List routine tests to be conducted on 3 phase transformer as per 1S-2026-2011. 

1 Answer

Answer :

Following tests are conducted/carried out on Transformer as per IS 2026 Routine tests of transformer include:-

1. Winding resistance measurement.(Both HV and LV winding ) 2. Measurement of insulation resistance.(Between HV and LV winding, HV and ground/tank, LV and ground/tank) 3. Measurement of voltage ratio/Turns ratio 4. Open circuit test (To determine no load loss, no load current /magnetizing current and shunt parameters of equivalent circuit) 5. Short circuit test (To determine full load losses, impedance voltage/short circuit impedance and series parameters of equivalent circuit.) 6. Polarity test 7. Phasing out test 8. Dielectric test of transformer or High Voltage Test. a. Power Frequency voltage with stand test or separate source voltage withstand test of transformer b. Induced voltage test of transformer. or DVDF (Double voltage double frequency) c. Impulse Voltage withstand test. 9. Vector group test. 10. Tests on on-load tap-changer, where appropriate. 11. To check against leakages through gaskets.

Related questions

Description : The state wise allocation of seats in Lok Sabha is based on the 1971 census. Up to which year does this remain intact? (1) 2031 (2) 2026 (3) 2021 (4) 2011

Last Answer : (2) 2026 Explanation: The state wise allocation of seats in Lok Sabha is based on 1971 census and this remain upto 2026 under article 82.

Description : On which of the following routine tests are conducted ? (a) Oil circuit breakers (b) Air blast circuit breakers (c) Minimum oil circuit breakers (d) All of the above

Last Answer : (d) All of the above

Description : On which of the following routine tests are conducted ?(a) Oil circuit breakers(b) Air blast circuit breakers(c) Minimum oil circuit breakers(d) All of the above

Last Answer : On which of the following routine tests are conducted ?(a) Oil circuit breakers(b) Air blast circuit breakers(c) Minimum oil circuit breakers(d) All of the above

Description : List any eight contamination agents of the transformer oil. 

Last Answer : The insulating oil gets contaminated when the following impurities are present in oil. 1. Presence of dissolved moisture content. 2. Presence of water content. 3. Presence of dissolved gases ... sulpher content 9. Presence of acetones content. 10. Presence of dissolved oil decay products content

Description : Prepare troubleshooting chart for transformer as per IS- 10028-1981 (4 trouble) and Induction motor (4 troubles). 

Last Answer : Troubleshooting chart for I.M. :-  Sr.No Type of fault/abnormal conditions/Troubles Causes Remedies 1 Motor fails to start or not accelerate (Faults in starting supply ... 1.Unequal terminal voltage. 2. Single phase operation 3.Unbalanced voltage Rectify the Cause

Description : Name the tests to be conducted for predetermining the performance of 3-phase induction machine.

Last Answer : (a) No load test (b) Blocked rotor test

Description : State and explain properties of transformer oil.  

Last Answer : Following are the properties of transformer oil:-  1. Dielectric strength :- It should be have a high dielectric strength  2. Specific resistance:- It should be have a high Specific ... be not contain impurities such as sulpher & its compounds to avoid rusting & sludge formation. 

Description : In India, Autonomous Emergency Braking system (AEB) could become mandatory on new cars by________ a) 2020 b) 2024 c) 2022 d) 2026

Last Answer : c) 2022

Description : Which one of the following statements BEST characterises marketing research? A)research is a continuous process, providing a constant flow of information B)research is conducted on a special- ... when routine information is required D)research is the basis for making recurring marketing decisions

Last Answer : B)research is conducted on a special-project basis

Description : List any four internal causes for abnormal operation of electrical equipment’s. 

Last Answer : Internal causes:- 1. Open circuit 2. Short circuit 3. Earth fault 4. Loose connection 5. Deposit of dirt and dust near ventilation passage 6. Low insulation resistance 7. Improper maintenance 8. Poor ... problems 13. Failure of cooling system 14. Excess wear and tear of internal parts 15. Ageing.

