Explain the procedure of the storage, transportation and erection of prefabricated building elements. 

1 Answer

Answer :

Storage of pre-fabricated building elements:

1) Procurement storage of Unloading raw materials

2) Testing of raw materials

3) Design of concrete mix

4) Fabrication of reinforcement cages

5) Oiling and laying of moulds in portion

6) Placing of reinforcement cages inserts and fixtures

7) Preparation of fresh concrete

8) Transport fresh concrete

9) De-pouring into mould etc.

10) Curing of concrete

11) Stacking of pre-cost element

12) Testing of finished Component


Transport of pre-fabricated building elements:

1) Transport of prefabrication elements must be carried out and with extreme care to avoid any flock and distress in elements and handled as far as possible to be placed in final portion.

2) Transport of prefab elements inside the factory depends on the method of production selected for the manufacture.

3) Transport of prefab elements from the factory to the site of action should be planned in conformity with the trafficable rules and regulations as stipulated by the authorities the size of the elements is often restricted by the availability of suitable transport equipment, such as tractor-am-tailor, to suits the load and dimension of the member in addition to the load carrying capacity of the bridges on the way.

4) While transporting the prefab elements in various systems, such as wages, trucks, bullock cards etc. care should be taken to avoid excessive cantilever actions and desired supports are maintained. Special care should be taken in negotiating sharp beds uneven of slushy roads to avoid undesirable stresses in elements and in transport vehicles.

5) Before loading the elements in the transporting media, care should be taken to ensure the base packing for supporting the elements are located at specified portion only.


Erection of pre-fabricated building elements.

1) It is the process of assembling the Prefabrication element in the find portion as per the drawing. In the erection of prefab elements, the following items of work are to be carried out.

2) Slinging of the prefab elements.

3) Tying up of erection slopes connecting to the erection hooks.

4) Cleaning the elements and the site of erection.

5) Cleaning the steel inserts before incorporation in the joints lifting and setting the elements to correct position.

6) Adjustments to get the stipulated level line and plumb.

7) Welding of cleats.

8) Changing of the erection tackles.

9) Putting up and removing the necessary scaffolding or supports.

10) Welding the insorts laying the reinforced in joints.

11) The erection work in various construction jobs by using prefab elements differs with risk condition, hence skilled foremen, and workers to be employed on the job.


Related questions

Description : Depict the effect of pre-fabricated building on the surrounding environment with respect to noise pollution, staking at elements and transportation. 

Last Answer : Noise pollution is the serious or more noise that may damage the activity or human life. The contribution of most outside noise is mainly due to building activities. Noise pollution affects both health and ... iv) Sleep interference v) Habit of talking loudly vi) Hearing loss vii) Concentration

Description : Explain freyssinet system of prestressing with respect to process and application with sketches.

Last Answer : Process: - 1. The freyssinet system was the first to be introduced among the post - tensioned system high tensile steel wires 5mm to 8mm diameter about 12 in number are arranged to form a group into a cable ... gas (LNG) storage tank 4. Off share platforms. 5. Wind turbine towers etc.

Description : Explain the loss of prestress due to friction and slip of anchorage and state two remedial measures to avoid them.

Last Answer : Loss due to Friction: This loss occurs only in post-tensioned members. There always exists a certain amount of friction in the jacking and anchoring system and on the walls of the duct. So, ... over-extending the tendon in the prestressing operation by the amount of the draw - in before anchoring

Description : Explain any one method of Prefab system.

Last Answer : Prefab system: It refers to any part of a building that has been fabricated at a place other than its final location. For this reason, it can be referred to by other names such as off-site fabrication, ... If you need further assessing, feel free to contact us; your needs are all that matter to us.

Description : Explain determination of Water absorption of paver block and state acceptable limits as per IS. 

Last Answer : Step 1. Saturation  The test specimen shall be completely immersed in water at room temperature for 24 * 2 h. The specimen then shall be removed from the water and allowed to drain for 1 min by ... more than 6 % by mass and in individual samples, the water absorption should be restricted to 7 %

Description : For what type of structures do you recommend post-tensioning?

Last Answer : 1) High rise buildings. In long span slab where beam is not provided & the slab of assembly hall, cinema theaters etc. like structure where the distance between columns are more, then post ... Post Tensioning is used extensively for slabs on grade where soils are likely to move (expansive soils)

Description : Illustrate cable profiles for eccentric straight and parabolic cables with sketches. 

Last Answer : i) Eccentric straight cable profile: The stress due to prestressing alone are generally combined stresses due to the action of direct load bending from an eccentrically applied load. In this case, the load is ... section as shown in the figure below. ii) Parabolic cable profile

Description : State the advantages and disadvantages of prestressed concrete.

Last Answer : Advantages: 1. The c/s ismore efficiently used in fully prestressed members. 2. Dead loads are reduced considerably. 3. Improved shear resistance, due to the effect of compressive prestress, ... cube strength of 35 N/mm2 for Posttensioned system and 45 N/ mm2 for pretensioned system.

Description : Justify the necessity of use of high-grade materials in prestressed concrete.

