Entire steel work of girder bridge should be painted at regular interval; known as a) patch painting
b) periodical through painting*
c) Any of the above
d) None of the above

1 Answer

Answer :

b) periodical through painting*

Related questions

Description : When as small area of girder bridge should be painted when requiring immediate painting; known as a) patch painting* b) periodical through painting c) Any of the above d) None of the above

Last Answer : a) patch painting*

Description : The date of painting of steel work should be painted in white on the out side of the left girder a) of the 1st span only b) first span only but on all spans for Imp. Bridges* c) of the all spans d) None of the above

Last Answer : b) first span only but on all spans for Imp. Bridges*

Description : Corrosion in Steel girder bridges may be prevented by : a) Protective coatings by painting b) Metallising c) Use of epoxy based paints d) All the above*

Last Answer : d) All the above*

Description : A bridge having super structure with “Single or duplicate girders with cross sleepers on top flanges” is classified as a) RSJ girder bridge b) Cross Girder c) Deck plate girder* d) Open web girder

Last Answer : c) Deck plate girder*

Description : What is the clear distance between two consecutive bridge Timbers or Girder bridge? (a) 450 mm (b) 510 mm* (c) 500 mm (d) 520 mm

Last Answer : (b) 510 mm*

Description : Length of bridge timber in BG a) outer to outer of girder plus 305mm b) 2440mm c) whichever is more in a) & b)* d) whichever is less in a) & b)

Last Answer : c) whichever is more in a) & b)*

Description : Super structure of a bridge includes a) Girder/Slab* b) Abutment c) Piers d) Bed block

Last Answer : a) Girder/Slab*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Depth of construction in a girder bridge means the depth from a) RL to HFL b) RL to top of bed block * c) RL to bottom of bed block d) RL to Bed level

Last Answer : b) RL to top of bed block *

Description : Greasing of bearings of Steel girder bridges is done once in years.

Last Answer : Three

Description : What is the clear distance between two consecutive steel channel sleepers on Girder bridges? (a) 450 mm* (b) 510 mm (c) 500 mm (d) 460 mm

Last Answer : (a) 450 mm*

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : Steel channel sleepers are provided in bridges with superstructure of a) PSC slab b) PSC girder c) Steel girder* d) RCC Box

Last Answer : c) Steel girder*

Description : Camber in steel triangulated girder is provided to compensate for deflection a) Under live load and dead load* b) Under live load c) Under dead load d) None of the above

Last Answer : a) Under live load and dead load*

Description : Periodical Census of traffic at unmanned level Crossings should be done once in a) Once in 6 years b) Every year c) Once in 3 years* d) Once in 5 years

Last Answer : c) Once in 3 years*

Description : Periodical inspection of PSC & Composite girders a) Once in 3 years b) Once in 5 years * c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 5 years *

Description : Periodical inspection of Welded girders a) Once in 3 years b) Once in 3 years* c) Once in 2 years d) Once in 5 years

Last Answer : b) Once in 3 years*

Description : The load transferred from rails to web of girders is in a) deck type girder b) through type girder c) semi-through type girder* d) plate girder

Last Answer : c) semi-through type girder*

Description : The load transferred from rails to bottom flanges is in a) deck type girder b) through type girder* c) semi-through type girder d) plate girder

Last Answer : b) through type girder*

Description : Metallising is the process of spraying of …. on the surface prepared girder.

Last Answer : Zinc.. or ..Aluminium.

Description : Piano wire is used for measuring the a) Distortion b)Camber in PSC girder c)Both a & b* d)None of above

Last Answer : c)Both a & b*

Description : The depth of 19.81 mlong service girder is about……… a)1.67 m b)1.16 m* c)0.95 m d)1.52 m

Last Answer : b)1.16 m*

Description : Shallow type girder can be used in a) ROBs b) RUBs* c) FOBs

Last Answer : b) RUBs*

Description : Flood level gauge to be marked a) commencing from bed level to top b) commencing from bottom of girder towards bed level* c) commencing from Rail level d) commencing from Danger level

Last Answer : b) commencing from bottom of girder towards bed level*

Description : n Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 12.20 < 30.5 m a) 300 mm b) 600 mm* c) 500 mm d) 450 mm

Last Answer : b) 600 mm*

Description : In Girder and Slab Bridges Danger level should be marked below bottom of girders/slabs for water way is > 6.10 < 12.2 m a) 300 mm b) 600 mm c) 450 mm* d) 500 mm

Last Answer : c) 450 mm*

Description : Temporary arrangements for rebuilding of Railway bridges can be executed by providing a) Temporary girder b) Temporary diversion c) Any of the above* d) None of the above

Last Answer : c) Any of the above*

Description : Maximum vertical clearance (VC) for a slab/ girder bridges with discharge above 3000 cumecs is a) 300 mm b) 1500 mm c) 1800 mm* d) 600 mm

