Wing walls and return walls are provided to retain  
a) earth on approaches
b) ballast
c) track on approaches
d) none

1 Answer

Answer :

a) earth on approaches

Related questions

Description : In case of LWR track, full ballast section as specified in LWR Manual should be provided up to ……….. from the bridge abutment. a) 200 m b) 50 m c) 300 m d) 100 m*

Last Answer : d) 100 m

Description : Cracks in return walls/ wing walls or Slight tilting/ bulging of abutments are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Sub structure of a bridge does not include a) Abutment b) Girder/Slab* c) Piers d) Wing and Return walls

Last Answer : b) Girder/Slab*

Description : Stop boards on either side of approaches of all unmanned level crossings shall be provided at -------------from the centre line of nearest track. a) 3meters b) 5 meters* c) 6 meters d) 10 meters

Last Answer : b) 5 meters*

Description : For laying a Railway track the prepared surface ready to receive the ballast is called a) Sub ballast b) Formation* c) Blanket d) Cushion

Last Answer : b) Formation*

Description : Track structure for CC+8 t+ 2 t loaded trains is:- (a) 52 Kg 90 UTS;PSC 1540 sleepers/ Km.; 250 mm ballast. (b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.* (c) 52 Kg 72 UTS;PSC 1540 sleepers/ Km.; 300 mm ballast. (d) 90 R;PSC 1340 sleepers/ Km.; 250 mm ballast.

Last Answer : b) 60 Kg 90 UTS;PSC 1660 sleepers/ Km.; 300 mm ballast.*

Description : Speed breaker has to be provided on road approaches of level crossing at maximum feasible distance within Railway boundary but not exceeding a) 10 meters b) 15 meters c) 20 meters* d) 200 meters

Last Answer : c) 20 meters*

Description : Which of the following ingredients of Brick earth enables the brick to retain its shape a) Alumina b) Silica* c) Iron d) Magnesia

Last Answer : b) Silica*

Description : Stone generally preferred for railway ballast is a) Sandstone b) Dolomite c) Marble d) Basalt or trap granite*

Last Answer : d) Basalt or trap granite*

Description : Cross slope of the formation to have good drainage of Ballast section is a) 1 in 40* b) 1 in 50 c) 1 in 30 d) 1 in 20

Last Answer : a) 1 in 40*

Description : Minimum depth of ballast cushion below the bottom of sleeper at the rail seat on BG group A route should be :- (a) 350 mm. (b) 250 mm. (c) 300 mm.* (d) 325 mm.

Last Answer : (c) 300 mm.*

Description : What is the full form of PQRS used for Track renewal works. a. Plasser quick Relaying system* b. Please quick return services c. Poor Quality renewal system d. None of above

Last Answer : a. Plasser quick Relaying system*

Description : In case of a curved track on electrified, double line, BG section a) Duty hut cannot be provided for a level crossing. b) Duty hut should be on the inside of the curve. c) Duty hut should be on the outside of the curve.* d) Duty hut can be provided on any side of the curve.

Last Answer : c) Duty hut should be on the outside of the curve.*

Description : In LWR track on BG a) Level crossing should be separated by providing SEJs b) Level crossing cannot be provided in LWR. c) Level crossing should not fall within the breathing length of LWR* d) Level crossing should be laid with rail free fastenings.

Last Answer : c) Level crossing should not fall within the breathing length of LWR*

Description : On Broad gauge tracks whistle indicator shall be provided at a distance of ---------- from level crossing along the track a) 400 meters b) 600 meters* c) 350 meters d) 500 meters

Last Answer : b) 600 meters*

Description : On an unmanned level crossing stop board should be provided at a distance of --------- from the centre of nearest track a) 5 meters * b) 6 meters c) 3 meters d) 7.5 meters

Last Answer : a) 5 meters

Description : Bearings are provided in bridges to transfer the load to a) Super structure b) Track c) Embankment d) Sub structure*

Last Answer : d) Sub structure*

Description : Parapet walls along hill roads, are provided (A) To retain the back filling (B) To prevent the hill from sliding (C) To prevent the wheels of the vehicle from coming on the retaining wall (D) None of these

Last Answer : Answer: Option C

Description : .Minimum wing rail clearance opposing nose of crossing on Fan shaped turnout a. 45 mm b. 40 mm c. 41 mm* d. 44 mm

Last Answer : c. 41 mm*

Description : There should not be any combination joint on level crossing proper and its approaches up to a) 15 meters b) 30 meters c) 40 meters d) 50 meters

Last Answer : d) 50 meters

Description : The advantages of electrometric bearings are a) Permits movement of the structure in all directions b) Serves as a shock absorber due to anti-vibration properties of elestomeric c) better dispersion of longitudinal forces to the approaches d) All of the above*

Last Answer : d) All of the above*

Description : How does ballast-less track provide safe travel?

Last Answer : ANSWER I: Ballast is a prime component of the track that acts as a vibrant medium to transmit from the rail surface the weight of the train down to the formation, the wells set on ... cost involved in laying a ballast-less track is more initially but it requires less recurring maintenance cost.

Description : An artificial stone made from pieces of white marble, white cement and other coloring agents, generally used for floor and facing walls is known as a) Topaz b) Marble c) Terrazzo* d) Gneiss

Last Answer : c) Terrazzo*

Description : In arch bridges, Cracks/ lean/ bulge in parapet walls, Bulging or separation of spandrel from arch barrel, are the signs of distressed bridge under a) Group I b) Group II* c) Both of the above d) None of the above

Last Answer : b) Group II*

Description : Bentonite is used in pile driving -- a) to facilitate pile driving b) to enable proper pile concreting c) to stabilize the bore hole walls* d) None of the above

Last Answer : c) to stabilize the bore hole walls*

Description : How many detonators are planted during protection of track for welding site ? (i) One (ii) Two (iii) Three* (iv) None of the above

Last Answer : iii) Three*

Description : Weather protection of track is required during block for execution of AT Welding? (i) Yes.* (ii) No (iii) As decided by site supervisor (iv) As per site condition

Last Answer : (i) Yes.*

Description : hat is the minimum distance between AT Weld and other joint exist in track? (i) 2 Mt. (ii) 3 Mt. (iii) 4 Mt.* (iv) 4.5 Mt.

