Which is the ‘Slack Season’ in the Indian Economy? -Do You Know?

1 Answer

Answer :

answer:

Related questions

Description : Which is the ‘Slack Season’ in the Indian Economy? -Do You Know?

Last Answer : answer:

Description : 1. Most of the explosions in mines occur due to the mixing of things? 2. Which is the Slack Season' in the Indian Economy? 3. Which metal causes Itai-itai disease? 4. Which state is ... area of the world? 20. From where The Great Granary of the Indus Valley Civilization has been discovered?

Last Answer : Answer : 1. Oxygen with acetylene 2. Jan.-June 3. Cadmium 4. Arunachal Pradesh 5. Kabir 6. 40,000 7. Directive Principles 8. A pin hole box 9. Cirques 10. 1764 11. 1946 12. Cost of ... process 15. Lord Amherst 16. Habeas Corpus 17. Sand and silicates 18. 1874 19. Pastoral herding 20. Mohenjodaro

Description : 1. What is the number of electrons in an atom of atomic number Z and mass number A? 2. With which of the following fields is M. F. Hussain associated? 3. Which is the Slack Season' in ... 19. What are Shield volcanoes? 20. Mughal dynasty was to Bahadur Shah Zafar-as what was Lodi dynasty to?

Last Answer : Answer : 1. Z 2. Painting 3. Jan.-June 4. Australia 5. Valanadu 6. Stomata 7. 9th December, 1946 8. Measuring flask 9. China 10. Rajaraja Chola I 11. Vocal music 12. Abidjan 13. ... N. Rao 17. By radiation only 18. Useful but need strict regulation 19. Repeated lava flows 20. Ibrahim Lodi

Description : In Indian agriculture, the period from July to October November is called - (1) Rabi season (2) Kharif season (3) Pre-kharif season (4) Slack season

Last Answer : (2) Kharif season Explanation: Ratna is a resistant variety of rice. This paddy variety takes about 130-135 days to grow. The main states growing this variety are Bihar, Madhya Pradesh, Assam, West Bengal, Orissa, Terai region of UP, Punjab, Haryana and Tamil Nadu.

Description : How is Indian economy ? -Do You Know?

Last Answer : answer:

Description : Should we privileged people of the US cut some slack to those immigrants from 3rd world nations on possible body odor?

Last Answer : answer:I've heard these same comments most frequently made about the French and last I checked, they're not exactly a Third World country (many apparently don't believe in either frequent bathing nor in ... conference for movement theater performers.) And this was in a week or two in the summer :).

Description : Northern automobile driving jellies, what precautions are you taking with west bound traffic and are you cutting them some slack due to the glare in the afternoon?

Last Answer : I try to be hyper aware, and I always assume they can’t see me. Like you, I stay waaaaay to the right, and sometimes I find alternate routes when I know (from experience) that visibility is zero on some roads.

Description : As a spider ascends a single strand of silk web where does the slack go?

Last Answer : I believe that some spiders eat the strand of silk as they ascend. Source

Description : Hatch-Slack pathway is present in which type of plants? -Biology

Last Answer : answer:

Description : In Hatch-Slack pathway, carboxylation occurs how many times? -Biology

Last Answer : answer:

Description : In Hatch-Slack pathway, carboxylation occurs how many times? -Biology

Last Answer : answer:

Last Answer : Hatch and Slack are Australian citizens

Last Answer : The C4 path of CO2 degradation Of the discoverer By name Hatch, Snack Cycle Says.

Description : Why telephone wires need to be slack in the summer?

Last Answer : Feel Free to Answer

Description : Select the correct statement: (1) C4 pathway for. CO2 fixation were discovered by Hatch and Slack (2) CO2 is essential for photosynthesis (3) Addition of sodium carbonate in water retards photosynthetic rate in vallisneria (4) Phloem is the principal pathway for translocation of solutes

Last Answer : Ans. ((c))

Description : What is the need for slack bus

Last Answer : The slack bus is needed to account for transmission line losses. In a power system the total power generated will be equal to sum of power consumed by loads and losses. In a power system only ... for losses. Since the losses are unknown the real and reactive power are not specified for slack bus.

Description : What is the need for slack bus?

