If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest
finish time, then the following relation holds good
(A) EF = ES + D
(B) LS = LF - D
(C) LF = LS + D
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : The EST + activity duration = .............................. a. Earliest Finish Time b. Latest Start Time c. Latest Finish Time d. None of these

Last Answer : a. Earliest Finish Time

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : To calculate early start (ES) and early finish (EF) perform a:  A. Backward pass B. Forward pass  C. Lateral pass D. Critical pass

Last Answer : B. Forward pass

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : For the same draw down in two observations wells at distances r1 and r2, the times after start of  pumping are t1 and t2 hours respectively. The relation which holds good is  (A) t2 = r2/r1 × t1 (B) t2 = (r2/r1)² × t1 (C) t2 = (r2/r1)3  × t1 (D) t2 = (r2/r1) × t1 2

Last Answer : (B) t2 = (r2/r1)² × t1

Description : In a PERT network, the earliest(activity) start time is the a. Earliest time that an activity can be finished without delaying the entire project b. Latest time that an activity can ... of precedence requirements d. Latest time that an activity can be finished without delaying the entire project

Last Answer : c. Earliest time that an activity can be started without violation of precedence requirements

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Earliest expected time is denoted by TE (B) Latest occurrence time is denoted by TL (C) Contractual obligation time is denoted by Ts (D) All the above

Last Answer : (D) All the above

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : What are the earliest and latest possible dates, on the common Roman calendar, for the Hebrew Festival of Shabuot, the Feast of Weeks, or Pentecost?

Last Answer : It always falls 49 days from the second day of Passover. (7 weeks ). Those 49 days are known as the Counting of the Omer. (The 33rd day - Lag B'omer) is considered a holiday to spend ... Pesach can be anywhere between mid-March and late April. Quick consult a Jewish calendar. The date is variable.

Description : What are your personal guidelines as far as the earliest in the day you'll call someone and the latest in the evening you'll call, if you don't know their sleep/wake habits?

Last Answer : 10am, 9pm.

Description : Why doesn't the summer solstice have the earliest sunrise or latest sunset of the year?

Last Answer : It's supposed to be the longest day of the year, right? What gives?

Description : Backward pass calculations are done to find ________ occurrence times of events a. Tentative b. Definite c. Latest d. Earliest

Last Answer : c. Latest

Description : Forward pass calculations are done to find _____ occurrence times of events a. Exact b. Earliest c. Latest d. Approximate

Last Answer : b. Earliest

Description : If the roots of the equation x^2 + x + 1 = 0 are in the ratio of m : n, then which one of the following relation holds ? -Maths 9th

Last Answer : answer:

Description : The latest finish time for an activity: A. Equals the min. of LFT − t for al immediate successors B. Equals the max. of LFT − t for al immediate predecessors. C. Equals the max. of EST + t for all immediate predecessors. D. Equals the min. of EST + t for all immediate successors

Last Answer : A. Equals the min. of LFT − t for al immediate successors

Description : lf the poles of system are lying on the imaginary axis in s-plane, then the system will be

Last Answer : lf the poles of system are lying on the imaginary axis in s-plane, then the system will be marginally stable

Description : In a dynamic vibration absorber system, under tuned conditions which of the following relation holds good? A K 1 K 2 =M 1 M 2 B K 1 M 2 =M 1 K 2 C K 1 M 1 = K 2 M 2 D none of the mentioned

Last Answer : B K 1 M 2 =M 1 K 2

Description : For a database relation R(a, b, c, d) where the domains of a, b, c, d include only the atomic values. The functional dependency a → c, b → d holds in the following relation (A) In 1NF not in 2NF (B) In 2NF not in 3NF (C) In 3NF (D) In 1NF

Last Answer : (A) In 1NF not in 2NF 

Description : Total float in a planning network is (a) Late start time – Early start time (b) Early start time – Late start time (c) Late start time – Late finish time (d) Late finish time – Early finish time

Last Answer : Ans: (a & d)

