The three time estimates for the activities of the network shown in the given figure are shown
above their arrows. The earliest expected time for the event 4, is
(A) 19
(B) 14
(C) 24
(D) None of these

1 Answer

Answer :

(A) 19

Related questions

Description : For the network shown in the given figure, the expected time for the activity (A) 1-2 is 4 (B) 2-3 is 7 (C) 3-4 is 8 (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) Forward pass is used for calculating earliest expected time (B) Backward pass is used for calculating the latest occurrence time (C) Maximum value of earliest ... time is used if there is more than one value of any event (D) All the above

Last Answer : (D) All the above

Description : Pick up the correct statement from the following: (A) The difference of latest occurrence time and earliest expected time, is called slack (B) The activities connecting the events having zero slack, lie on the critical path (C) The critical path consumes the maximum time (D) All the above

Last Answer : (D) All the above

Description : You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the ... the weighted average or expected value? A. 54 B. 66 C. 60 D. 30

Last Answer : C. 60

Description : For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is (A) 8 days (B) 9 days (C) 10 days (D) 15 days

Last Answer : (B) 9 days

Description : In PERT analysis, the time estimates of activities and probability of their occurrence follow (A) Normal distribution curve (B) Poisson's distribution curve (C) Beta distribution curve (D) None of the above

Last Answer : (C) Beta distribution curve

Description : In the given figure, the network of a project represents (A) Activity of an excavation of a footing (B) Activity of an excavation which starts at event No. 1 and ends at even No. 2 (C) Activity of excavation which takes 8 units of time (D) None of thes

Last Answer : (C) Activity of excavation which takes 8 units of time

Description : Pick up the correct statement from the following: (A) Earliest expected time is denoted by TE (B) Latest occurrence time is denoted by TL (C) Contractual obligation time is denoted by Ts (D) All the above

Last Answer : (D) All the above

Description : In sea urchin DNA, which is double stranded, 17% of the bases were shown to be cytosine. The percentages of the other three bases expected to be present in this DNA are (a) G 17%, A 33%, T 33% (b) G 8.5%, A 50%, T 24.5% (c) G 34%, A 24.5%, T 24.5% (d) G 17%, A 16.5%, T 32.5%.

Last Answer : (a) G 17%, A 33%, T 33%

Description : Select the correct statement. (A) Activity arrows in a CPM network are drawn to scale (B) The tail of an arrow represents the finish of an activity (C) Arrow bead represents the start of an activity (D) None of the above

Last Answer : (D) None of the above

Description : Select the incorrect statement. (A) Earliest start of an activity is the early event time of the node it leaves. (B) Latest finish of an activity is the late event time of the node it enters. (C) Latest start of an activity is its latest finish minus its duration. (D) None of the above

Last Answer : (D) None of the above

Description : Pick up the correct statement from the following: (A) The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float' (B) ... C) The difference between total float and free float, is called interfering float (D) All the above

Last Answer : (D) All the above

Description : 1. The ODI Player of the Year 2012' Award was given by ICC to which India cricketer? 2. Who has created world record in the men's 100 metres sprint event at 2008 Olympic Games? 3. Which ... reach Sri Lanka from Nagercoil ? 20. Which was the last governor of Bengal appointed by the Mughal emperor?

Last Answer : Answer : 1. Virat Kohli 2. Usain Bolt 3. Mitochondria 4. California and Texas 5. Sheikh Moinuddin Chisti 6. 5 years 7. 5 8. Rules and regulations 9. White Nile and Blue Nile 10. Aurangzeb ... 16. Methane 17. Ishwar Chandra Vidyasagar 18. Remains constant 19. Gulf of Mannar 20. Murshid Quli Khan

Description : What network model enables engineer managers to schedule, monitor and control large and complex projects by employing three time estimates per activity a. Forecasting b. Program evaluation review technique c. Critical path method d. simulation

Last Answer : b. Program evaluation review technique

Description : 1. Where did India first win the Olympic Hockey gold? 2. FIFA World Cup 2018 would be held in which country? 3. Which vitamin is synthesised in the body by intestinal bacteria? 4. ... distance from the sun (Apehelion)? 20. Which structure was constructed by Emperor Akbar in Fatehpur Sikri?

