d)6 meters

Last Answer : b) 3 meters

Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters

Last Answer : c) 20 meters*

Description : Indication post for detonator should be provided at a distance of ---------meter and --------- meter for BG level crossing a) 400 meters in 800 meters b) 500 meters and 1200 meters c) 600 meters and 1200 meter * d)600 meters and 1000 meters

Last Answer : c) 600 meters and 1200 meter *

Description : Minimum clearance of check rails for B.G. at level crossing should be (a) 48mm (b) 57mm (c) 51mm* (d) 44mm

Last Answer : (c) 51mm*

Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51 mm (b) 57mm* (c) 65mm (d) 70mm

Last Answer : (b) 57mm*

Description : Maximum clearance of check rails at level crossing for B.G. should be (a) 48mm (b) 57mm* (c) 51mm (d) 44mm

Last Answer : (b) 57mm*

Description : On B.G. maximum clearances of check rails at a level crossing are (a) 51mm ( b ) 57mm* (c) 65mm (d) 54mm

Last Answer : ( b ) 57mm*

Description : .Minimum check rail clearance at Level crossing a. 45 mm b. 51 mm* c. 50 mm d. 57 mm

Last Answer : b. 51 mm*

Description : Periodical Census of traffic at unmanned level Crossings should be done once in a) Once in 6 years b) Every year c) Once in 3 years* d) Once in 5 years

Last Answer : c) Once in 3 years*

Description : When the railway crosses a deep vally without perinial water,it is called……. a)Aqueduct * b)Cause way c)Via-duct d)River crossing

Last Answer : a)Aqueduct *

Description : Which set of truth table input signals will result in an output signal value of 1 from the 'AND' gate as shown in the illustration? EL-0035 A. 1-Jan B. Jan-00 C. 0-1 D. 0-0

Last Answer : Answer: A

Description : Which of the facilities do not exist at halt station? (a) Facilities for stopping the train (b) Facilities for a small waiting (c) Facilities for crossing of train* (d) Facilities for book of passengers

Last Answer : (c) Facilities for crossing of train*

Description : CC Crib stands for a) Cement concrete b) Criss crossing c) Christ church* d) None of the above

Last Answer : c) Christ church*

Description : One of the following works does not require CRS sanction a) Regirdering/ Rebuilding b) Erection of new FOB c) Erection of platform shelter* d) Pipe line crossing

Last Answer : c) Erection of platform shelter*

Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier

Last Answer : a) C.L. of water course/road to C.L. of track*

Description : Service life of CMS crossing ( 52 Kg rail) is:- (a) 400 GMT. (b) 300 GMT. (c) 200 GMT. (d) 150 GMT.*

Last Answer : (d) 150 GMT.*

Description : Minimum permissible vertical wear on nose of a 52 kg CMS crossing on Rajdhani route is i) 6mm ii) 8mm* iii) 10mm iv) 12 mm

Last Answer : ii) 8mm*

Description : Points & Crossing is laid at a cant of a. 1 in 20 b. 1 in 10 c. 1 in 15 d. NIL*

Last Answer : d. NIL*

Description : .Minimum wing rail clearance opposing nose of crossing on Fan shaped turnout a. 45 mm b. 40 mm c. 41 mm* d. 44 mm

Last Answer : c. 41 mm*

Description : The maximum permissible speed recommended for Indian Railways for 1 in 8 and half crossing is a)16 kmph* b) 20 kmph c)24 kmph

Last Answer : a)16 kmph*

Description : Minimum distance of gate post from centre line of nearest track on BG is a) 2 meters b) 3 meters* c) 4 meters d) 5 meters

Last Answer : b) 3 meters*

Description : O.D.C. Stands for (a) On direct current (b) Over dimensioned consignment* (c) None of them (d) Operating & gate

Last Answer : (b) Over dimensioned consignment*

Description : Height gauges should be located at a minimum distance of….. from gate post. (a) 5 m (b) 7.5m (c) 8m* (d)10m

Last Answer : (c) 8m*

Description : Stop boards on either side of approaches of all unmanned level crossings shall be provided at -------------from the centre line of nearest track. a) 3meters b) 5 meters* c) 6 meters d) 10 meters

Last Answer : b) 5 meters*

Description : During periodic testing of an AT weld with 700 probe, a bunch of moving signals of less than 40% but more than 10% is observed in the head of weld, the joint will be. (i) Good joint.* (ii) DFWR (iii) DFWO (iv) OBSW

Last Answer : i) Good joint.*

Description : While finalizing the IRBM, which of the following have been taken into account. a) Indian RailwaysGeneral Rules 1976 b) Indian Railways Code for Engineering Department 1993 c) Bridge Rules and Substructure d) All the above*

Last Answer : d) All the above*

Description : Investigation for important bridges may be carried out in which stage a) Technical feasibility study (reconnaissance survey) b) Techno-economic feasibility study (preliminary engineering survey) c) Detailed survey and project report stage (final location survey) d) All the above *

Last Answer : d) All the above

Description : Which para of Engineering code deals with cost sharing of ROB/RUBs a) 1716 b) 1814 c) 1816* d) 1819

Last Answer : c) 1816*

Description : A detailed project report of the proposed railway line is made after (a) Preliminary survey (b) Reconnaissance survey (c) Final location survey* (d) Traffic survey

Last Answer : (c) Final location survey*

Description : Traffic survey is done to find out (a) The most promising route for the railway in the area (b) The possible traffic the railway line will carry (c) Standard of railway line to be followed (d) All the above*

Last Answer : d) All the above*