Last Answer : c) 1800 mm*

Description : Minimum vertical clearance (VC) for a slab/ girder bridges with discharge of 0-30 cumecs is a) 300 mm b) 1500 mm c) 1800 mm d) 600 mm*

Last Answer : d) 600 mm*

Description : Temporary staging for casting PSC Box Girder for a ROB over the Railway span shall be removed a) after hardening of concrete b) before hardening of concrete c) during concreting d) after stressing the cables

Last Answer : d) after stressing the cables

Description : In shallow type girders, the rail level shall be a) 25mm above the top flange of girder* b) near the bottom of the girder c) near the middle of the girder d) below the girder

Last Answer : a) 25mm above the top flange of girder*

Description : Initial inspection for PSC girders / Welded girder bridges as per IRBM 1998 a) Within one year of installation* b) Once in 3 years d) Once in 2 years d) Once in 5 years

Last Answer : a) Within one year of installation*

Description : Explain in brief expansion bearing for steel girder bridge.

Last Answer : Types of Expansion Bearing: 1. Sliding Plate Bearing 2. Deep cast with curve plate 3. Rocker bearing with curved base 4. Rocker & roller bearing Types of Expansion Bearing:  1. Sliding Plate ... and the bottom shoe. Bottom shoe rests on number of steel rollers.

Description : Contour interval on a map sheet denotes (a) Vertical distance of contour lines above the datum plane (b) Vertical distance between two successive contour lines (c) Slope distance between two successive contour lines (d) Horizontal distance between two successive contour lines

Last Answer : (b) Vertical distance between two successive contour lines

Description : Density of each compacted layer should be ascertained by taking soil samples on either side of Central Line at a) 5 meter interval b) 10 meter interval* c) 12 meter interval d) 15 meter internal

Last Answer : b) 10 meter interval*

Description : Name the paint used in A.T. Welding painting? (i) Black Paint (ii) Bituminous black IS:9862-1981.* (iii) Any type of black paint (iv) None of the above

Last Answer : (ii) Bituminous black IS:9862-1981.*

Description : Painting of weld is done up to (i) 10 CM minimum both side of weld & on welded surface .* (ii) 15 CM minimum both side of weld & on welded surface (iii) 20 CM minimum both side of weld & on welded surface (iv) None of the above

Last Answer : (i) 10 CM minimum both side of weld & on welded surface .*

Description : When was the collar painting done ? (i) After the welding * (ii) after one week of welding (iii) After 15 days of welding (iv) None of the above

Last Answer : (i) After the welding *

Description : Painting during night and early morning avoided because of

Last Answer : dew

Description : For painting, the unit of rate is per a) Sqm b) cum c) 10sqm * d) 10cum

Last Answer : c) 10sqm *

Description : While painting with Aluminium paint, a little quantity of ………..shall be added to the paint while doing the first coat to distinguish it from the second coat a) little blue paint* b) lamp black c) red paint d) green paint

Last Answer : a) little blue paint*

Description : While painting with red oxide paint, a little quantity of ………..shall be added to the paint while doing the first coat to distinguish it from the second coat a) little blue paint b) lamp black* c) red paint d) green paint

Last Answer : b) lamp black*

Description : When proposed depth of construction of a bridge is more than the existing depth of construction in a bridge work, the existing rail level requires a) Lowering b) Lifting* c) Slewing d) None

Last Answer : b) Lifting*

Description : In a temporary signaling arrangements for a bridge work in BG section, speed board shall be placed in advance of 30 m from the a) C.L. of the bridge b) Termination Board c) Start of the bridge/work spot* d) Caution Board

Last Answer : c) Start of the bridge/work spot*

Description : .In a temporary signaling arrangements for a bridge work in BG section, caution board shall be placed in advance of ……. m from start of the bridge/ work spot. a) 30 m b) 1200 m* c) 677 m d) 1000 m

Last Answer : b) 1200 m*

Description : A uniform girder simply supported at its ends is subjected to a uniformly distributed load over its entire length and is propped at the centre so as to neutralise the deflection. The net B.M. at the centre will be (A) WL (B) WL/8 (C) WL/24 (D) WL/32

Last Answer : (D) WL/32

Description : Deep screening of entire track must be done at least:- (a) Once in a quarter. (b) Once in a year. (c) Once in 5 years. (d) Once in 10 years.*

Last Answer : (d) Once in 10 years.*

Description : Foot over bridge must be provided on the following type of stations as per minimum essential facility criteria (a) A, B, C, & D class station (b) A,B & C class station* (c) A, & B class station (d) Only A class station

Last Answer : b) A,B & C class station*

Description : The project report of final location survey gives tabulated statement of the following (a) Curve abstract (b) Gradient abstract (c) Bridge abstract (d) Important bridges (e) Station machinery (f) Stations and stations sites (g) All the above*

Last Answer : g) All the above*

Description : Which of the following stone is best suited for construction of piers and abutments of Railway Bridge a) Granite* b) Sandstone c) Limestone d) Quartzite

Last Answer : a) Granite*