Description : If a concrete column 200 200 mm in cross-section is reinforced with four steel bars of 1200  mm2  total cross-sectional area. Calculate the safe load for the column if permissible stress in  concrete is 5 N/mm2 ... 15 Ec (A) 264 MN  (B) 274 MN  (C) 284 MN  (D) 294 MN 

Last Answer : (C) 284 MN 

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : In given figure, AD = 3 cm, AE = 5 cm, BD = 4 cm, CE = 4 cm, CF = 2 cm, BF = 2.5 cm, then (a) DE || BC (b) DF || AC (c) EF || AB (d) none of

Last Answer : (c) EF || AB

Description : If ΔABC ~ ΔEDF and ΔABC is not similar to ΔDEF then which of the following is not true? (a) BC.EF = AC.FD (b) AB.EF = AC.DE (c) BC.DE = AB.EF (d) BC.DE = AB.FD

Last Answer : (c) BC.DE = AB.EF

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : A pie was cut into 8 equal slices .lf Ruben ate 3/4 of the pie ,how many slices did he eat?

Last Answer : For my kid

Description : In what range of frequencies are most omnidirectional horizontally polarized antennas used? A. VHF, UHF B. VLF, LF C. SH, EHF D. MF, HF

Last Answer : A. VHF, UHF

Description : Which frequency bands can be refracted during the day by the D layer? A. VLF B. MF C. LF D. Both VLF and LF

Last Answer : D. Both VLF and LF

Description : Where does the AM broadcast band located in the spectrum band? A. HF band B. VHF band C. LF band D. MF band

Last Answer : D. MF band

Description : In what frequency band is the ATIS normally broadcasted?  a. LF  b. HF  c. ADF  d. VHF

Last Answer : d. VHF

Description : Which frequency band is a wavelength of 1200m? a. UHF b. LF c. HF d. MF

Last Answer : b. LF

Description : In what frequency band is the ATIS normally broadcasted? a. LF b. HF c. ADF d. VHF

Last Answer : d. VHF

Description : yo presented by hx of syncope when he do excurses and there was hix of same complain when he on rest . and there is chest pain on ex. There was ejection systolic murmur ... t changing and there is lf atrium enlargement Aortic stenosis p.s hypertrophic cardiomyopathy constrictive cardiomyopathy

Last Answer : Aortic stenosis

Description : lf the series 4,5,8,13,14,17,22,........ is continued in the same pattern, which one of the following is not a term of this series? (A) 31 (B) 32 (C) 33 (D) 35

Last Answer : Answer: C

Description : "lf a large diamond is cut up into little bits, it will lose its value just as an army is divided up into small units of soldiers, it loses its strength." The argument put above may be called as (A) Analogical (B) Deductive (C) Statistical (D) Casual

Last Answer : (A) Analogical

Description : The VLF and LF bauds use .............. propagation for communication. (A) Ground (B) Sky (C) Line of sight (D) Space

Last Answer : Answer: A Explanation: VLF (Very Low Frequency) LF (Low Frequency) In general there are three type of propagation.1.Ground Propagation 2.Sky propagation 3.Line-of-sight propagation ... portion of the atmosphere. These low-frequency signals travel in all directions from the transmitting antenna.

Description : lf the wire which is vertical to this page has electron flow downwards the conductor will have

Last Answer : lf the wire which is vertical to this page has electron flow downwards the conductor will have a counter-clockwise field in the plane of the paper

Description : lf a travelling-wave travelling along a loss-less overhead line does not result in any reflection after it has reached the far end, then the far end of the line is

Last Answer : lf a travelling-wave travelling along a loss-less overhead line does not result in any reflection after it has reached the far end, then the far end of the line is terminated into a resistance equal to surge impedance of the line

Description : lf slip of an induction machine is 0.02 and the stator supply frequency is 50 Hz, what will be the frequency of the rotor induced e.m.f.? (A) 10 Hz (B) 50 Hz (C) 1 Hz (D) 2500 Hz

Last Answer : 1hz