Pick up the incorrect statement from the following:
(A) The various functions under each activity, are shown by one bar on Bar Charts
(B) Bar chart establishes the interdependency of one event on another
(C) Only approximate percentage of the completed work is reported
(D) None of these

1 Answer

Answer :

(B) Bar chart establishes the interdependency of one event on another

Related questions

Description : Various activities of a project, are shown on bar charts by (A) Vertical lines (B) Horizontal lines (C) Dots (D) Crosses

Last Answer : (B) Horizontal lines

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Select the incorrect statement. (A) Start float and finish float are always equal. (B) Total float can be either start float or finish float. (C) Start float and finish float need not be equal. (D) Start float and finish float are the differences between activity times and not event times.

Last Answer : (C) Start float and finish float need not be equal.

Description : Pick up the incorrect statement from the following: (A) An activity of a project is denoted by an arrow on the net work (B) The tail of the arrow indicates the start of the activity (C) The head of the arrow indicates the end of the activity (D) The arrows are drawn to scale from left to right

Last Answer : (D) The arrows are drawn to scale from left to right

Description : Pick up the PERT event from the following: (A) Digging of foundation started (B) Digging of foundation completed (C) Laying of concrete started (D) All the above

Last Answer : (D) All the above

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : Which of the following is an INCORRECT statement about the parasympathetic system? a) It increases digestive action. b) It is the fight or flight system. c) slows breathing rate d) establishes resting state

Last Answer : ANSWER: B -- IT IS THE FIGHT OR FLIGHT SYSTEM.

Description : Pick up the incorrect statement from the following. For performing compressive strength test of cement (A) Cement and standard sand mortar are used in the ratio of 1 : 3 (B) Water is added at the ... cm 10 cm is used (D) The prepared moulds are kept in a atmosphere of 50% relative humidity

Last Answer : Answer: Option A

Description : Pick up the incorrect statement from the following: (A) While measuring a distance with a tape of length 100.005 m, the distance to be increasing by 0.005 m for each tape length (B) An increase in ... ) A 100 m tape of cross section 10 mm 0.25 mm stretches about 10 mm under 5 kg pull

Last Answer : (B) An increase in temperature causes a tape to increase in length and the measured distance is too large

Description : Bar charts are suitable for (A) Minor works (B) Major works (C) Large projects (D) All the Above

Last Answer : (A) Minor works

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : Which of the following types of Organizational Charts can be BEST used to track project costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : Which of the following types of Organizational Charts can be BEST used to track project  costs : A. Hierarchical-type Organizational Chart B. Organizational Breakdown Structure C. Resource Breakdown Structure D. Responsibility Assignment Matrix

Last Answer : C. Resource Breakdown Structure

Description : What are the various types of charts? Explain each. -Technology

Last Answer : The various types of charts in Excel are given below:Line Chart:Data that is arranged in columns or rows on a worksheet can be plotted in a line chart. Line charts can display continuous data ... data that represents profit over time can be plotted in an area chart to emphasize the total profit.

Description : Which of the following is not a PERT event? (A) Site investigation started (B) Sessional work completed (C) Bus starts from Jaipur (D) Class is being attended

Last Answer : (D) Class is being attended

Description : Pick up the incorrect statement from the following: (A) The rate of flow of water through a unit cross-sectional area under a unit hydraulic gradient, is called coefficient of permeability (B) ... aquifers, is governed by the Darcy's law (D) The term 'transmissibility' was introduced by Meinzer

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following: (A) Horizontal D.P.C. is provided at plinth level in internal walls (B) D.P.C. is provided under door and verandah openings (C) Vertical D.P.C. is not provided in internal walls (D) Cement concrete is a rigid damp-proofing material

Last Answer : Answer: Option B

Description : Pick up the incorrect statement from the following: (A) Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil (B) The lead is calculated for each block of the ... a distance upto 500 m (D) The unit of lead is 1 km where the lead exceeds 2 km

Last Answer : (D) The unit of lead is 1 km where the lead exceeds 2 km

Description : Pick up the incorrect statement from the following: (A) The bottom and top ends of slump mould are parallel to each other (B) The axis of the mould is perpendicular to the end faces (C) The ... clean and free from set cement (D) The mould is in the form of a frustum of hexagonal pyramid

Last Answer : Answer: Option D

Description : Pick up the incorrect statement from the following: (A) In Flemish bond, headers and stretchers are laid alternately in the same course (B) In Flemish bond every header in each course lies ... laid in every course (D) In English bond, headers and stretchers are laid in alternate courses

Last Answer : Answer: Option C

Description : Pick up the incorrect statement from the following a. The activity which consumes maximum time, is called a node b. The activity is the time consuming part of a project c. The beginning ... of a job, are called events d. Logically and sequentially connected activities and events form a network

Last Answer : a. The activity which consumes maximum time, is called a node

Description : When to use percentage component bar chart?

Last Answer : Ans: We use percentage component bar chart when we want to make the comparison in components holding the difference of total constants.

Description : When we use simple bar chart, multiple bar chart, component bar chart & percentage component bar chart?

Last Answer : Ans: A simple bar chart is used when there is only one variable classified on spatial, qualitative or temporal, in more than one interrelated variables we sue multiple bar chart, simple component ... is used when we want to make a comparison in components holding the difference of total constants.