Last Answer : Answer : 1. Amsterdam 2. Russia 3. Vitamin K 4. Brahmaputra valley 5. Lucknow Pact6. Kurnool 7. Colloidal silver bromite 8. Agricultural credit 9. Andhra Pradesh and Gujarat 10. Chera 11. Paris 12. Blue and ... Rupyaka 16. Completely inelastic 17. London 18. 4 : 2 : 1 19. July 4th 20. Panch Mahal

Description : A triode amplifier similar to the one shown in figure 1-19 has an Ebb -conditions, 1.5 milliamperes of current conducts through the tube. What w

Last Answer : +275 volts

Description : What is Work Breakdown Structure (WBD) and how does it affect the work estimates of tasks/activities?

Last Answer : Work breakdown structure defines the work activities required for the project and the sub activities of each of the work requirement. The breakdown goes down to levels where all the work required ... and effort estimates can be accurate when everything about the work and dependencies are known.

Description : In network diagram, events are commonly represented by ......................... a. Arrows b. Nodes c. Triangles d. None of these

Last Answer : b. Nodes

Description : Does anyone know the best way to figure out traffic estimates from San Francisco to Tahoe (North Lake/Alpine Meadows) and Ski forecast in an easy way?

Last Answer : You can try this site.

Description : 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50'. What number is missing? -Riddles

Last Answer : 22

Description : Which article of the constitution prohibits the employment of children bellow 14 years of age in any factory ,mine or other hazardous job- a) Art-14 b) Art-19 c) Art-24 d) Art-29

Last Answer : c) Art-24

Description : By selling 45 lemons for Rs 40, a man loses 20%.How many should he sell for Rs 24 to gain 20% in the transaction? a) 19 b) 22 c) 20 d) 18 e) 14

Last Answer : Selling price = Rs. 40 Loss = 20% Therefore, cost price = 40×100 /(100 - 20) = Rs. 50 Therefore, cost price of each lemon = Rs. 50/45 Now, selling price = Rs. 24 Profit = 20% Cost price = 24×100/120 = Rs. 20 Number of lemons for Rs. 20 = 20/(50/45) = 900/50 = 18 Answer: d)

Description : In a PERT network, slack time is _____. (a) The end point that represents the completion of a major activity (b) The time or resources required to progress from one event to another ( ... without delaying the whole Project (d) The longest or most time-consuming sequence of events and activities 

Last Answer : (c) The amount of time an individual activity can be delayed without delaying the whole Project 

Description : A manufacture undertakes to supply 2000 pieces of a particular component at Rs.25 per piece. According to his estimates, even if 5% fail to pass the quality tests, then he will make a profit of 25%. However as it turned out, ... A. Rs 12,000 B. Rs 13,000 C. Rs 14,000 D. Rs 15,000 E. None f these

Last Answer : Answer - B. Rs 13,000 Explanation: 5% of 2000=100 so 2000-100=1900 so,if he sells 1900 he will get 25% profit cost per piece rs 25 so 25x 1900 don't solve here if 125% . ... /125=38000=CP if 50% rejected,only 1000 pieces sold so 1000 25=25000=SP loss=cp-sp= 38000-25000=13000

Description : The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage ... 15) chains (B) (6 + 12) chains (C) (6 + 18) chains (D) None of these

Last Answer : (B) (6 + 12) chains

Description : The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is (A) Rs. 400 (B) Rs. 425 (C) Rs. 450 (D) Rs. 500

Last Answer : (C) Rs. 450

Description : The value of 'A' of Indian type W.C. shown in the given figure is: (A) 25 cm (B) 30 cm (C) 40 cm (D) 45 cm

Last Answer : (B) 30 cm

Description : The value of 'C' of Indian type W.C. shown in the given figure is: (A) 400 mm (B) 450 mm (C) 500 mm (D) 550 mm

Last Answer : (C) 500 mm

Description : The value of 'B' of Indian type W.C. shown in the given figure is: (A) 45 cm (B) 50 cm (C) 30 cm (D) 25 cm

Last Answer : (A) 45 cm

Description : The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is (A) b - rd)²/(r - s) (B) b - rd)²/(r + s) (C) ½ × (b + rd)²/(r - s) (D) b - rd)²/(s - r)

Last Answer : (A) b - rd)²/(r - s)

Description : The area of the cross-section of a road fully in banking shown in the given figure, is (A) [sb² + r² (2bd + sd)²]/(r² - s²) (B) [sb² + r² (2bd + sd)²]/(r² - s5 ) (C) [sb² + r² (2bd + sd)²]/(r - s) (D) None of these

Last Answer : (A) [sb² + r² (2bd + sd)²]/(r² - s²)

Description : EST stands for ____________. A. Earliest Start Time. B. Event Start Time. C. Effective Start Time. D. Essential Start Time.

