Total float in a planning network is
(a) Late start time – Early start time (b) Early start time – Late start time
(c) Late start time – Late finish time (d) Late finish time – Early finish time
(a) Late start time – Early start time (b) Early start time – Late start time
(c) Late start time – Late finish time (d) Late finish time – Early finish time