Last Answer : (iii) 4 Mt.*

Description : 1. Which of the statements with regard to formation is correct (1) One of the Functions of the formation is to facilitate drainage (2) Width of bank for double railway line is 12.155 meters (3) Width of cutting for double railway track is 11. ... a) 2, 3, 5 b) 3, 4, 5* c) 2, 3, 4 d) 2, 4, 5

Last Answer : b) 3, 4, 5*

Description : Minimum distance of duty hut from centre line of nearest track on BG is a) 2 meters b) 3 meters c) 4 meters d) 6 meters*

Last Answer : d) 6 meters*

Description : Minimum distance of gate post from centre line of nearest track on BG is a) 2 meters b) 3 meters* c) 4 meters d) 5 meters

Last Answer : b) 3 meters*

Description : TVU is abbreviated for a) Track vulnerable unit b) Train vehicle unit * c) Total vehicle unit d) Traffic variation unit

Last Answer : b) Train vehicle unit *

Description : RBG loading caters for maaaaximum axle load of…….tones for locomotive with trailing loadof…… tonnes/metre of track with maximum axle load of…….tonnes for wagons a)22.9,7.67,25 b)22.5,7.67,22.9* c)25,7.67,22.9, d)None of above

Last Answer : b)22.5,7.67,22.9*

Description : Length of guard rails to be bent so as to be brought together at the middle of the track.(L2) a) 3200 mm b) 4875 mm* c) 3655 mm d) None of the above

Last Answer : b) 4875 mm*

Description : Facia boards of platform shelters shall have a minimum horizontal clearance of ……. from C.L. of track at a minimum height of 4.61m above RL. a) 2360 mm b) 3660 mm c) 3000 mm d) 1600 mm*

Last Answer : d) 1600 mm*

Description : The horizontal clearance between guard rail and running rail in BG track is a) 25 mm b) 250 ± 50 mm* c) 75 mm d) 200 ± 50 mm

Last Answer : b) 250 ± 50 mm*

Description : Angle of crossing of a bridge is the angle between a) C.L. of water course/road to C.L. of track* b) C.L. of water course to C.L. of pier c) C.L. of water course to normal (perpendicular) of C.L. of track d) C.L. of abutment to C.L. of pier

Last Answer : a) C.L. of water course/road to C.L. of track*

Description : Skew of a bridge is the angle between a) C.L. of water course to C.L. of track b) C.L. of water course to C.L. of pier c) C.L. of water course/road to normal (perpendicular) of C.L. of track* d) C.L. of abutment to C.L. of pier

Last Answer : c) C.L. of water course/road to normal (perpendicular) of C.L. of track*

Description : The minimum track centres in B.G. double line is (a) 4500 mm (b) 4750 mm (c) 5000 mm (d) 5300 mm*

Last Answer : (d) 5300 mm*

Description : The minimum horizontal distances form centre of track to face of passenger platform coping for B.G. is ……. Mm (A) 1650 MM. (B) 1670 MM* (C)1676 MM (D) 1685 MM

Last Answer : (B) 1670 MM*

Description : The minimum centre to centre distance of a B.G. track in mid-section is ……….. mm (a) 4200 (b) 4265* (C) 4350 (d) 4000

Last Answer : (b) 4265*

Description : For taking track measurement at accident site stations shall be marked at …….. Apart. (a) 1 m (b) 2m (c) 3m* (d) 5m

Last Answer : (c) 3m*

Description : Deep screening of entire track must be done at least:- (a) Once in a quarter. (b) Once in a year. (c) Once in 5 years. (d) Once in 10 years.*

Last Answer : (d) Once in 10 years.*

Description : Minimum speed restriction to be imposed for Track renewal is:- (a) Stop dead & 10 Kmph (b) 10 Kmph (c) 15 Kmph (d) 20 Kmph*

Last Answer : (d) 20 Kmph*

Description : Permissible creep in track is m. 50 mm n. 100 mm o. 125 mm p. 150 mm.*

Last Answer : p. 150 mm.*

Description : Lowest level of staff/supervisor competent for packing or renewal of single isolated sleeper not requiring lifting or slewing of track in LWR/CWR. a. PWI b. Keyman c. Gangmate* d. PWS

Last Answer : c. Gangmate*

Description : Lowest level of staff/supervisor competent for Lifting/Lowering of track in LWR/CWR. a. Keyman. b. Gangmate. c. PWI. d. PWS.*

Last Answer : d. PWS.*

Description : What is the full form of TGI a. Track Geometry Index* b. Track general Index c. Track gravity Index d. None of above

Last Answer : a. Track Geometry Index*

Description : Frequency of TTM tamping on PSC sleepers track a. 2 years or 100 GMT which ever is earlier* b. 2 years or 150 GMT which ever is earlier c. 1.5 years or 200 GMT which ever is earlier d. 2 years or 175 GMT which ever is earlier

Last Answer : a. 2 years or 100 GMT which ever is earlier*

Description : what is the value of long chord for measuring unevenness in track recording a. 3.6 meter b. 9.6 meter* c. 7.2 meter d. 4.8 mete

Last Answer : b. 9.6 meter*