Last Answer : 1) If mild steel is used, the working stress in it (i.e. 140 N/mm2) is more or less completely lost due to elastic deformation, creep and shrinkage of concrete. 2) The ... structural elements. With reduced dead weight of the material, larger spans become technically and economical practicable. 

Description : Describe with sketch any two joints in doors and window frame.

Last Answer : 1. Connections must be adequate structurally. 2. Means of connections between adjacent must allow safe and speedy erection regardless of minor inherent inaccuracies in precast elements and in-situ concrete. 3. ... height) of the frames shall confirm to the requirements of IS : 4021-1976

Description : Describe any two design considerations for Precast Canal lining.

Last Answer : 1. Precast concrete slabs, laid properly on carefully prepared sub-grades and with the joints, effectively sealed, constitute a serviceable type of lining. The precast slabs are about 5 to ... . However, seepage losses are obviously more. Transportation of precast slabs may contribute to breakage. 

Description : State any four advantages and four disadvantages of precast concrete.

Last Answer : Advantages: 1. Very rapid speed of erection 2. Good quality control 3. Entire building can be precast-walls, floors, beams, etc. 4. Rapid construction on site 5. High quality because of ... is required in the application of the panel on site. 11. Cranes are required to lift panels.

Description : State cable profile in simply supported rectangular beam section.

Last Answer : Cabe profile: In a prestressed concrete member, external type of loads is balanced by transverse component of suitable cable profile, on effect of loading the net deformation increases the stress, strain and length of the tendon, extension of tendon, increase in strain, increase in stress.

Description : List the various types of losses of prestress in pretensioned pre-stressed member.

Last Answer : i. Elastic shortening ii. Shrinkage of concrete iii. Creep of concrete iv. Relaxation of steel

Description : What is the basic principle of Prestressed concrete?

Last Answer : Principle: The compressive stresses induced by high strength steel tendons in a concrete member before the application of load, will balance the tensile stresses imposed in the member during its service.

Description : Define Prestressed concrete and state types of prestressing steel.

Last Answer : Prestressed concrete: Prestressed concrete is basically a concrete in which internal stresses of a suitable magnitude and distribution are deliberately introduced so that the stresses resulting from external loads are ... 1962, and. 4) Uncoated stress relieved strand conforming to IS: 6006-1970. 

Description : Define Modules and modular co-ordination

Last Answer : Modules: Modules are a standard unit of size used to coordinate the dimensions of buildings and components. They are of two types: 1. Multi modules 2. Basic modules  Modular Co-ordination: The modular ... for basic module is M 1M = 100mm 100 mm = 1M = It is international standard value.

Description : State any four precast non-structural components that can be used for speedy construction.

Last Answer : 1. Architectural Precast 2. Insulated Architectural Cladding 3. Insulated Wall Panels 4. Column Covers 5. Precast Concrete Light Wall 6. Precast Concrete Spandrels 7. Precast Concrete Solid Walls 8. Stormwater Deflector 9. Façade 10. Concrete panels for partition walls 11. Concrete planks

Description : State any two names of materials used in precast concrete

Last Answer : 1. Cement 2. Sand 3. Steel 4. Water 5. Polystyrene 6. Fly ash. 7. Ground granulated blast furnace slag

Description : Have you heard the prefabricated steel structure building?

Last Answer : Our life? Are we married?

Description : In India, are prefabricated components costlier than those of traditional cast-in-situ items that the prefabricated components replace? (A) Yes, because of heavier overheads and handling cost (B) Yes, ... of repetitive manufacture of a number of elements (D) No, because of savings in site labour

Last Answer : (C) No, because of repetitive manufacture of a number of elements

Description : Consider the following activities in a building construction: 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace The correct sequence of these ... (B) 3, 1, 4, 2 (C) 3, 1, 2, 4 (D) 1, 3, 4, 2

Last Answer : (C) 3, 1, 2, 4

Description : How many years can a block of flats with normal modifications last? 300 years?

Last Answer : if there were no design and implementation errors, certainly 100, easily even 150 300 years will require major repairs, but technically and economically realistic it is

Description : If you have a requirement to buy a large commercially available prefabricated wash rack?

Last Answer : Need answer

Description : What prefabricated decks work well on a slope?

Last Answer : A Mechanical type prefabricated decks work well on a slope. For more information of the product, you can also visit this site http://www.deckhouse.com/.

Description : Which of the following is NOT a porous absorber? A. Prefabricated tiles B. Plasters and spray on materials C. Acoustic blankets D. Membrane absorber

Last Answer : D. Membrane absorber

Description : New Yorkers, how do you feel about the Kushner Corp.'s idea for a large erection on Fifth Avenue?

Last Answer : Appropriate address for the family of The Anti-Christ.

Description : How do you stop a erection?

Last Answer : think of your mother,naked, on a cold day.

Description : Fluther Men: At what age did you get your first erection?

Last Answer : 12 or 13 for mean. I cant remember for sure.

Description : Am 45 and my penis is not getting erected in the morning as it used to be? What can I do to enhance my testeron and get better stamina, energy and erection?

Last Answer : See a urologist immediately, and do exactly what s/he advises.

