Answer :

Types of Expansion Bearing:

1. Sliding Plate Bearing

2. Deep cast with curve plate

3. Rocker bearing with curved base

4. Rocker & roller bearing


Types of Expansion Bearing: 

1. Sliding Plate Bearing: It consists of sole plate which is provided between main girder and bed plate. It is the simplest type of expansion bearing. 

2. Deep cast with curve plate: It consists of a sole plate which is fixed to underside of girder. The sole plate rests on a deep cast base with a curved bed plate 

3. Rocker bearing with curved base: This is the type of rocker bearing. In this type of bearing, the bottom shoe is given a circular shape. 

4. Rocker & roller bearing: It consist of a rocker pin which is provided between the top shoe and the bottom shoe. Bottom shoe rests on number of steel rollers.

image

image

image

image

Related questions

Description : Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting b) periodical through painting* c) Any of the above d) None of the above

Last Answer : b) periodical through painting*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Depth of construction in a girder bridge means the depth from a) RL to HFL b) RL to top of bed block * c) RL to bottom of bed block d) RL to Bed level

Last Answer : b) RL to top of bed block *

Description : In a railway track, two rails are joined end to end with a gap in between them because – (1) steel can be saved (2) accidents due to contraction in winter can be avoided (3) air-gaps are necessary for bearing the weight of running train (4) accidents due to expansion in summer can be avoided.

Last Answer : (4) accidents due to expansion in summer can be avoided. Explanation: The volume of materials changes depending on current temperature. Usually heat makes them expand, and cold leads them to contract. ... on the tracks. The same applies in many other fields of engineering, i.e. bridge building.

Description : In a railway track, two rails are joined end to end with a gap tin between them because? A. Steel can be saved B. Accidents due to contraction in winter can be avoided C. Air gaps are necessary ... of running train D. Accidents due to expansion in summer can be avoided (Answer) E. All of these

Last Answer : D. Accidents due to expansion in summer can be avoided (Answer)

Description : In a railway track, two rails are joined end to end with a gap in between thembecause (1) steel can be saved (2) accidents due to contraction in winter can be avoided (3) air-gaps are necessary for bearing the weight of running train (4) accidents due to expansion in summer can be avoided.

Last Answer :  accidents due to expansion in summer can be avoided.

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : Classify bearing and explain any one in brief.

Last Answer : Bearing : Hydrodynamic Bearings Hydrostatic Bearings Rolling Element Bearings Types of bearings- Radial bearing Thrust bearing Sliding contact bearings Rolling contact bearings  ... of bearing holds is enormous. The forthcoming articles will deal more with these details.

Description : Write a brief introduction of Bangabandhu Bridge ?

Last Answer : 1. Total project area = 69 acres. 2. Length of main bridge = 4.60 km. 3. Width of main bridge = 16.5 m. 4. Road lanes = 4 5. Total number of spans = 49. . Total number of piles = 121. . ... Stones required for the dam = 8 , 40,000 cubic meters. 11. Length of guide embankment on both banks = 2.2 km.

Description : Describe in brief caisson foundation for a bridge with neat sketch

Last Answer : Caisson foundation A caisson foundation also called as pier foundation is a watertight retaining structure used as a bridge pier in the construction of a concrete dam or for the repair of ships. It is ... the ground to some desired depth and then filled with concrete thus forming a foundation.

Description : The failure of ball bearings used in electric motors can result from _____________. A. failure to clean the bearing before repacking B. failure to maintain proper alignment C. excess lubrication forcing the bearing full of grease and eliminating all areas of expansion D. all of the above

Last Answer : Answer: D

Description : What is an important requisite for fillers in dental composite restorative resins in load bearing areas: A. Sub micro sized particles B. High coefficient of thermal expansion C. High in content (High filler)

Last Answer : C. High in content (High filler)

Description : What happened to a bridge that did not have expansion joints?

Last Answer : What is the answer ?

Description : In a curved prestressed bridge, how should the guided bearings in piers of the curved region be oriented with respect to the fixed bearing in abutment?

Last Answer : To determine the orientation of guided bearings, one should understand the movement of curved region of a prestressed bridge. Movement of prestress and creep are tangential to the curvature of the ... large, temporary freedom of movement at the guided bearings has to be provided during construction.