Last Answer : A. Earliest Start Time.

Description : Independent float is the amount of time by which:  A. Start of the activity can be delayed without affecting the EST of subsequent  activity  B. reduces the float of subsequent ... without affecting EST  D. completion of an activity can be delayed beyond earliest possible finishing time

Last Answer : A. Start of the activity can be delayed without affecting the EST of subsequent  activity

Description : With reference to Indian freedom struggle which event occurred earliest? -Do You Know?

Last Answer : answer:

Description : With reference to Indian freedom struggle which event occurred earliest?

Last Answer : Lucknow Pact

Description : Pick up the correct statement from the following: (A) With both handles in his left hand, the chain man throws out the chain with his right hand and the second chain man assists him to free it from ... the two chain men meet and the ten arrows are handed over to the leader (D) All the above

Last Answer : (D) All the above

Description : Pick up the incorrect statement from the following: (A) An activity of a project is denoted by an arrow on the net work (B) The tail of the arrow indicates the start of the activity (C) The head of the arrow indicates the end of the activity (D) The arrows are drawn to scale from left to right

Last Answer : (D) The arrows are drawn to scale from left to right

Description : The equivalent resistance resistance between A and B of network shown in figure is

Last Answer : The equivalent resistance resistance between A and B of network shown in figure is A. `(3R)/(4)` B. `(4R)/(3)` C. 6 R D. 2 R

Description : The effective resistance between points A and C for the network shown figure is

Last Answer : The effective resistance between points A and C for the network shown figure is A. `(2)/(3)R` B. `(3)/(2)R` C. 2R D. `(1)/(2R)`

Description : In the network of resistors shown in the adjoining figure, the equivalent resistance between A and B is

Last Answer : In the network of resistors shown in the adjoining figure, the equivalent resistance between A and B is A. 54 ... `Omega` C. 36 `Omega` D. 9 `Omega`

Description : Consider the following statements regarding the network shown in the figure. The eqivalent resistance of the network between points A and B is indepen

Last Answer : Consider the following statements regarding the network shown in the figure. The eqivalent resistance of the network between ... D. (1), (2) and (3)

Description : Consider the star network shown in figure. The resistance between terminals A and B with C open is 6 ohms, between terminals B and C withAopen is 11 ohms and between terminals C andAwith B open is 9 ohms. Then RA, RB, RC respectively is 

Last Answer : Consider the star network shown in figure. The resistance between terminals A and B with C open is 6 ohms, between terminals B and C withAopen is 11 ohms and between terminals C andAwith B open is 9 ohms. Then RA, RB, RC respectively is  2, 4,7

Description : If my d.o.b. is 12 14 1956 when is the earliest I can retire at full retirement age?

Last Answer : That depends on where you live and what the retirement age is inthat country

Description : Pick up the incorrect statement from the following: (A) The various functions under each activity, are shown by one bar on Bar Charts (B) Bar chart establishes the interdependency of one event on another (C) Only approximate percentage of the completed work is reported (D) None of these

Last Answer : (B) Bar chart establishes the interdependency of one event on another

Description : The pressure at a point 4 m below the free surface of water is (A) 19.24 kPa (B) 29.24 kPa (C) 39.24 kPa (D) 49.24 kPa

Last Answer : Answer: Option C

Description : If the velocity of moving vehicles on a road is 24 km/per hour, stopping distance is 19 metres and average length of vehicles is 6 metres, the basic capacity of lane, is (A) 500 vehicles per hour (B) 700 vehicles per hour (C) 1000 vehicles per hour (D) 1250 vehicles per hour

Last Answer : Answer: Option C

Description : What does the recycling symbol with the three arrows represent? -SST 10th

Last Answer : The recycling symbol with the three arrows represents the three steps in the recycling process, (i) Collection and processing of recyclable materials, (ii) Manufacturing of those materials into new products, and (iii) Products Sold to consumers which then starts the process over again.

Description : The three boxes in this diagram represent the three major biosynthetic pathways in aerobic respiration. Arrows represent net reactants or products. PathwayA Pathway B 6 Pathway C 11 2 Glucose 1 5 10 12 7 4 8 3 Arrows numbered 4, 8 and 12 can all be (a) H2O (b) FAD+ or FADH2 (c) NADH (d) ATP.

Last Answer : (d) ATP.

Description : Various activities of a project, are shown on bar charts by (A) Vertical lines (B) Horizontal lines (C) Dots (D) Crosses

Last Answer : (B) Horizontal lines