Updating may result in
(A) Change of critical path
(B) Decrease of project completion time
(C) Increase of project completion time
(D) All of the above

1 Answer

Answer :

(D) All of the above

Related questions

Description : For completion of a project, the critical path of the network represents (A) Minimum time (B) Maximum time (C) Maximum cost (D) Minimum cost

Last Answer : (A) Minimum time

Description : The process of incorporating changes and rescheduling or replanning is called (A) Resource levelling (B) Resource smoothening (C) Updating (D) Critical path scheduling

Last Answer : (C) Updating

Description : Fill in the blank. Crashing refers to when the task duration’s are __ along the  critical path to meet the project completion date. Select one: a. scope creep b. floated c. slack d. compressed e. expedited

Last Answer : d. compressed

Description : A bar chart is commonly used because (a) It is simple to draw and easy to understand (b) It indicates at a glance the overall progress of the project (c) It shows critical ... critical activities (d) It incorporates uncertainties for delay in estimation of time required for completion of activities.

Last Answer : (a) It is simple to draw and easy to understand

Description : An activity whose start or end cannot be delay without affecting total project completion time is called ______ activity a. Dummy b. Non-critical c. Critical d. Important

Last Answer : c. Critical

Description : Crash project duration is obtained by summing the (A) Normal durations for all the activities (B) Crash durations for all activities (C) Crash durations for all the activities along the ... along the critical path obtained by taking into account the crash duration for all the activities.

Last Answer : (D) Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities.

Description : While assessing your project processes, you have identified some  uncontrolled process variations. Which of the following would be the  appropriate chart you may use for this purpose? Select one: a. Pareto diagram b. PERT chart c. Control chart d. HR personnel chart e. Critical path

Last Answer : c. Control chart

Description : Complete the following statement. The method of incorporating change into  project planning and execution processes is called the: Select one: a. project logic diagram. b. change management process. c. milestone schedule d. critical path e. rough order of magnitude

Last Answer : b. change management process.

Description : Critical path (A) Is always longest (B) Is always shortest (C) May be longest (D) May be shortest

Last Answer : (A) Is always longest

Description : Which section is basically a sequence of instruction with a clear indication of beginning and end for updating shared variables. a. Racing section b. Critical section c. d. Both None of thes

Last Answer : . Critical sectio

Description : If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is (A) 4 days (B) 6 days (C) 10 days (D) 16 day

Last Answer : (D) 16 days

Description : If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be (A) 2.3% and 84.1% (B) 97.7% and 84.1% (C) 97.7 % and 15.9% (D) 15.9% and 97.7%

Last Answer : (A) 2.3% and 84.1%

Description : After the celebration of the successful milestone completion, a project manager  will often do which of the following? Select one: a. Continue to increase the intensity of the project to achieve the ... milestone. e. Stretch the goals of the project team, making them more tough and rigorous.

Last Answer : c. Allow the team to reflect on finding new ways of approaching the project work.

Description : The critical exist gradient of seepage water in soils, increases with (A) An increase in specific gravity (B) A decrease in specific gravity (C) A decrease in void ratio (D) Both (a) and (c)

Last Answer : Answer: Option D

Description : Which of the following establishes key dates throughout the life of a project that  must be met for the project to finish on time? Select one: a. Critical path b. Ballpark estimate c. Pert diagram d. Slack chart e. Milestone schedule

Last Answer : e. Milestone schedule

Description : In time-cost optimization of a project, crashing is done. (A) On all the activities (B) On all the activities lying on the critical path (C) Only on activities lying on the ... critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Last Answer : D

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description :  Once the logic of a network is laid out, the project manager will conduct a forward  pass and a backward pass through the network. This will provide information regarding  ______ and will identify ... C. Resource shortages, high risk activities D. The high risk activities, non-critical path

Last Answer : A. The total duration of the project, critical path

Description :  In a project schedule, the sequence of activities which cannot be delayed during the  course of the project without extending the project end date is referred to as the:  A. Action plan B. Critical path C. Schedule baseline D. Slack line

Last Answer : B. Critical path

Description : A critical path network diagram does NOT: A. Help determine the amount of float B. Identify the particularly important activities C. Calculate earned value D. Calculate the duration of the whole project

Last Answer : C. Calculate earned value

Description : A project activity has several components as indicated below; S.  No. Activity Preceded by Duration (in  Weeks) 1 A - 8 2 B A 6 3 C A 12 4 D B 4 5 E D 5 6 F B 12 7 G E& F ... H 5 10 J I & G 6 d. Prepare a PERT chart, estimate the duration of the project and identify the  critical path.

Last Answer : PERT Diagram based on Activity on Arrow  .  E  D 5 G B 5 9 J, 6 A 6 F,12 I ,5 8 c 12 H 8 OR  PERT Diagram based on Activity on Node …………………….6 marks a. Critical Path: A-B-F-G-J …………………….1 mark  b. Estimated Project Duration: 41 weeks

Description : ............................ is the sequence of activities which determines the total project duration. a. Critical path b. Network c. Non-critical activities d. None of these

Last Answer : a. Critical path

Description : To crash a schedule you should: 1. Increase the time allowed on those tasks that have float.  2. Try to increase expenditures of time only those tasks that are behind schedule.  3. Replace those ... to par with the busy.  4. Increase work efforts on those tasks that are on the critical path.

Last Answer : 4. Increase work efforts on those tasks that are on the critical path.