Description : Classify the insulating materials as per operating temperature. Give two examples of each type.

Last Answer : Sr.No.  Insulation Classes  Maximum permissible temperature (0C) Insulating Material 1 Class-Y or O  900 Cotton, silk, paper, press board, wood, cellulose-, PVC, VIR. (Cotton, silk, ... adhesive coating.  7 Class- C  Over 1800 Porcelain, ceramics, glass, quartz. 

Description : How direct tests are conducted in circuit breakers?

Last Answer : Using a short circuit generator as the source. Using the power utility system or network as the source.

Description : Pick up the incorrect statement from the following: (A) Concrete for which preliminary tests are conducted, is called controlled concrete (B) Bulking of sand depends upon the fineness of grains (C) Concrete mix 1 : 6 : 12, is used for mass concrete in piers (D) All the above

Last Answer : Answer: Option D

Description : Which of the following correspond to the recommendations of IRC for pavement thickness determination by CBR Method ? 1. CBR tests are to be conducted in-situ 2. Static compression is best adopted 3. The top 50 cm of sub grade ... 1, 2 and 3 (b) 1 and 2 only (c) 2 and 3 only (d) 1 and 3 only

Last Answer : (c) 2 and 3 only

Description : Acceptance tests are normally conducted by the A. Developer B. End usersC. Test team D. Systems engineers

Last Answer : B. End users

Description : Alpha testing is differentiated from Beta testing by A. The location where the tests are conducted. B. The types of test conducted C. The people doing the testing D. The degree to which white box techniques are used

Last Answer : A. The location where the tests are conducted.

Description : Where Portion sample tests(test piece) should be conducted? (i) At desire by RDSO (ii) At Zonal CMT’s organisation or the Flash Butt Welding plant. * (iii) In RDSO campus (iv) As decided by in charge of the plant

Last Answer : At Zonal CMT’s organisation or the Flash Butt Welding plant.

Description : If you won't go for a routine colonoscopy, what other medical tests can you get to see if you're alright in the colon?

Last Answer : Virtual colonoscopy, which might be more effective than a real colonoscopy. You still need to do the GI prep however, and if they see something suspicious, then you need a real one anyway.

Description : As per 1S: 456-2000, minimum grade of concrete in seat water constructions is [ A ] M20 [ B ] M25 [ C ] M30 [ D ] M50

Last Answer : [ C ] M30

Description : In 2011 alone, Google ran roughly ______ A/B tests. A. 5000 B. 6000 C. 7000 D. 8000

Last Answer : C. 7000

Description : Why the open circuit test on a transformer is conducted at rated voltage?

Last Answer : A:The open circuit on a transformer is conducted at a rated voltage because core loss depends upon the voltage. This open circuit test gives only core loss or iron loss of the transformer.

Description : An open-circuit test on a transformer is conducted primarily to measure?

Last Answer : The open-circuit test in a transformer is used to measure

Description : Sumpner's test is conducted on transformer to determine?

Last Answer : Sumpner's test is conducted on transformer to determine temprature.

Last Answer : In a transformer, routine efficiency depends upon load current and power factor of load.

Description : State types of maintenance. Explain each with example. 

Last Answer : Maintenance are classified as below:- 1. Preventive Maintenance (PM) 2. Routine /daily maintenance 3. Periodic maintenance/Time based maintenance (TBM) 4. Predictive maintenance (PDM) 5. ... by the manufacturer. It involves partial or complete dismantling of the equipment/machine and overhaul.

Description : Compare direct and Indirect method of testing.  

Last Answer : Sr No.  Parameter Direct Testing Indirect Testing   1 Nature of loading  The m/c is actually loaded at full load. The m/c is not actually loaded but machine run on N.L. 2 ... 1.O.C. and S.C test on transformer/Alternator / I.M. , 2. Swinburne test on DC machines. 

