Select the incorrect statement.
(A) Start float and finish float are always equal.
(B) Total float can be either start float or finish float.
(C) Start float and finish float need not be equal.
(D) Start float and finish float are the differences between activity times and not event times.

1 Answer

Answer :

(C) Start float and finish float need not be equal.

Related questions

Description : Pick up the incorrect statement from the following: (A) The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity (B) The ... start time and earliest start time of an activity, is called total float (D) None of thes

Last Answer : (D) None of these

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Total float for any activity is defined as the difference between (A) Its latest finish time and earliest start time for its successor activity (B) Its latest start time and earliest start ... earliest finish time (D) Its earliest finish time and earliest start time for its successor activity

Last Answer : (B) Its latest start time and earliest start time

Description : Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. (A) A is correct but R is not correct (B) R is correct but A is not correct (C) Both A and R is correct (D) Both A and R is incorrect

Last Answer : (A) A is correct but R is not correct

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : Total float in a planning network is (a) Late start time – Early start time (b) Early start time – Late start time (c) Late start time – Late finish time (d) Late finish time – Early finish time

Last Answer : Ans: (a & d)

Description : Free float for any activity is defined as the difference between A. its earliest finish time and earliest start time for its successor activity B. its latest start time and earliest start time ... its successor activity D. its earliest finish time and latest start time for its successor activity

Last Answer : A. its earliest finish time and earliest start time for its successor activity

Description : Free float is mainly used to (A) Identify the activities which can be delayed without affecting the total float of preceding activity (B) Identify the activities, which can be delayed ... which can be delayed without affecting the total float of either the preceding or succeeding activities

Last Answer : (B) Identify the activities, which can be delayed without affecting the total float of succeeding activity

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as (A) Event (B) Free float (C) Dummy (D) Constrain

Last Answer : (C) Dummy

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description :  During a new project planning process to sequence activities, the project  manager, Nate, decides to use the precedence diagraming method to show the  identified activity dependencies. Which of the following logical ... -finish c. Finish-to-finish d. Start-to-start e. All of these answers

Last Answer : b. Start-to-finish

Description : Whenever an activity has zero total float, then (A) Free float of the activity must be zero but independent float need not be zero (B) Independent float must be zero but free float need not be ... and independent float both must be zero (D) Free float and independent float both need not be zero

Last Answer : (C) Free float and independent float both must be zero

Description : Which of the following statements is correct regarding float' for anactivity? a) Time between its earliest start time and earliest finish time b) Time between its latest start time and latest ... start time and earliest finish time d) Time between earliest finish time and latest finish time

Last Answer : d) Time between earliest finish time and latest finish time

Description : The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as (A) Total float (B) Free float (C) Interfering float (D) Independent float

Last Answer : (D) Independent float

Description : The project schedule is used to determine all of the following except which one?  A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

Last Answer : A. Cost estimates

Description : Pick up the incorrect statement from the following: (A) An activity of a project is denoted by an arrow on the net work (B) The tail of the arrow indicates the start of the activity (C) The head of the arrow indicates the end of the activity (D) The arrows are drawn to scale from left to right

Last Answer : (D) The arrows are drawn to scale from left to right

Description : Fill in the blank. Risk represents the likelihood that an event will happen during  the life of the project that will negatively affect the ________________ of project goals. Select one: a. scope creep b. achievement c. float d. rough order of magnitude e. slack

Last Answer : b. achievement

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : The difference between the time avail-to do a job and the time required to do the job, is known as (A) Event (B) Float (C) Duration (D) Constraint

Last Answer : (B) Float

Description : Which of the following statement is incorrect? a. An agency may be terminated by death of either party. b. An agency may be terminated by express agreement. c. An agency agreement can always be terminated by a principal. d. Mental incapability of an agent will terminate the agency relationship.

Last Answer : c. An agency agreement can always be terminated by a principal.

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : Different cultures sometimes vary in their attitudes to time. In cultures where people follow event time: A. It is important to turn up for meetings on time. B. Much time is devoted to having a chat ... running over time, people do not wait for it to finish before moving on to the next event.

Last Answer : Much time is devoted to having a chat over a coffee during the working day.

Description : Different cultures sometimes vary in their attitudes to time. In cultures where people follow event time: A. It is important to turn up for meetings on time. B. Much time is devoted to having a chat ... running over time, people do not wait for it to finish before moving on to the next event.

Last Answer : Much time is devoted to having a chat over a coffee during the working day.

Description : In case of a Rotameter, the density of the float material is __________ that of the liquid it replaces. (A) More than (B) Less than (C) Equal to (D) Either (A) or (B)

Last Answer : (A) More than

Description : .......................... is the duration by which an activity can be delayed without delaying the project. a. Slack b. Total float c. Both a and b d. None of these

Last Answer : b. Total float

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.

Description : The independent float affects only (A) Preceding activities (B) Succeeding activities (C) The particular activity involved (D) None of the above

Last Answer : (C) The particular activity involved

Description : As a new project manager, Karen was worried about a statement from  her client: your project deliverable is in low quality with low grade .  According to PMBOK, how can you help Karen ... quality with high grade is always desirable to your client. e. High quality always  represents high grade.

