Description : The conceptual estimate is developed with the least amount of knowledge. When more information is known, the project team can develop a: Select one: a. work breakdown structure b. critical estimate c. rough order of magnitude (ROM) estimate d. scope of work e. ballpark estimate
Last Answer : c. rough order of magnitude (ROM) estimate
Description : A project budget estimate that is developed with the least amount of knowledge is known as which of the following? Select one: a. Rough order of magnitude (ROM) estimate b. Scope of work estimate c. Conceptual estimate d. Line estimate e. Milestone schedule estimate
Last Answer : c. Conceptual estimate
Description : You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D ... . A. Crashing B. fast tracking C. resource leveling D. adjusting the resource calendar
Last Answer : A. Crashing
Description : Earned value management integrates scope, cost, and schedule measures to: A. assess project performance and progress. B. develop a preliminary budget. C. assess communication effectiveness among project team members. D. assess whether all requirements were met.
Last Answer : A. assess project performance and progress.
Description : In which of the following project phases is the project schedule developed? 1. Conceptual 2. Planning 3. Implementation 4. Design
Last Answer : 2. Planning
Description : In the ____ stage, of project identification the project ideas generated above are screened and a preliminary exercise is conducted to weed out the bad or unviable ideas.
Last Answer : Ans. Screening
Description : According to the PMBOK Guide, the project manager is identified and assigned during which process? A. Prior to beginning the Develop Project Charter process B. At the conclusion of the ... . Prior to beginning the Planning processes D. Prior to beginning the Preliminary Scope Statement process
Last Answer : C. Prior to beginning the Planning processes
Description : Complete the following statement. The method of incorporating change into project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude
Last Answer : b. change management process.
Description : Fill in the blank. Risk represents the likelihood that an event will happen during the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack
Last Answer : b. achievement
Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms
Last Answer : a. An approximation of project time and cost targets, refined throughout the project life cycle.
Description : A(n) _ is a review of the quality plan, procedures, data collection, and analysis by an outside group. Select one: a. scope document b. project appraisal c. cost performance index d. analogous estimate e. quality audit
Last Answer : e. quality audit
Description : The budgeted cost for all the activities in a project with the help of Earned Value Method is A. Actual Cost B. Budget at completion C. Budget for completion D. Estimate at completion
Last Answer : D. Estimate at completion
Description : Which one of the following statements best defines an estimate? a. An approximation of project time and cost targets, refined throughout the project life cycle. b. A prediction of a future ... . A situation that affects or influences the outcome of the project expressed in time or cost terms.
Description : The accuracy of an estimate should: a. decrease as a project progresses through its life cycle. b. increase as a project progresses through its life cycle. c. stay constant throughout the project life cycle. d. vary independently of where the project is in its life cycle.
Last Answer : b. increase as a project progresses through its life cycle.
Description : Which of the following does NOT generate changes to the Project documents: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations
Last Answer : A. Define Activities
Description : Which of the following can estimate size of project directly from problem specification? A. LOC B. Function Point Metric C. Both D. None
Last Answer : B. Function Point Metric
Description : Which of the following establishes key dates throughout the life of a project that must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule
Last Answer : e. Milestone schedule
Description : Fill in the blank. Work breakdown structure (WBS) is a ______________ of the work with increasing detail in each layer. Select one: a. layered description b. step change c. ballpark estimate d. project execution plan e. project logic diagram
Last Answer : a. layered description
Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000
Last Answer : d. $875,000
Description : Which of the following is typically a written document that defines what work will be accomplished by the end of the project? Select one: a. Scope of work (SOW) b. Project logic diagram c. Milestone schedule d. Ballpark estimate e. Work breakdown structure
Last Answer : a. Scope of work (SOW)
Description : Complete the following statement. As a project manager, Darrell is excited that he is assigned to be in charge of the most important project this year. After being chartered for the project, he ... c. prepare for the template to monitor project progress. d. estimate the entire project budget.
Last Answer : b. start to define and develop the stakeholder needs and requirements
Description : What is the first step in developing a risk management plan? Select one: a. Analyze the risks. b. Estimate the likelihood of the risks occurring. c. Identify potential project risks. d. Develop a risk mitigation plan. e. Estimate the potential impact of risk on the project goals.
Last Answer : c. Identify potential project risks.
Description : It is often difficult to estimate size at an early stage in a project when only a specification is available a) True b) False
Last Answer : a) True
Description : Kathryn has little experience estimating the time it will take to complete a systems project. She has just completed the planning phase of the project. What method should she use to estimate the ... b. function points c. industry standards d. Microsoft Project e. more complex approach
Last Answer : c. industry standards
Description : To identify the tasks for a work plan the project manager can _____. a. control and direct the project b. estimate the size, staff the project, and remember technical skills c. establish a ... of the SDLC and the steps that occur in each e. set conservative numbers for the project software
Last Answer : d. list the four phases of the SDLC and the steps that occur in each
Description : The basic approach to Earned Value is to A. Sum up the Work Package Earned Values to calculate the Earned Value of the Control Account and ultimately the Project B. Multiply the percent complete by ... that package C. Estimate a percent complete for each WBS Work Package D. All of the above
Last Answer : D. All of the above
Description : When is the project's amount at stake the lowest 1. conceptual 2. design 3. close-out 4. implementation
Last Answer : 1. conceptual
Description : The hurricane model implies that project estimates become more accurate as the project's product becomes better understood.
