In case the factor of safety against sliding is less than 1.5, a portion of slab is constructed
downwards at the end of the heel slab, which is known as
(A) A key
(B) A cut-off wall
(C) A rib
(D) All the above

1 Answer

Answer :

Answer: Option D

Related questions

Description : If"w" is weight of a retaining wall and is the horizontal earth pressure, the factor of safety against sliding, is (A) 1.0 (B) 1.25 (C) 1.5 (D) 2.0

Last Answer : Answer: Option C

Description : In a T-beam , the breadth of the rib is equal to the (a) Total thickness of the slab, including cover (b) Width of the portion of the beam in the compression zone (c) Width of the portion of the beam in the compression zone (d) All the above.

Last Answer : (c) Width of the portion of the beam in the compression zone

Description : In a cantilever retaining wall without a heel slab (A) Thickness of the stem is kept same throughout (B) Base slab is made 10 cm thicker than the stem (C) Width of the base slab is kept 0.7 time the total height of the wall (D) All the above

Last Answer : Answer: Option D

Description : The toe projection of foundation slabs is taken (A) As one third of the base (B) As one sixth of overall height of the wall (C) Equal to heel slab (D) Below ground surface

Last Answer : Answer: Option A

Description : Pick up the incorrect statement from the following: (A) In the stem of a retaining wall, reinforcement is provided near the earth side (B) In the toe slab of a retaining wall, reinforcement is ... slab of a retaining wall, reinforcement is provided at the top of the slab (D) None of these

Last Answer : Answer: Option D

Description : The design of heel slab of a retaining wall is based on the maximum bending moment due to: (A) Its own weight (B) Weight of the soil above it (C) Load of the surcharge, if any (D) All the above

Last Answer : Answer: Option D

Description : Factor of safety against sliding of a slope, is the ratio of (A) Actual cohesion to that required to maintain stability of slope (B) Shear strength to shear stress along the surface (C) Neither (a) nor (b) (D) Both (a) and (b)

Last Answer : Answer: Option D

Description : On the ladder resting on the ground and leaning against a smooth vertical wall, the force of  friction will be  (A) Downwards at its upper end  (B) Upwards at its upper end  (C) Perpendicular to the wall at its upper end  (D) Zero at its upper end 

Last Answer : (D) Zero at its upper end 

Description : On a ladder resting on smooth ground and leaning against vertical wall, the force of friction will be (A) Towards the wall at its upper end (B) Away from the wall at its upper end (C) Upwards at its upper end (D) Downwards at its upper end

Last Answer : (C) Upwards at its upper end

Description : For a ribbed slab (A) Clear spacing between ribs shall not be greater than 4.5 cm (B) Width of the rib shall not be less than 7.5 cm (C) Overall depth of the slab shall not exceed four times the breadth of the rib (D) All the above

Last Answer : Answer: Option D

Description : The width of the flange of a T-beam should be less than (A) One-third of the effective span of the T-beam (B) Distance between the centres of T-beam (C) Breadth of the rib plus twelve times the thickness of the slab (D) Least of the above

Last Answer : Answer: Option D

Description : The width of the flange of a L-beam, should be less than (A) One-sixth of the effective span (B) Breadth of the rib + four times thickness of the slab (C) Breadth of the rib + half clear distance between ribs (D) Least of the above

Last Answer : Answer: Option D

Description : The wall constructed for the stability of an excavated portion of a road on the hill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option B

Description : The wall constructed for the stability of a back filling portion of a road on the downhill side, is known as (A) Retaining wall (B) Breast wall (C) Parapet wall (D) All the above

Last Answer : Answer: Option A

Description : Pick up the incorrect statement from the following: (A) The retaining wall should be structurally capable to resist the applied earth pressure (B) The section of the retaining wall should be so ... off water from the earth retained, weep holes are provided near the top of the retaining wall

Last Answer : Answer: Option D

Description : In counterfort type retaining walls (i) The vertical slab is designed as a continuous slab (ii) The heel slab is designed as a continuous slab (iii) The vertical slab is designed as a cantilever (iv) The heel slab is designed ... (ii) (B) (i)and(iv) (C) (ii) and (iii) (D) (iii) and (iv)