Description : Draw the flow chart of Risk Management-Activity and explain various Software risks.

Last Answer : Ans RISK is a problem that could cause some loss or threatens the success of the project, but which has not happened yet. Typical Software Risks:- 1. Dependencies: -Many ... Inadequate application domain experience. New technologies. Ineffective, poorly documented, or neglected processes.

Description : Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. ... and 4 are correct (C) 2, 3 and 4 are correct (D) 1, 2 and 4 are correct

Last Answer : (B) 1 and 4 are correct

Description : For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is (A) 1 (B) 2 (C) 3 (D) 4

Last Answer : (A) 1

Description : Pick up the incorrect statement regarding a master trap from the following: (A) It is provided in between the lower end of the house drain and the street sewer (B) It is provided a cleaning eye at the ... fitted at the top of the inlet pipe (D) The water seal is less than that of ordinary traps

Last Answer : (D) The water seal is less than that of ordinary traps

Description : Pick up the incorrect statement from the following. While performing preliminary test on concrete (A) Proportions of the material and water should be the same as to be used at the work site (B) ... in air-tight containers (D) Concrete ingredients should be kept at a temperature of 37° 2°C

Last Answer : Answer: Option D

Description : The component labeled 'CR1' in the circuit shown in the illustration __________________. EL-0085 A. varies its anode/cathode polarity depending on 'RL' current B. rectifies the varying voltage from the ... reactance to smooth ripple D. establishes a constant reference voltage for the base of 'Q1'

Last Answer : Answer: D

Description : While scheduling a project by C.P.M. (A) A project is divided into various activities (B) Required time for each activity is established (C) Net work is drawn by connecting the activities and the events (D) All the above

Last Answer : (D) All the above

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : Which of the following is a weakness of bar chart? (A) Interdependencies of activities (B) Project progress (C) Uncertainties (D) All of the above

Last Answer : (D) All of the above

Description : Time and progress chart of a construction, is also known as (A) Bar chart (B) Gantt chart (C) Modified Mile stone chart (D) All the above

Last Answer : (D) All the above

Description : A bar chart is commonly used because (a) It is simple to draw and easy to understand (b) It indicates at a glance the overall progress of the project (c) It shows critical ... critical activities (d) It incorporates uncertainties for delay in estimation of time required for completion of activities.

Last Answer : (a) It is simple to draw and easy to understand

Description : What is approximate total population of the five cities on the chart in 1760 How much did that total population increase by 1881?

Last Answer : jhbi.lk...................gggggggggggggggggguuuuuuuuuuuuuuuuuuu

Description : What is approximate total population of the five cities on the chart in 1760 How much did that total population increase by 1881?

Last Answer : jhbi.lk...................gggggggggggggggggguuuuuuuuuuuuuuuuuuu

Description : Select the incorrect statement from the following [ A ] Reinforcing bars in a column should not be less than 12 mm in diameter [ B ] The number of longitudinal bars in a circular column should not ... The minimum percentage of longitudinal steel in columns should be 0.8% [ D ] None of the above

Last Answer : [ B ] The number of longitudinal bars in a circular column should not exceed four

Description : Pick up the incorrect statement from the following: (A) Water disinfected with ozone is free from any odour (B) Ozone removes bacterias as well as colour and odour (C) Ozonized water becomes tasteless (D) None of these

Last Answer : (C) Ozonized water becomes tasteless

Description : Pick up the incorrect statement from the following: (A) Porosity of clay sand soil is 45% (B) Porosity of pure sand is 35% (C) Porosity of sand stone is up to 15% (D) None of these

Last Answer : (D) None of these

Description : Pick up the incorrect statement from the following regarding fire hydrants (A) Fire hydrants are fitted in water mains at 100 m to 150 m apart at fire (B) The minimum water pressure hydrants, is kept 1.5 kg/ ... to 1.5 kg/cm2 is made available for 4 to 5 hours for constant use (D) None of these

Last Answer : (D) None of these

Description : Pick up the incorrect statement from the following: (A) Iron salts produce heavy flocks and hence remove more suspended matter (B) Iron salts remove hydrogen sulphides (C) Iron salts can be used over a limited range of pH values (D) Iron salts impart corrosiveness to water

Last Answer : (C) Iron salts can be used over a limited range of pH values

Description : Pick up the incorrect statement from the following. The source of surface water is from  (A) Streams and rivers  (B) Storage reservoirs  (C) Springs  (D) Ponds and lakes 

Last Answer : (C) Springs 

Description : Pick up the incorrect statement from the following:  (A) The flow in strainer type wells is radial  (B) The flow in cavity type wells in spherical  (C) In strainer type wells, area of flow ... pipe  (D) In cavity type wells, area of flow depends upon the size of the cavity 

Last Answer : (C) In strainer type wells, area of flow depends upon the length of the strainer pipe 

Description : Pick up the incorrect statement from the following:  (A) Free surface ground water is subjected to atmospheric pressure  (B) Water table surface rises and falls with seasons  (C) ... directly proportional to the rate of drawl of water  (D) Level of water table remains stationary 

Last Answer : (D) Level of water table remains stationary