Description : Explain importance and purpose of earthing. 

Last Answer : Importance and purpose of earthing is as below:- 1. To provide an alternative path for the leakage current to flow towards earth. 2. To save human life from danger of electrical shock due to ... equipment body (frame) below the earth potential in the event of fault from safety point of view. 

Description : Describe any four methods used to reduce earth resistance.  

Last Answer : To reduce earth resistance following steps/methods are necessary: 1. Earth pit of more depth & width- breadth should be made. 2. Use of higher size/cross section of earthing material like ... galvanized. 12. Electrodes should be placed in the earth in the upright vertical position. 

Description : State the methods of Neutral Grounding. State difference between Earthing and grounding. 

Last Answer : Neutral Grounding connections are of three types:  1. Solid earthing 2. Resistance earthing 3. Reactance earthing SR. NO. Earthing Grounding 1 Earthing means connecting the dead part ... earthing provides suitable means for earth fault protecting system.  10

Description : Explain vacuum impregnation method used for Re-varnishing of insulation with neat diagram.

Last Answer : Figure of process of vaccum impregnation:-  Explain the process of vacuum impregnation:- The plant consists of: 1. A large air tight chamber (VIC) i.e. processing or impregnation chamber. 2 ... )curing temperature varies from 90°C to 110°C for 10-20 minutes in some cases one to two hours.

Description : State any eight causes of fire. 

Last Answer : Following are the Causes of electrical Fires:- 1. Overloading on cables/wires/machine causes possibility of fire. 2. Use of too many device plugged into a circuit, causing heated wire & possible a ... & equipment's used in hazards area are not used as per the specification/type of protection.

Description : State the basic requirements of foundation for :(i) Static equipment’s (ii) Rotating equipment’s

Last Answer : Following are the basic requirements of foundation to be considered in designing the machine foundation for :(i) Static equipment's (ii) Rotating equipment's  1. Depth of foundation should be ... it.  11. The dimension of foundation should be proportional to safe bearing capacity of soil.

Description : Describe Effect of misalignment of direct coupled drives.

Last Answer : Following are the effects of misalignment of direct coupled drives:- 1. There will be excess vibrations. 2. Increase in noise level. 3. Increases in friction loss. 4. The shaft will bent. 5. There ... stresses on coupling & shaft. 13. Early wear & tear of both driving & driven machine.

Description : State the methods used to measure insulation resistance and explain Dielectric Absorption method.

Last Answer : There are three types of tests for measuring insulation resistance:  1. Spot test reading or Short Time test  2.Time-resistance test or Dielectric absorption test or Testing methods based on the PI & DAR  3. ... and if value of PI is less than 2 and value of DAR is less than 1.25

Description : State the procedure for developing preventive maintenance schedule. 

Last Answer : Procedure of PM is as below:-  Step 1:- Inspection: What to inspect and how to inspect? Maintenance engineer / team should inspect the plan under working condition. Prepare the check ... :- Check the availability of trained & skilled technician to do maintenance before starting the work.

Description : Describe the factors affecting preventive maintenance schedule. 

Last Answer : Following factors affect the PM schedule:- 1. Non availability of spares & raw material. 2. Non availability of tools, trackless, jacks, fixture required for PM. 3. Non availability of trained & skilled ... the work is held up for certain period. This is also a cause of disturbing a PM schedule.

Description : State any eight safety precautions to be followed while working with an electric installation. 

Last Answer : Wear safety boot and use right tool for the right job

Description : State the objective of testing. Explain the role of BIS (Bureau of Indian Standards) in testing of electrical machines. 

Last Answer : 1. Objective of testing is to finding error/defects in machine/equipment/ product. 2. To confirm whether the results obtain during testing are within tolerance limits specified by BIS / ISS 3. To ... BIS/ISS specified standards. 5. To avoid in convinces & accidents BIS plays important role.  