Last Answer : Answer: Option A

Description : In a T-beam, the vertical distance between the bottom of the flange and the centre of the tensile reinforcement is (a) Breadth of flange (b) Thickness of flange (c) Breadth of slab (d) Depth of rib

Last Answer : (d) Depth of rib

Description : The breadth of the flange of a T-beam is (a) 1/3rd of the effective span of the T-beam (b) Twelve times the depth of slab plus breadth of rib. (c) Centre to centre distance between the adjacent beam. (d) Least of (a) , (b) or (c)

Last Answer : (d) Least of (a) , (b) or (c)

Description : Coulomb's wedge theory assumes that (A) Back fill is dry, cohesionless, homogeneous and isotropic (B) Slip surface is the plane which passes through the heel of the wall (C) Position and direction of the resultant earth pressure are known (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The roof slabs of multi-storeyed buildings are constructed monolithically to carry the various floor loads (B) The beams of multi-storeyed ... slab is spanned across the secondary beams provided between the main beams (D) All of these

Last Answer : Answer: Option D

Description : In a constant level tube, size of the bubble remains constant because upper wall is (A) Of relatively larger radius (B) Of relatively smaller radius (C) Flat (D) Convex downwards

Last Answer : (A) Of relatively larger radius

Description : A failure wedge develops if a retaining wall (A) Moves away from the backfill (B) Moves towards the backfill (C) Sinks downwards (D) Stresses equally by vertical and horizontal forces

Last Answer : Answer: Option A

Description : Pick up the correct statement from the following: (A) The artificial barrier constructed to enclose "n area for safe anchorage, is called break water (B) The smoothened surface at the top end of ... fending (C) The effective berthing lengths of inclined guays can be adjusted (D) All the above

Last Answer : (D) All the above

Description : The reinforcement in a continuous slab is provided (a) At the top of the slab portion over the intermediate supports. (b) At the bottom of the slab portion over the intermediate supports. (c) All the middle of the slab portion over the intermediate supports (d) All the above

Last Answer : (a) At the top of the slab portion over the intermediate supports.

Description : The portion of the slab which acts monolithically with the beam and which resists the compressive stresses, is called _________of flange of the T-beam (a) Length (b) Breadth (c) Thickness (d) Depth

Last Answer : (b) Breadth

Description : The main reinforcement in the heel of a T-shaped R.C. retaining wall is provided on (A) Top face perpendicular to wall (B) Bottom face perpendicular to wall (C) Both top and bottom faces perpendicular to wall (D) None of these

Last Answer : Answer: Option A

Description : For a slab supported on its four edges with corners held down and loaded uniformly, the Marcus correction factor to the moments obtained by Grashoff Rankine's theory (A) Is always less than 1 (B) Is always greater than 1 (C) Can be more than 1 (D) Can be less than 1

Last Answer : Answer: Option A

Description : My head and tail both equal are, My middle slender as a bee. Whether I stand on head or heel Is quite the same to you or me. But if my head should be cut off, The matter's true, though passing strange Directly I to nothing change.What Am I? -Riddles

Last Answer : The figure eight.

Description : The stability of a dam is checked for (A) Tension at the base (B) Overturning of the wall or dam (C) Sliding of the wall or dam (D) All of these

Last Answer : Answer: Option D

Description : Parapet walls along hill roads, are provided (A) To retain the back filling (B) To prevent the hill from sliding (C) To prevent the wheels of the vehicle from coming on the retaining wall (D) None of these

Last Answer : Answer: Option C

Description : It is always provided on each end of the cutter bar to regulate the height of cut and to provide easy and smooth sliding of the cutter bar on the land. b. Plate c. pitman d. None of above

Last Answer : Ans-    b. shoe

Description : A rail which is tapered to a toe at one end and has a heel at the other end is called as : a) Stock rail b) Tongue rail c) Wing rail d) Lead rail

Last Answer : b) Tongue rail

Description : Describe the procedure of laying a floor finish on a newly constructed slab.