Last Answer : c. Low quality represents a true problem, but low grade might not be the case.

Description : Pick up the incorrect statement from the following: (A) The activity is the time consuming part of a project (B) The beginning and end of a job, are called events (C) The activity ... maximum time, is called a node (D) Logically and sequentially connected activities and events form a network

Last Answer : (C) The activity which consumes maximum time, is called a node

Description : A man standing at the finish line is recording the time of a race competition by means of a stop watch. He must start the watch when (a) He hears the sound of the starting gun (b) He sees flash ... gun (c) He sees first man leaving the starting line (d) He either sees the flash or hears the sound

Last Answer : Ans:(b)

Description : Select the incorrect statement. Effective angle of shearing resistance (A) Increases as the size of particles increases (B) Increases as the soil gradation improves (C) Is limited to a maximum value of 45° (D) Is rarely more than 30° for fine grained soil

Last Answer : (C) Is limited to a maximum value of 45°

Description : Select the incorrect statement. (A) Bearing capacity of a soil depends upon the amount and direction of load (B) Bearing capacity of a soil depends on the type of soil (C) Bearing capacity of a ... upon shape and size of footing (D) Bearing capacity of a soil is independent of rate of loading

Last Answer : Answer: Option A

Description : Select the incorrect statement. (A) Effective cohesion of a soil can never have a negative value. (B) Effective angle of internal friction for coarse grained soils is rarely below 30°. (C ... (D) Effective angle of internal friction is a complicated function of mineralogy and clay size content.

Last Answer : Answer: Option A

Description : Select the incorrect statement. (A) In a direct shear box test, the plane of shear failure is predetermined (B) Better control is achieved on the drainage of the soil in a triaxial compression ... compression test is uniform (D) Unconfined compression test can be carried out on all types of soils

Last Answer : Answer: Option D

Description : Select the incorrect statement. (A) The progress of work in low level method of mound construction is very slow (B) Barge method of mound construction is economical (C) In low level method ... (D) In staging method of mound construction, the work is not interrupted even during stormy weather

Last Answer : (B) Barge method of mound construction is economical

Description : Select the incorrect statement (A) Lean mixes bleed more as compared to rich ones. (B) Bleeding can be minimized by adding pozzolana finer aggregate (C) Bleeding can be increased by addition 'of calcium chloride (D) None of the above

Last Answer : Answer: Option D

Description : Select the incorrect statement (A) The loss of pre-stress is more in pre-tensioning system than in post-tensioning system. (B) Pre-tensioning system has greater certainty about its durability. (C ... or bridges, post-tensioning system is cheaper than pre-tensioning system (D) None of the above

Last Answer : Answer: Option D

Description : Select the incorrect statement from the following [ A ] Reinforcing bars in a column should not be less than 12 mm in diameter [ B ] The number of longitudinal bars in a circular column should not ... The minimum percentage of longitudinal steel in columns should be 0.8% [ D ] None of the above

Last Answer : [ B ] The number of longitudinal bars in a circular column should not exceed four

Description : Select the incorrect statement from the following In eccentrically loaded columns, [ A ] The tensile strength of concrete is ignored [ B ] Design stress - strain curve for steel in compression is the ... different points in the section will be same [ D ] Plane section remain plane even after bending

Last Answer : [ C ] The strain at different points in the section will be same

Description : Select incorrect statement from the following. In the Virtual work method, it is generally assumed that [ A ] Elastic deformations in the slab are negligible [ B ] Plastic deformations in the slab are negligible [ C ] Plastic deformations takes place at the yield lines [ D ] Both (a) and (b)

Last Answer : [ B ] Plastic deformations in the slab are negligible

Description : Select incorrect statement from the following [ A ] With passage of time, the strength of cement decreases [ B ] With passage of time, the strength of cement increases [ C ] After a period ... cement reduces to 50% [ D ] The concrete made with storage deteriorated cement; gains strength with time.

Last Answer : [ B ] With passage of time, the strength of cement increases

Description : Select the incorrect statement [ A ] R.C.C has better fire resistance than steel [ B ] R.C.C. structure is economical than steel structure [ C ] Strength of concrete decreases as age increases [ D ] R.C.C can be used for under water and marine structures

Last Answer : [ C ] Strength of concrete decreases as age increases

Description : . A schedule activity may begin 10 days before the predecessor activity finishes. This is an example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : A schedule activity may begin 10 days before the predecessor activity finishes. This is an  example of: A. Finish-to-Start B. Start-to-Finish C. Start-to-Start D. Finish-to-Finish

Last Answer : A. Finish-to-Start

Description : At the completion of the forward and backward passes, the slack for an activity is given by the a. Difference between early start and early finish b. Difference between early start and ... c. Difference between latest start and early finish d. Difference between latest start and latest finish

Last Answer : c. Difference between latest start and early finish