A bar chart is commonly used because
(a) It is simple to draw and easy to understand
(b) It indicates at a glance the overall progress of the project
(c) It shows critical and non-critical activities
(d) It incorporates uncertainties for delay in estimation of time required for completion of activities.

1 Answer

Answer :

(a) It is simple to draw and easy to understand

Related questions

Description : Which of the following is a weakness of bar chart? (A) Interdependencies of activities (B) Project progress (C) Uncertainties (D) All of the above

Last Answer : (D) All of the above

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. ... and 4 are correct (C) 2, 3 and 4 are correct (D) 1, 2 and 4 are correct

Last Answer : (B) 1 and 4 are correct

Description : Time and progress chart of a construction, is also known as (A) Bar chart (B) Gantt chart (C) Modified Mile stone chart (D) All the above

Last Answer : (D) All the above

Description : Every entrepreneur should draw an _______ for his project to ensure the timely completion of all activities involved in setting up an enterprise. A. cost structure B. implementation plan C. market structure D. production structure

Last Answer : B. implementation plan

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : Updating may result in (A) Change of critical path (B) Decrease of project completion time (C) Increase of project completion time (D) All of the above

Last Answer : (D) All of the above

Description : A horizontal bar chart that shows project tasks against a calendar is called (A) milestone (B) goal (C) Gantt chart (D) PERT chart

Last Answer : (C) Gantt chart

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : Which one of the following is the most appropriate management control technique for timely completion of a project ? (A) Organisation chart (B) Management by Objectives (C) PERT (D) Span of control

Last Answer : Answer: PERT

Description : Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to ... and 4 (B) 3, 4 and 5 (C) 1, 3 and 4 (D) 1, 2 and 5

Last Answer : (A) 1, 2 and 4

Description : The main purpose of business ethics is to understand A. Ethical uncertainties B. Principles and concepts C. Application of practices D. All of the above

Last Answer : D. All of the above

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : . An important aim of a post-project review is to: a. validate overall progress to date against the budget and schedule. b. capture learning and document it for future usage. c. ... of all permanent documentation, signed by the sponsor. d. establish that project benefits have been identified.

Last Answer : b. capture learning and document it for future usage.

Description : An important aim of a post-project review is to:  a. validate overall progress to date against the budget and schedule.  b. capture learning and document it for future usage.  c. ... of all permanent documentation, signed by the sponsor.  d. establish that project benefits have been identified

Last Answer : b. capture learning and document it for future usage.

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : The budgeted cost for all the activities in a project with the help of Earned Value  Method is  A. Actual Cost  B. Budget at completion  C. Budget for completion  D. Estimate at completion

Last Answer : D. Estimate at completion

Description : For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is (A) 1 (B) 2 (C) 3 (D) 4

Last Answer : (A) 1

Description : This activity is undertaken once the development activities start? A. Project Planning B. Project Monitoring and Control C. Project size estimation D. Project cost estimation

Last Answer : B. Project Monitoring and Control

Description : FP-based estimation techniques require problem decomposition based on (A) information domain values (B) project schedule (C) software functions (D) process activities

Last Answer : (C) software functions

Description : Petri is working for Nokia in Finland. He has completed 10 months of his 12-month project, budgeted at $800,000. His earned value analysis shows that variance at  completion is $75,000. What is the estimate at completion value ... : a. 725,000 b. -725,000 c. -$875,000 d. $875,000 e. $800,000

Last Answer : d. $875,000

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : gnition delay is defined as the A)time between start of fuel injection and ignition of fuel B)time between end of fuel injection and ignition of fuel C)time between start of ignition and tdc D)time between completion of ignition and bdc

Last Answer : A)time between start of fuel injection and ignition of fuel

Description : Cost controls can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Last Answer : 4. The process of gathering, accumulating, analyzing, reporting, and managing the costs on  an on-going basis.

Description : Cost budgeting can be best described by which of the following? 1. The process of developing the future trends along with the assessment of probabilities,  uncertainties, and inflation that  could ... of gathering, accumulating, analyzing, reporting, and managing the costs on an on- going basis

Last Answer : 3. The process of establishing budgets, standards, and a monitoring system by which the  investment cost of the project can be measured and managed

Description : )The critical element in a project's communication system is the: 1. Progress report * 2. Project directive  3. Project manager  4. Customer

Last Answer : 3. Project manager

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Which of the following is true about management meetings? Select one: a. They are short meetings to develop a common understanding of what the short-term  priorities are for the project. ... , tracking progress of existing plans, and  making adjustments to plans in response to new information.

Last Answer : e. They are oriented toward developing plans, tracking progress of existing plans, and  making adjustments to plans in response to new information.

Description : Which one from the following is highly associated activity of project planning? (A) Keep track of the project progress. (B) Compare actual and planned progress and costs (C) Identify the activities, milestones and deliverables produced by a project (D) Both (B) and (C)

Last Answer : (C) Identify the activities, milestones and deliverables produced by a project

Description : Various activities of a project, are shown on bar charts by (A) Vertical lines (B) Horizontal lines (C) Dots (D) Crosses

Last Answer : (B) Horizontal lines

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : When we use simple bar chart, multiple bar chart, component bar chart & percentage component bar chart?

Last Answer : Ans: A simple bar chart is used when there is only one variable classified on spatial, qualitative or temporal, in more than one interrelated variables we sue multiple bar chart, simple component ... is used when we want to make a comparison in components holding the difference of total constants.

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : Creating a work plan requires three steps: identify the tasks that need to be  accomplished, estimate the time that it will take to complete the tasks, and record the task  completion time in a Gantt Chart.

Last Answer : Ans: False

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gant

Description : This/These Management Guru/s, formulated a bar chart that measures planned and completed work along each stage of project A. Frederick Taylor B. Henry Gantt C. Frank and Lillian Gilbreth D. Henri Fayol

Last Answer : Henry Gantt

Description : A critical ratio scheduling (A) Determines the status of each activity (B) Adjusts automatically changes in activity progress (C) Is a dynamic system (D) None of these

Last Answer : (D) None of these

Description : Fill in the blank. A __ represents the sequence of the activities needed to  complete the project. Select one: a. work break down structure b. scope of work c. project logic diagram d. run chart e. step change

Last Answer : c. project logic diagram

Description : If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is (A) 4 days (B) 6 days (C) 10 days (D) 16 day

Last Answer : (D) 16 days

Description : If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be (A) 2.3% and 84.1% (B) 97.7% and 84.1% (C) 97.7 % and 15.9% (D) 15.9% and 97.7%

Last Answer : (A) 2.3% and 84.1%