Last Answer : 1. Slab is cleared off from loose mortar deposited during plaster work and level the surface. 2. Chalk out the marking on wall @ 0.6 m above the slab surface in one level. 3. Construct mortar dots at four ... and lay the tile in line and level. 8. Repeat point no 7 procedure up to door corner.

Description : The portion of a brick cut to form angles other than right angles in plan, is known as (A) Queen closer (B) King closer (C) Closer (D) Squint brick

Last Answer : Answer: Option D

Description : It is easier to roll a barrel than to pull it because (a) the full weight of the barrel comes into play when it is pulled (b) rolling friction is much less than sliding friction (c) the surface ... in contact with the road is more in the case of pulling (d) of a reason other than those mentioned

Last Answer : Ans:(b)

Description : For the design of retaining walls, the minimum factor of safety against overturning is taken as (A) 1.5 (B) 2.0 (C) 2.5 (D) 3.0

Last Answer : Answer: Option B

Description : The temperature reinforcement in the vertical slab of a T-shaped R.C. retaining wall is (A) Not needed (B) Provided equally on inner and front faces (C) Provided more on inner face than on front face (D) Provided more on front face than on inner face

Last Answer : Answer: Option D

Description : If is the overall height of a retaining wall retaining a surcharge, the width of the base slab usually provided, is (A) 0.3 H (B) 0.4 H (C) 0.5 H (D) 0.7 H

Last Answer : Answer: Option D

Description : The clear cover in a simply supported slab should not be less than the diameter of the reinforcing bar (a) Correct (b) Incorrect’ (c) Not known (d) None of these

Last Answer : (a) Correct

Description : Enlarged head of a supporting column of a flat slab is technically known as (A) Supporting end of the column (B) Top of the column (C) Capital (D) Drop panel

Last Answer : Answer: Option C

Description : The portion of the brick cut across its width and having its length equal to that of a full brick, is known as (A) Closer (B) Queen closer (C) King closer (D) Prince closer

Last Answer : Answer: Option B

Description : The thickness of base slab of a retaining wall generally provided, is (A) One half of the width of the stem at the bottom (B) One-third of the width of the stem at the bottom (C) One fourth of the width of the steam at the bottom (D) Width of the stem at the bottom

Last Answer : Answer: Option D

Description : The effective span of a simply supported slab, is (A) Distance between the centres of the bearings (B) Clear distance between the inner faces of the walls plus twice the thickness of the wall (C) Clear span plus effective depth of the slab (D) None of these

Last Answer : Answer: Option B

Description : If P kg/m2 is the upward pressure on the slab of a plain concrete footing whose projection on either side of the wall is a cm, the depth of foundation D is given by (A) D = 0.00775 aP (B) D = 0.0775 aP (C) D = 0.07775 aP (D) D = 0.775 Pa

Last Answer : Answer: Option A

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : Find the correct statement from the followings. (a) For a cantilever slab, the ratio of span to overall depth should not 12. (b) One way slab which carry uniformly distributed load should be designed to ... be designed to resist a hogging moment at the face of the support. (d) All of the above.

Last Answer : (d) All of the above.

Description : Pick up the incorrect statement from the following: (A) The width of the wall is constructed thicker at the base in a stepped fashion (B) A long vertical load transferring concrete structure is ... ) The pile which transfers the load to a hard rock bed at certain depth is called load bearing

Last Answer : Answer: Option D

Description : Brick nogging type of partition wall, is constructed by (A) Laying bricks as stretchers in cement mortar (B) Laying bricks as headers in cement mortar (C) Reinforcing brick wall with iron straps (D) Constructing brick work within a wooden framework

Last Answer : Answer: Option D

Description : The horizontal portion of a step in a stairs case, is known as (A) Rise (B) Flight (C) Winder (D) Tread

Last Answer : Answer: Option D

Description : I cut my heel open and I still can't walk. How much longer?

Last Answer : answer:Your doctor is the only one that can tell you how much longer this is going to take. The length of time is dependent on the severity of your injury, your body's healing time, and ... up appointment scheduled with your doctor, you should make on so you can discuss your concerns with them.