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration

Last Answer : (C) Least cost slope

Description : The first method invented for planning projects, was (A) Bar chart method (B) Milestone chart (C) Critical path method (CPM) (D) Programme Evaluation and Review Technique (PERT)

Last Answer : (A) Bar chart method

Description : A CPM family includes (A) CPA (Critical Path Analysis) (B) CPP (Critical Path Plotted) (C) MCE (Minimum Cost Expenditure) (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Programme Evaluation and Review Technique, is event oriented (B) Programme Evaluation and Review Technique is not event oriented (C) Critical Path Method is event oriented (D) Critical Path method is event oriented

Last Answer : (A) Programme Evaluation and Review Technique, is event oriented

Description : Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than ... (B) 2 and 3 are correct (C) 1 and 4 are correct (D) 1 and 2 are correct

Last Answer : (B) 2 and 3 are correct

Description : Critical path method (A) Is an improvement upon bar chart method (B) Provides a realistic approach to daily problems (C) Avoids delays which are very common in bar charts (D) All the above

Last Answer : (D) All the above

Description : Critical path moves along the activities having total float as (a) Positive (b) Negative ( c) Zero (d) Unity

Last Answer : ( c) Zero

Description : The resistance of most conducting materials will change as a result of temperature change. The resistance of copper will _____________. A. increase as temperature decreases B. decrease as temperature decreases C. remain the same between 20°F and 110°F D. remain the same between 68°F and 230°F

Last Answer : Answer: B

Description : Recycling back of outlet stream to the reactor from an ideal CSTR carrying out a first order liquid phase reaction will result in __________ in conversion. (A) Decrease (B) Increase (C) No change (D) Either (A) or (B), depends on the type of reaction

Last Answer : (C) No change

Description : In case of calcination of limestone, CaCO3 CaO + CO2 , the addition of more of CaO will result in __________ in the concentration of CO2 . (A) No change (B) Increase (C) Decrease (D) Unpredictable from the data

Last Answer : (A) No change

Description : A decrease in price will result in an increase in total revenue if (a) Percentage change in quantity demanded in greater than the percentage change in price (b) Percentage change in quantity demanded ... (c) Percentage change in quantity demanded is equal to the percentage change in price (d) None

Last Answer : (a) Percentage change in quantity demanded in greater than the percentage change in price 

Description : If therapy with multiple drugs causes induction of drug metabolism in your asthma patient, it will (a) Result in increased smooth endoplasmic reticulum (b) Result in increased rough endoplasmic reticulum ... soluble cytoplasmic fraction (d) Require 3-4 months to reach completion (e) Be irreversible

Last Answer : Ans: A

Description : Who orchestrate the completion of the project by inducting the right people at the  right time to address the right issue and make the right decisions?  A.Project Coordinator  B.Project Manager  C.Operations Manager  D.Strategic Business Unit Head

Last Answer : B.Project Manager

Description : Which stage of project management life cycle requires the maximum time of  completion  A.Conceptualization  B.Planning  C.Execution  D.Estimation

Last Answer : C.Execution

Description : . When estimating project time schedules using industry standards, the estimated  project completion time for a systems project would be _____ person-months if the actual  planning phase were completed in 6 person-months.  a. 30  b. 40  c. 17.14  d. 9  e. 50

Last Answer : b. 40

Description : What is a project phase? A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)  B. A singular activity that completes a ... that has very similar parts D. A consistent period of time that is used throughout a project

Last Answer : A. A collection of logically related project activities that culminate in the completion  of one or more deliverables (Ans.)

Description : A prerequisite of effective time management is:  1. Knowing the dictated project completion date  2. Having the most advanced software package for project planning, scheduling and control  3. ... and the  person responsible for each of them  4. Having a well staffed scheduling department

Last Answer : 1. Knowing the dictated project completion date

Description : ........................... is the latest time by which an activity can be finished without delaying the completion of the project. a. LST b. LFT c. EFT d. EST

Last Answer : b. LFT

Description : ..................... is the duration by which an activity can be delayed without delaying the completion of the project. a. Earliest Start Time b. Earliest Finish Time c. Latest Start Time d. Latest Finish Time

Last Answer : c. Latest Start Time

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : Which one of the following does project change control primarily seek to ensure? a. All variance to the project scope is evaluated. b. No reduction in the perceived quality of the project outcome. ... project do not increase. d. Any decrease in the scoped deliverable of the project is rejected.

Last Answer : a. All variance to the project scope is evaluated.

Description : Which one of the following does project change control primarily seek to ensure?  a. All variance to the project scope is evaluated.  b. No reduction in the perceived quality of the project outcome ... project do not increase.  d. Any decrease in the scoped deliverable of the project is rejected

Last Answer : a. All variance to the project scope is evaluated.

Description : Spurious tuples may occur due to i. Bad normalization ii. Theta joins iii. Updating tables from join a) i& ii b) ii & iii c) i& iii d) ii & iii

Last Answer : a) i& ii b) ii & iii

Description : The one guideline to be followed while designing the database is A) A database design may be ambiguous. B) Unrelated data should be in the same table so that updating the data will be easy. C) It should avoid/reduce the redundancy. D) An entity should not have attributes.

Last Answer : C) It should avoid/reduce the redundancy.

Description : The critical angle of a glass slab increases with (a) Increase in the refractive index of glass (b) Decrease in the refractive index of glass (c) Increase in temperature (d) None of these