A CPM family includes
(A) CPA (Critical Path Analysis)
(B) CPP (Critical Path Plotted)
(C) MCE (Minimum Cost Expenditure)
(D) All the above

1 Answer

Answer :

(D) All the above

Related questions

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : Which of the following is an independent commodity exchange based in Mumbai? A. MGEX B. MCE C. MDEX D. MCX E. MEX

Last Answer : D. MCX Explanation: Multi Commodity Exchange of India Ltd (MCX) (BSE: 534091) is an independent commodity exchange based in India. It was established in 2003 and is based in Mumbai.

Description : ....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis

Last Answer : d. Network analysis

Description : _____________ is used to accomplish the project economically in the minimum available time with limited resources A. Project Scheduling. B. Network Analysis. C. Budget Analysis. D. Critical Planning.

Last Answer : A. Project Scheduling.

Description : The attest function: a. Is an essential part of every engagement performed by a CPA. b. Includes the preparation of a written report of the CPA's conclusion. c. Requires a complete review ... under examination. d. Requires a review of a sample of transactions during the period under examination.

Last Answer : Includes the preparation of a written report of the CPA's conclusion

Description : If the area calculated form the plan plotted with measurements by an erroneous chain, accurate  area of the plan is  (A) Measured area (Length of chain used/Nominal chain length)  (B) Measured ... of chain used)²  (D) Measured area (Length of chain used/Nominal chain length)² 

Last Answer : (D) Measured area × (Length of chain used/Nominal chain length)² 

Description : The area of any irregular figure of the plotted map is measured with (A) Pentagraph (B) Sextant (C) Clinometer (D) Planimeter

Last Answer : (D) Planimeter

Description : The distances AC and BC are measured from two fixed points A and B whose distance AB is known. The point C is plotted by intersection. This method is generally adopted in (A) Chain surveying (B) Traverse method of surveys (C) Triangulation (D) None of these

Last Answer : (A) Chain surveying

Description : While surveying a plot of land by plane tabling, the field observations (A) And plotting proceed simultaneously (B) And plotting do not proceed simultaneously (C) And recorded in field books to be plotted later (D) All the above

Last Answer : (A) And plotting proceed simultaneously

Description : Angles to a given pivot station observed from a number of traverse stations when plotted, the lines to the pivot station intersect at a common point (A) Angular measurements are correct and ... plotting of traverse (D) Angular and linear measurements and also plotting of the traverse are correct

Last Answer : (D) Angular and linear measurements and also plotting of the traverse are correct

Description : Pick up the correct statement from the following: (A) Hydrograph is a plot of discharge and time (B) In hydrographs, time is plotted on X-axis (C) The maximum flow in the river due to rainfall, is called peak flow (D) All the above

Last Answer : Answer: Option D

Description : In open channels, the specific energy is the (A) Total energy per unit discharge (B) Total energy measured with respect to the datum passing through the bottom of the channel (C) Total energy measured above the horizontal datum (D) Kinetic energy plotted above the free surface of water

Last Answer : Answer: Option B

Description : CPM is (A) Synthesising in concepts (B) Is built of activities oriented programme (C) Is based on time estimate (D) All the above

Last Answer : (D) All the above

Description : Completion of an activity on CPM network diagram, is generally known (A) Event (B) Node (C) Connector (D) All the above

Last Answer : (D) All the above

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : In a plane-table survey, the process of determining the plotted position of a station occupied by the plane-table by means of sights taken towards known points, the locations of which have already been plotted, is known as (a) Radiation (b) Resection (c) Intersection (d) Traversing

Last Answer : (b) Resection

Description : Traffic engineering only includes (A) Planning of regulatory measures (B) Design and application of control devices (C) Analysis of traffic characteristics (D) All the above

Last Answer : Answer: Option D

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : The process of incorporating changes and rescheduling or replanning is called (A) Resource levelling (B) Resource smoothening (C) Updating (D) Critical path scheduling

Last Answer : (C) Updating

Description : Critical path (A) Is always longest (B) Is always shortest (C) May be longest (D) May be shortest

Last Answer : (A) Is always longest

Description : Pick up the correct statement from the following: (A) Programme Evaluation and Review Technique, is event oriented (B) Programme Evaluation and Review Technique is not event oriented (C) Critical Path Method is event oriented (D) Critical Path method is event oriented

Last Answer : (A) Programme Evaluation and Review Technique, is event oriented

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : Updating may result in (A) Change of critical path (B) Decrease of project completion time (C) Increase of project completion time (D) All of the above

Last Answer : (D) All of the above

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : An engagement in which a CPA firm arranges for a critical review of its practices by another CPA firm. a. Attestation engagement b. Peer review engagement c. Quality control engagement d. Quality assurance engagemen

Last Answer : Peer review engagement

Description : Which term is CPM refer to ? 1. Cost per hundred 2. Cost per Million 3. Cost per Thousand 4. Cost per Clic

Last Answer : Cost per Million

Description : The Philippine Accountancy Act of 2004 provides that all Working papers made during an audit shall be the property of the auditor. These working papers shall include the following, except: a. Working ... of documents furnished to the auditor. d. Any report submitted by the auditor to his client.

Last Answer : Any report submitted by the auditor to his client.

Description : What is the biggest difference between CPA and CLV analysis A. CPA is more appropriate for short term, tactical optimization B. CLV is truly customer-centric C. CLV encompasses online and offline customer touchpoints and uses back-office data D. All of the above

Last Answer : D. All of the above

Description : An approach to location anal on analysis that include includes both qualitative and quantitative considerations is a. locational cost-volume b. factor rating c. transportation model d. assignment assignment method e. make or buy analysis

Last Answer : b. factor rating

Description : The primary difference between a full -cost approach and a direct -cost approach is that when the direct -cost approach is used, the cost analysis A)does not include nontraceable ... includes nontraceable common costs. C)does not include traceable common costs. D)includes traceable common costs.

Last Answer : A)does not include nontraceable common costs

Description : Which of the following is displayed as an S curve?  A. Gantt B. Cost baseline C. Critical path D. Schedule baseline

Last Answer : B. Cost baseline

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : 15. The depth of water in a channel corresponding to the minimum specific energy is known as critical depth. A) Agree B) Disagree

Last Answer : A

Description : The discharge in an open channel corresponding to critical depth is (A) Zero (B) Minimum (C) Maximum (D) None of these

Last Answer : Answer: Option C

Description : Consider the following statements in respect of critical flow in a wide rectangular channel: 1. The specific energy is minimum for a given discharge. 2. The discharge is maximum for a given specific energy 3. The specific force is minimum for a ... b) 1, 2, 3 & 4 (c) 1, 2 & 4 only (d) 2, 3 & 4 only

Last Answer : (b) 1, 2, 3 & 4

Description : Which of the following is not a function of the Board of Accountancy as specified in the Philippine Accountancy Act of 2004? a. To investigate violations of the Accountancy Law ... determine and prescribe minimum requirements leading to the admission of candidates to the CPA licensure examination

Last Answer : To create and direct accrediting agencies that are entrusted the functions of reviewing higher educational institutions' policies and practices leading to accreditation/reaccreditation of BSA program.

Description : A CPA who is engaged to prepare an income tax return has a duty to prepare it in such a manner that the tax is: a. The legal minimum. b. Computed in conformity with generally accepted ... principles. c. Supported by the client's audited financial statements. d. Not subject to change upon audit

Last Answer : The legal minimum

Description : A CPA should not submit unaudited financial statements of a non-public entity to a client or others unless, as a minimum, the CPA complies with the provisions applicable to a. Audit engagements. b. Review engagements. c. Assurance engagements. d. Compilation engagements.

Last Answer : Compilation engagements.

Description : Pick up the correct statement from the following: (A) The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value (B ... for incurring an expenditure on the work, is called administrative approval (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The cost of square rooms is less (B) The expenditure on the foundation and roof for the double storeyed building is nearly half of that ... cost of construction of a house may be minimised by restricting the height floors (D) All the above

Last Answer : Answer: Option D

Description : Path coverage includes A. Statement coverage B. Condition coverage C. Decision coverage D. None of the above

Last Answer : C. Decision coverage

Description : Have you ever plotted your life on a timeline to look for a pattern in your life?

Last Answer : Yes I attempt to improve my situation, and then fail ;then move in with another parent, and then attempt to improve my life , and fail, and then move back with another parent, Then go to a group home or university, or homeless shelter. ect. and repeat.