Last Answer : Ans: True
Description : What is the most accurate method of obtaining project information that can reduce the amount of risk? 1. Observations on the current project 2. Determining the risk by using brainstorming ... from previous projects that were similar in nature 4. Sensitivity analysis 5. Delphi technique.
Last Answer : 3. The use of historical data from previous projects that were similar in nature
Description : A planning method, which provides details of the work to accomplish, but also provide some preliminary description of the work to be done in later phases is called : 1. Progressive detailing 2. Rolling wave 3. Strategic 4. Operational
Last Answer : 2. Rolling wave
Description : Find the false statement: (A) The relationship construct known as the weak relationship type was defined by Dey, Storey & Barron (1999). (B) A weak relationship occurs when two ... Ternary, Quaternary and Quintary relationships are shown through a series of application scenario's and vignette's
Last Answer : (C) Conceptual model is not accurate representation of "Universe of interest".
Description : The most reliable estimate is (A) Detailed estimate (B) Preliminary estimate (C) Plinth area estimate (D) Cube rate estimate
Last Answer : (A) Detailed estimate
Description : Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job. (A) Algorithmic model (B) Expert judgment (C) Bottom-up (D) Top down
Last Answer : (C) Bottom-up
Description : Which of the following may generate a milestone list: A. Define Activities B. Sequence Activities C. Estimate Activity Resources D. Estimate Activity Durations
Description : We can accurately estimate lines of code from the problem specification. A. True B. False C. NA D. NA
Last Answer : B. False
Description : Each component of the product is separately estimated and the results aggregated to produce an estimate for the overall job. (A)Algorithmic model (B)Expert judgment (C)Bottom-up (D)Top down
Last Answer : (C)Bottom-up
Description : Creating a work plan requires three steps: identify the tasks that need to be accomplished, estimate the time that it will take to complete the tasks, and record the task completion time in a Gantt Chart.
Last Answer : Ans: False
Description : To assist in budget control, it is suggested that the estimate occur at the _____ ____ ______ level of the WBS 1. Highest 2. Lowest 3. Major work effort 4. Third
Last Answer : 2. Lowest
Description : Preliminary project report for a road project must contain (A) The detailed estimated cost based on detailed design (B) The several alternatives of the project that have been considered (C ... , traffic survey, concept design and approximate cost (D) The contract documents for inviting tenders
Last Answer : (C) The soil survey, traffic survey, concept design and approximate cost
Description : )A new project was initiated that involves new technology and subsequently has never been done before. What type of contract would to owner want to issue to reduce or eliminate as much risk as possible. 1. Firm ... 2. Cost plus fix fee 3. Cost plus incentive fee 4. Lump sum 5. A and D
Last Answer : 5. A and D
Description : Which of the following type of contracts is most preferable to the contractor doing the project work? 1. Cost plus fixed fee 2. Fixed price 3. Fixed price plus incentive free 4. B and C
Last Answer : 1. Cost plus fixed fee
Description : Following are the phases of Project Management Life Cycle. Arrange them in correct order 1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery (A) 3-2-1-4 (B) 1-2-3-4 (C) 2-3-1-4 (D) 4-3-2-1
Last Answer : (A) 3-2-1-4
Description : A ____ is a set of activities which are networked in an order and aimed towards achieving the goals of a project. (A) Project (B) Process (C) Project management (D) Project cycle
Last Answer : (A) Project
Description : Which one of the following is captured in the Work Breakdown Structure (WBS)? a. The life cycle phases. b. The logical order of tasks. c. The scope of the project. d. Project costs.
Last Answer : c. The scope of the project.
Description : Fill in the blank. Risk must be considered in the _____ phase and weighed against the potential benefit of the project’s success in order to decide if the project should be chosen. Select one: a. completion b. closeout c. execution d. planning e. initiation
Last Answer : e. initiation
Description : Once the project is approved and moves into the planning stage, what happens in the next phase of the project life cycle? Select one: a. Agreements for risk sharing need to be concluded. ... activities. e. A risk response plan can be used to identify increasing levels of detailed risk analysis
Last Answer : d. Risks are identified with each major group of activities.
Description : CV = $70,000; AC = 90,000; Budget = $200,000. What percent of the project is complete? Select one: a. 80% b. 53% c. 45% d. 35% e. 75% Answer - a. 80% 39. As a project manager, John ... paid off the project. d. John's boss is happy. e. John and his team are promoted and get salary increases.
Last Answer : c. John’s client has paid off the project.
Description : What is considered to be the most useful skill for a project manager who works in a matrix environment in order to achieve project goals? Select one: a. Leadership skill b. Influencing c. Conflict management skill d. Time management e. Planning skill