Description : My new partner is 5 years older than me. I don't know why, but when "cuddling" with her I can't get an erection, I've been desperate, it never happened to me. Like I'm scared of something, I ... want to sleep with her, it just doesn't work. Any advice? Don't know any over-the-counter erection drugs?

Last Answer : It is a problem of many couples where the partner is older. It is not a unique phenomenon of today's society. The worst case in this case is if they do not explain it to each other face to face, or if they do not go to a specialist for counseling.

Description : I would like to know how it is with hygiene regarding the menstrual cycle with women in a coma? And a similar question occurred to me when I heard about Schumachr, what about erections? I'm no pervert, it's just out of curiosity ...

Last Answer : Menstruation and erection are 2 different things .... :) Yes they have Menstruation even in a coma ... with that erection it's the same ... the coma is stronger than REM sleep .. but they also have an erection ... never just exceptionally ☢ ☠ ☣ ☠ ☣ ☠ ☣ ☠ ☢

Description : How long does a female erection last?

Last Answer : Need answer

Description : How do I get a erection on crystal meth?

Last Answer : Need answer

Description : Erection problems?

Last Answer : DefinitionAn erection problem is the inability to get or maintain an erection that is firm enough for a man to have satisfactory intercourse. You may be unable to get an erection at all, or you may ... man's self esteem and harm his relationship with his partner, and thus requires treatment.If you

Description : Recently I had double inguinal hernia surgery after surgery I developed a staph infection. I'm still experiencing numbness in the surgical site areas. my question is since the surgery i've had problems maintaining an erection could there have been damage?

Last Answer : It is possible, you should contact a doctor about this.

Description : What medicines are available for erection problems?

Last Answer : Medicines that are available for erection problems are Viagra, Trazodone, Phetolamine, Yohimbine, Apomorphine, and Alprostadil. The most efficient medicine available is Viagra because an enzyme within Viagra turns off the erection.

Description : In male sex organs _______ system is responsible for erection. (a) Sympathetic (b) Parasympathetic (c) Norepinephrine (d) None of the above

Last Answer : Ans: B

Description : In erection of falsework, for a rectangular panel inside a falsework should it be braced along the two diagonals?

Last Answer : When a rectangular panel is subject to an eccentric load or a lateral load, it tends to deform into a parallelogram with one diagonal shortening and the other elongating. Theoretically, it is sufficient to ... may come from both sides of the panel and hence it should be braced in both diagonals.

Description : During erection, the pile of length is supported by a crane at a distance of (A) 0.207 l (B) 0.293 l (C) 0.707 l (D) 0.793 l

Last Answer : (C) 0.707 l

Description : What is the purpose of rotating the gimbal assembly in a gyro using a mercury erection system?

Last Answer : Applies torque at the proper point for correct precession.

Description : What is the purpose of an erection system used with a gyro?

Last Answer : To achieve and maintain the proper operating position for the gyro (usually vertical or horizontal).

Description : Which of the following cannot be treated as revenue expenditure? A. Cost of goods purchased for resale. B. Wages paid for the erection of plant and machinery. C. Obsolescence cost. D. Expenses incurred by way of repairs of existing assets which do not in any way add to their earning capacity.

Last Answer : B. Wages paid for the erection of plant and machinery.

Description : One of the following works does not require CRS sanction a) Regirdering/ Rebuilding b) Erection of new FOB c) Erection of platform shelter* d) Pipe line crossing

Last Answer : c) Erection of platform shelter*

Description : Prolonged painful erection of penis has been noted particularly as a side effect of: A. Doxepin B. Citalopram C. Bupropion D. Trazodone

Last Answer : D. Trazodone

Description : Can Arduino be used for building a smart transportation system?

Last Answer : Yes, Arduino can be used for building a smart transportation system by using sensors to measure various parameters such as traffic flow and air quality, and by using communication modules to transmit data to a control system to optimize transportation management.

Description : What was a democratic party argument against the building of transportation systems by federal government?

Last Answer : The plan would result in domination of the country by specialinterests.

Description : (i) Suggest the relevant method of water-proofing used for following construction. 1) Basement of buildings. 2) Swimming pool. 3) Water tank. (ii) Suggest the relevant method of transportation of ... 1) Concreting in hilly areas. 2) Concreting of high-rise building. 3) Concreting under water.

Last Answer : Method of water-proofing for: 1) Basement of buildings: Waterproofing by using waterproof sealants. 2) Swimming pool: Waterproofing by spraying or grouting in cracks. 3) Water tank: Waterproofing by ... , concrete pump, slip form technique. 3) Concreting under water: Tremie pipe, grout pipe.

Description : Presence of force moisture in coal is most disadvantageous during its (A) Transportation and handling (B) Washing (C) Pulverisation (D) Storage

Last Answer : (C) Pulverisation

Description : A secondary -use package can best be defined as one that A)can be used as a promotional tool. B)can be reused for purposes other than its initial use. C)facilitates transportation, storage, and handling for middlemen. D)is recyclable and environmentally safe.

Last Answer : A)can be used as a promotional tool.