Description : What is a antonym for girder?

Last Answer : What is the answer ?

Description : How do engineer determine the number of cells for concrete box girder bridges?

Last Answer : If the depth of a box girder bridge exceeds 1/6 or 1/5 of the bridge width, then it is recommended to be designed as a single cell box girder bridge. However, if the bridge depth is ... improvement in transverse load distribution when the number of cells of box girder is increased to three or more.

Description : Are diaphragms necessary in the design of concrete box girder bridges?

Last Answer : Diaphragms are adopted in concrete box girder bridges to transfer loads from bridge decks to bearings. Since the depth of diaphragms normally exceeds the width by two times, they are usually designed ... In fact, diaphragms also contribute to the provision of torsional restraint to the bridge deck.

Description : A single rolling load of 8 kN rolls along a girder of 15 m span. The absolute maximum bending moment will be (A) 8 kN.m (B) 15 kN.m (C) 30 kN.m (D) 60 kN.m

Last Answer : (C) 30 kN.m

Description : When a series of wheel loads crosses a simply supported girder, the maximum bending moment under any given wheel load occurs when (A) The centre of gravity of the load system is midway between the centre of ... the centre of span and the centre of gravity of the load system (D) None of the above

Last Answer : (B) The centre of span is midway between the centre of gravity of the load system and the wheel load under consideration

Description : The maximum bending moment due to a train of wheel loads on a simply supported girder (A) Always occurs at centre of span (B) Always occurs under a wheel load (C) Never occurs under a wheel load (D) None of the above

Last Answer : (B) Always occurs under a wheel load

Description : When a uniformly distributed load, shorter than the span of the girder, moves from left to right, then the conditions for maximum bending moment at a section is that (A) The head of the load ... position should be such that the section divides the load in the same ratio as it divides the span

Last Answer : (D) The load position should be such that the section divides the load in the same ratio as it divides the span

Description : When a uniformly distributed load, longer than the span of the girder, moves from left to right, then the maximum bending moment at mid section of span occurs when the uniformly distributed load occupies (A) Less ... (B) Whole of left half span (C) More than the left half span (D) Whole span

Last Answer : (D) Whole span

Description : A uniform girder simply supported at its ends is subjected to a uniformly distributed load over its entire length and is propped at the centre so as to neutralise the deflection. The net B.M. at the centre will be (A) WL (B) WL/8 (C) WL/24 (D) WL/32

Last Answer : (D) WL/32

Description : The thickness of web for unstiffened plate girder with clear distance‘d’ between the flanges shall be not less than

Last Answer : d/85

Description : A protective or decorative non-structural element placed at the level of the truss supports and column head is called (a) Eaves girder (b) Baluster (c ) Eaves board (d) Tie girder

Last Answer : (c ) Eaves board

Description : A uniformly distributed load (w) of length shorter than the span crosses a girder. The bending moment at a section in the girder will be maximum when (a) Head of the load is at the section (b) Tail ... load in the same ratio as it divides the span (d) Section divides the load in two equal lengths.

Last Answer : (c) Section divides the load in the same ratio as it divides the span

Description : In Case If Concrete Box Girder Bridges How Is The Number Of Cells Determined?

Last Answer : Answer : When the depth of a box girder bridge exceed 1/6th or 1/5th of the bridge width then the design recommended is that of a single cell box girder bridge. But in case the depth of ... the transverse load distribution when the number of cells of the box girder is higher than three or more.

Description : Metallising is the process of spraying of …. on the surface prepared girder.

Last Answer : Zinc.. or ..Aluminium.

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : The depth of 19.81 mlong service girder is about……… a)1.67 m b)1.16 m* c)0.95 m d)1.52 m

Last Answer : b)1.16 m*

Description : Shallow type girder can be used in a) ROBs b) RUBs* c) FOBs

Last Answer : b) RUBs*

Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level

Last Answer : b) commencing from bottom of girder towards bed level*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30 cumecs is a) 300 mm b) 1500 mm c) 1800 mm d) 600 mm*

Last Answer : d) 600 mm*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder