In the time-cost optimisation, using CPM method for network analysis, the crashing of the
activities along the critical path is done starting with the activity having
(A) Longest duration
(B) Highest cost slope
(C) Least cost slope
(D) Shortest duration

1 Answer

Answer :

(C) Least cost slope

Related questions

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : Project crashing is the method for -------------  A. Shortening the project duration by reducing the time of one or more critical  activities  B.Adding resources at critical points  C.Doing technical analysis of the finished work for review  D.Adding duration to each activity

Last Answer : A. Shortening the project duration by reducing the time of one or more critical  activities

Description : For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time  is 13. Duration of activity is 6. Which of the following statements is true?  A.The early start is 6 B. ... of the activity is 13  C.The slack of this activity is 13  D.The activity is on the critical path

Last Answer : D.The activity is on the critical path

Description : A CPM family includes (A) CPA (Critical Path Analysis) (B) CPP (Critical Path Plotted) (C) MCE (Minimum Cost Expenditure) (D) All the above

Last Answer : (D) All the above

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : The critical path  A. Is a path that operates from the starting node to the end node  B. Is a mixture of all paths.  C.Is the longest path  D.Is the shortest path

Last Answer : C.Is the longest path

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : The basic difference between PERT and CPM is that a. PERT deals with events and CPM with activities b. Critical Path is determined in PERT only c. Costs are considered on CPM only d. Guessed times are used in PERT and evaluated times in CPM.

Last Answer : a. PERT deals with events and CPM with activities

Description : Critical path (A) Is always longest (B) Is always shortest (C) May be longest (D) May be shortest

Last Answer : (A) Is always longest

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : Floats for critical activities will be always _____ a. One b. Zero c. Highest d. Same as duration of the activity

Last Answer : b. Zero

Description : CPM stands for____________. A. Continuous Path Method. B. Clear Path Method. C. Critical Path Method. D. Critical Probabilistic Method.

Last Answer : C. Critical Path Method.

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by using only one time factor per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : Economic saving of time results by crashing (A) Cheapest critical activity (B) Cheapest noncritical activity (C) Costliest critical activity (D) Costliest noncritical activity

Last Answer : (A) Cheapest critical activity

Description : What would be the critical path if the duration of activity C increased to 10? A. ABCF B. ABCEF C. ABGHIF D. ABGHIF & ABDEF

Last Answer : A. ABCF

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : Which one of the following is the objective in crashing? (a) Reduction in duration (b) Reduction in resources (c) Reduction in cost (d) Reduction in project size

Last Answer : (c) Reduction in cost

Description : Completion of an activity on CPM network diagram, is generally known (A) Event (B) Node (C) Connector (D) All the above

Last Answer : (D) All the above

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : An Equinox is when: (1) Day and night are of equal length (2) Day is of the shortest duration during the year (3) Day is of the longest duration in the year (4) Day when maximum rainfall of the year occurs

Last Answer : (1) Day and night are of equal length Explanation: An equinox is an astronomical event in which the plane of Earth's equator passes through the center of the Sun, which occurs twice each year, ... . They are not exactly equal, however, due to the angular size of the sun and atmospheric refraction.

Description : What is meant by “Equinox”? A. The longest day B. The shortest day C. The sun-month long day D. Equal duration of day and night (Answer)

Last Answer : D. Equal duration of day and night (Answer)

Description : An Equinox is when: (1) Day and night are of equal length (2) Day is of the shortest duration during the year (3) Day is of the longest duration in the year (4) Day when maximum rainfall of the year occurs

Last Answer : Day and night are of equal length

Description : What is the longest and yet the shortest thing in the world; the swiftest and yet the slowest; the most divisible and the most extended; the least valued and the most regretted; without which ... every thing, however small, and yet gives life and spirits to every object, however great? -Riddles

Last Answer : Time.

Description : The second longest path in the network diagram is called a. Alternate b. Feasible c. Sub-critical d. Critical

Last Answer : c. Sub-critical

Description : Feasibility study determines -----------------  A.Whether the project is possible with resources  B.Comparing the project with world class manufacturing norms C.Calculate the cost crashing each unit  D.Add duration to each unit

Last Answer : A.Whether the project is possible with resources

Description : ....................... deals with the concepts such as critical path, float, events, etc. a. Game theory b. Decision theory c. Queuing theory d. Network analysis

Last Answer : d. Network analysis

Description : What is a visual representation of a project’s planned activities against a calendar called? a. A Gantt chart. b. A critical path network. c. A product flow diagram. d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : What is a visual representation of a project’s planned activities against a calendar called?  a. A Gantt chart.  b. A critical path network.  c. A product flow diagram.  d. A Pareto chart.

Last Answer : a. A Gantt chart.

Description : ......................... is activity oriented network diagram. a. CPM b. PERT c. Histogram d. Ogive

Last Answer : a. CPM

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as (A) Duration (B) Total float (C) Free float (D) Interfering float

Last Answer : (C) Free float

Description : CPM is (A) Synthesising in concepts (B) Is built of activities oriented programme (C) Is based on time estimate (D) All the above

Last Answer : (D) All the above

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : In multicast routing, eachinvolvedrouter needs toconstructa ________ path tree for each group. A) average B) longest C) shortest D) none of the above

Last Answer : shortest

Description : In unicast routing,each router in the domain has a table thatdefines a______ path tree to possible destinations. A) average B) longest C) shortest D) none of the above

Last Answer : shortest

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : . A shortest time span in the life cycle of a crop when weeding results in highest eco nomic returns a). Economic threshold b). Critical period c). Competitive threshold d). None of these

Last Answer : b). Critical period

Description : In precision theodolite traverse if included angles are read twice and the mean reading accepted using both verniers having a least count of 30". Assuming the instrument to be in perfect adjustment, linear measurements correct to 6 mm per ... legs) (A) 50" n (B) 30" n (C) 60" n (D) None of these

Last Answer : (A) 50" n

Description : Canada has the __________ coastline in the world. (A) shortest (B) longest (C) the most indented (D) the least indented

Last Answer : (B) longest 

Description : Which of the following routing algorithms can be used for network layer design? a. shortest path algorithm b. distance vector routing c. link state routing d. all of the mentioned

Last Answer : d. all of the mentioned

Description : Additional time which a non-critical activity can consume without increasing the project duration is called _____________. A. Total Float. B. Free Float C. Independent Float. D. Dependant Float

Last Answer : A. Total Float.