Description : State any one application of each tool : (i) Earth tester (ii) Megger (iii) Bearing puller (iv) Growler 

Last Answer : i) Earth Tester :- It is used to measure earth resistance.  ii) Megger :- Megger is used to find out (measure) insulation resistance of electrical machine/equipment.  iii) ... is an electrical device used to find out shorted turn faults in armature winding and stator winding of motor.

Description : State any four advantages of preventive maintenance. 

Last Answer : Following are the advantages of Preventive Maintenance:- 1. It increases life of machine/equipment. 2. It prevents premature failure. 3. It keeps the machine in good working condition by reducing wear and ... more expensive than the same job done PM/preplanned (and may take 10 times longer).

Description : State the factors on which severity of electric shock depends. 

Last Answer : The severity of shock depends on following factors.  1. Magnitude voltage of the system.  2. The period or duration for which the area of contact with lives part.  3. It is also depends on ... 200mA  May cause fibration of heart  6 Above -200mA Causes death, severe burns 

Description : The first order gas phase reaction as shown in the bellow figure is conducted isothermally in batch mode. The rate of change of conversion with time is given by (A) dXA /dt = k1 (1 - XA ) 2 (1 + 2XA ) (B) dXA /dt = k1 (1 - XA ... 5XA ) (C) dXA /dt = k1 (1 - XA ) (D) dXA /dt = k1 (1 - XA )/(1 + XA )

Last Answer : (C) dXA /dt = k1 (1 - XA

Description : No-load test on a 3-phase induction motor was conducted at different supply voltage and a plot of input power versus voltage was drawn. This curve was extrapolated to intersect the y-axis. The intersection point ... ) Core loss (B) Stator copper loss (C) Stray load loss (D) Friction and windage loss

Last Answer : No-load test on a 3-phase induction motor was conducted at different supply voltage and a plot of input power versus voltage was drawn. This curve was extrapolated to intersect the y-axis. The intersection point yields Friction and windage loss

Description : List the conditions for parallel operation of three phase transformer.

Last Answer : Conditions for Parallel operation of 3 phase transformer: 1) Voltage ratings of both the transformers must be identical. 2) Percentage / p.u. impedances should be equal in magnitude. 3) X/R ratio of ... between primary & secondary voltages must be same. 6) Phase sequence of both must be same.

Description : for Delta-Star connection of 3-phase transformer: i) Draw the connection diagram ii) List any two advantages of this connection iii) State its area of application. 

Last Answer : Disadvantages: i) In this type of connection, the secondary voltage is not in phase with the primary. Hence it is not possible to operate this connection in parallel with star-star or delta-delta ... iv) As line current is equal to phase current the conductor size of winding should be large. 

Description : Explain about the open and short circuit tests on transformer?

Last Answer : A. Open circuit test (No load test) and short circuit test (full load test) are performed on a transformer to determine (i) Equivalent circuit of transformer (ii) Voltage ... determine copper loss in transformer at full load and parameters of approximate equivalent circuit of transformer.

Description : What are the necessary tests to determine the efficiency, voltage regulation, and temperature rise of winding & insulation of transformer?

Last Answer : 1.Direct loading test 2.Open circuit test 3. Short circuit test 4. Sumpner's or back to back test

Description : Which of the following tests is not done for transformer oil? (A) Flash point and acid value (B) Aniline point (C) Dielectric strength (D) Copper strip corrosion test

Last Answer : (B) Aniline poin

Description : For a traction transformer circuit breaker state: 1) Rated current and rupturing capacity 2) Any two tests it should be capable of withstanding 3) Overall tripping time and relay time.

Last Answer : Ans: 1) Rated current --- 750 A and Rupturing capacity --- 500 MVA  2) Any two tests it should be capable of withstanding --- Breaking test , Reclosing test , Endurance test ( any two )  3) Overall tripping time --- 0.14 sec and Relay time --- 0.04 sec