Last Answer : The slack bus is needed to account for transmission line losses. In a power system, the total power generated will be equal to sum of power consumed by loads and losses. In a power system, ... power are not specified for slack bus. They are estimated through the solution of line flow equations.

Description : What is swing bus(slack bus/reference bus)?

Last Answer : A bus is called swing bus when the magnitude and phase of bus voltage are specified for it. The swing bus is the reference bus for load flow solution and it is required for accounting for the line losses. Usually one of the generator bus is selected as the swing bus.

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : ‘The law of limiting factors’ was proposed by (a) Leibig (b) Hatch and Slack (c) Blackman (d) Arnon.

Last Answer : (c) Blackman

Description : Which pair is wrong? (a) C3-maize (b) C4-kranz anatomy (c) Calvin cycle-PGA (d) Hatch and Slack cycle - OAA

Last Answer : (a) C3-maize

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : Slack time refers to (A) An activity (B) An event (C) Both event and activity (D) None of the above

Last Answer : (B) An event

Description : In simplex method, if there is tie between a decision variable and a slack (or surplus) variable, ______ should be selected a. Slack variable b. Surplus variable c. Decision variable d. None of the above

Last Answer : c. Decision variable

Description : In simplex method, we add _______ variables in the case of “=” a. Slack variable b. Surplus variable c. Artificial variable d. None of the above

Last Answer : c. Artificial variable

Description : . In simplex algorithm, which method is used to deal with the situation where an infeasible starting basic solution is given? a. Slack variable b. Simplex method c. Big M Method d. None of the above

Last Answer : b. Simplex method

Description : 66. Which method is an iterative procedure for solving LPP in a finite number of steps? a. Simplex algorithm b. Slack variable c. Big M method d. Simplex method

Last Answer : d. Simplex method

Description : Slack time is associated with (a) A real activity (b) An event (c) Both event and real activity (d) Dummy activity

Last Answer : (b) An event

Description : In Gauss Seidel method the following factors are influenced for operation a) Acceleration factor b) Selection of slack buss c) Both d) None

Last Answer : Ans: Selection of slack buss*

Description : What is the need for slack bus in power flow analysis.

Last Answer : The slack/swing bus is needed to account for transmission line losses. In a power system the total power generated will be equal to sum of power consumed by loads and losses. In a power ... power are not specified for slack bus. They are estimated through the solution of load flow equations.

Description : In a load flow problem solved by newton-Raphson method with polar coordinates, the size of the Jactobian is 100 × 100. If there are 20 PV buses in addition to PQ buses and a slack bus, the total number of buses in the system is_____

Last Answer : 61

Description : In power system, the maximum number of buses are a) Generator buses b) Load buses c) Slack buses d) P-V buses

Last Answer : b) Load buses

Description : All activities lying on critical path have slack time equal to (A) 0 (B) 1 (C) 2 (D) None of above

Last Answer : (A) 0

Description : Tension on the slack side in chain drive is A)more than on tight side. B)less than on tight side. C)zero. D)equal to tight

Last Answer : C)zero

Description : Tension on slack side in case of chain drive a) Lesser than on tight side b) Greater than on tight side c) Zero d) Equal to that on tight side

Last Answer : c) Zero

Description : Renewal of slack rivets should be taken up in steel girder bridges: a) All rivets which are hand loose or which have lost 50% of their head by corrosion. b) All hammer loose rivets where corrosion has set ... . c) In end stiffeners when the percentage of hammer loose rivets is >30% d) All the above*

Last Answer : d) All the above*

Description : Controllable variables are also called.................................. a. Slack variables b. Surplus variables c. Artificial variable d. Decision variables

Last Answer : d. Decision variables

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : ........................variables are fictitious and cannot have any physical meaning. a. Slack variables b. Surplus variables c. Artificial variables d. Decision variables

Last Answer : c. Artificial variables

Description : In simplex method, ........................ should be selected when there is tie between slack/surplus variable and decision variable. a. Slack variable b. Decision variable c. Surplus variable d. None of these

Last Answer : b. Decision variable

Description : In simplex method, we add .......................... in the case of constraints with sign “=” a. Surplus variable b. Artificial variable c. Slack variable d. None of these

Last Answer : b. Artificial variable

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 